To note the contents of the Audit Findings report.
AI summaryShropshire Council's Audit & Governance Committee noted the contents of the 2024/25 Audit Findings Report [D]. Final audit queries and a final review remain, audited financial statements must be published by 27 February 2026, and additional external audit costs are projected [2.2] [2.1] [5.2].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
To note the contents of the Audit Findings report.
2.1On 30 September 2024, the Accounts and Audit (Amendment) Regulations 2024 came into force. These regulations required audited financial statements for the year ended 31 March 2025 to be published by the 27 February 2026.
2.2The audit on the Statement of Accounts is substantially complete although there are some final audit queries still being worked through with the external audit team and a final review of the audit is still to be performed.
2.3In order to provide an update on the current audit findings, Grant Thornton have produced an Audit Findings Report. The Audit Findings Report is attached to this report as Appendix 1.
Contact: [email protected] 1 Audit & Governance Committee 27th November 2025 – Shropshire Council Audit Findings Report 2024/25
3.1Members are asked to receive and comment on the Audit Findings Report.
Report 4. Risk Assessment and Opportunities Appraisal
4.1Details of the potential risks affecting the balances and financial health of the Council are detailed within the Statement of Accounts that has been subject to audit. The Audit Findings Report highlights the audit work that has been focussed on the significant risk areas identified for the 2024/25 audit.
5.1Shropshire Council continues to manage unprecedented financial demands and a financial emergency was declared by Cabinet on 10 September 2025. The overall financial position of the Council is set out in the monitoring position presented to Cabinet on a monthly basis. Significant management action has been instigated at all levels of the Council reducing spend to ensure the Council's financial survival. While all reports to Members provide the financial implications of decisions being taken, this may change as officers and/or Portfolio Holders review the overall financial situation and make decisions aligned to financial survivability. All non-essential spend will be stopped and all essential spend challenged. These actions may involve (this is not exhaustive): • scaling down initiatives, • changing the scope of activities, • delaying implementation of agreed plans, or • extending delivery timescales.
5.2The projected external audit fee for 2024/25 is set out in the Audit Findings Report. This has identified that additional costs are being projected over and above the scale fee initially set for 2024/25, however this is subject to agreement by the Public Sector Audit Appointments.
6. Climate Change Appraisal
6.1This report does not directly make decisions on factors related to climate change.
7. Background 7.1. The external audit by Grant Thornton began on 28th July 2025 and was planned to be substantially complete by late November. As outlined in the Audit Findings Report, the audit has progressed well, and there are some limited items where testing is just being finalised.
Contact: [email protected] 2 Audit & Governance Committee 27th November 2025 – Shropshire Council Audit Findings Report 2024/25
8. External Audit Opinion
8.1Grant Thornton are expected to provide an unqualified audit opinion on the 2024/25 Statement of Accounts and therefore should report as follows.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shropshire Council AFR 24-25Appendix 1 | 52 pages | Download |
PDF |
Third line of assurance: External Audit: Shropshire Council Audit Findings Report 2024/25Report | 3 pages | DownloadRead as text |
Follow Audit & Governance Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Minutes of the previous meeting held on the 25 June 2026That the Minutes of the meeting of the Audit & Governance Committee held on the 25 June 2026 be approved as a true re... | Approved | Open |
| 15 Jul 2026 | Second line assurance: Annual Treasury ReportTo approve the actual 2025/26 prudential and treasury indicators in this report. 2. To note the annual treasury manag... | Approved | Open |
| 15 Jul 2026 | Overall assurance: Annual Governance Statement and Code of Corporate Governance 2025/26to note the Draft Annual Governance Statement 2025/26 and Code of Corporate Governance. to request that external audi... | Noted | Open |
| 15 Jul 2026 | Second line assurance: Approval of the Council's Draft Statement of Accounts 2025/26To approve the draft Statement of Accounts. | Approved | Open |
| 15 Jul 2026 | Exclusion of Press and PublicThat in accordance with the provision of Schedule 12A of the Local Government Act 1972, Section 5 of the Local Author... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.