First line assurance: The Lantern Management Update

Noted Finance 2 papers

AI summaryShropshire Council's Audit & Governance Committee noted corrective actions at The Lantern and asked Internal Audit to report progress in June or July. The work covers governance, financial controls and a new property booking system with assurance audits [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAll recommendations complete or in progress [3.1]
MoneyNot stated
What happens nextInternal Audit progress report [D]June or July [D]
Who it affectsThe Lantern and wider portfolio [D]Internal and external bookings [D]

What was decided

The Committee noted the corrective actions already undertaken and planned. Every recommendation is complete or in progress of completion, with assurance audits in place alongside the new booking system. Report 3.1

Internal Audit is to report progress in June or July. The progress should demonstrate better governance and financial control and confirm completion through the new booking system.

The new booking system will provide a common structure and framework for all internal and external bookings across Shropshire Council's entire property portfolio. Report 3.2

Why

The 2024/25 follow up audit identified 21 recommendations. Thirteen were significant and eight required attention. Report P4

The assurance level was UNSATISFACTORY, with no improvement from the previous audit. The report says 95% of recommendations are complete. It also says one recommendation (5%) has been completed as far as practicable. Report P8, 2.4

The audit found weaknesses in financial control, budget monitoring and payroll records. It also raised concerns about the booking system, access management and hirer insurance evidence. Report P6, P15

What happens next

Internal Audit will report progress in June or July, showing improvements in governance and financial control and the completion work delivered through the new booking system.

The officer report also proposes a responsible officer update within six months of the report. It says progress will be reviewed through an update report submitted to the Audit Committee within 6 months. Report 3.2, 9.2

Implications

  • Financial: Shropshire Council says significant management action is required to ensure its financial survival. Where non-essential spend is identified, it will be reduced, and initiatives may be scaled down, changed, delayed or extended. Report 5.1, P21
  • Financial: Weak financial controls, missing reconciliations and posting errors risk income losses or mismanagement. Incomplete payroll records also risk incorrect staff payments. Report P15, P23
  • Financial: The automated system is intended to remove financial control risk. Tighter controls on income processing are an opportunity to improve financial resilience, and call off logs now cover all invoicing. Report P17, P19
  • Legal: Failure to collect evidence of hirer insurance creates financial and legal risk. Not following financial policies may expose the Council to regulatory consequences. Report P6, P25
  • Staffing: The payroll procedure has been reviewed and implemented to remove risk. Resolving staffing and procedural inconsistencies should improve how The Lantern is run. Report P19, P17
  • Risk: The audit identified high financial and operational risks, including ineffective system controls and security concerns over access management. The assurance level remained UNSATISFACTORY with no improvement. Report P15, P6, P8
  • Other: The new booking system provides a common structure and framework for internal and external bookings across the Council's property portfolio. Report 3.2
  • Climate: No climate change or environmental impacts are anticipated from the recommendations. Report 6.1

Who and where

  • Shropshire Council's entire property portfolio Report 3.2
  • People making internal or external property bookings
  • People using The Lantern's library, IT suite, meeting rooms and community hall Report P1
  • Council staff responsible for bookings, invoicing, budgets and payroll Report P6, P19
  • External hirers of Council properties Report P6
  • Audit Committee Report 9.2
  • Council taxpayers if unresolved problems require additional funding Report P25

Timeline

  • 2021/22: The previous audit gave an unsatisfactory assurance level because of weaknesses in financial management, income processing and governance. Report P1
  • 2024/25: The follow up audit found limited progress and identified 21 recommendations. Report P4
  • Aug 2025: The new booking system was implemented. Recommendations 1, 2, 4, 10, 11 and 12 were recorded as complete. Report 7.3, 7.4
  • 27th November 2025: The Committee considered the management update and noted the corrective actions. Report P2
  • within six months of this report: The report proposes a responsible officer update and says progress will be reviewed through an update report submitted to the Audit Committee within 6 months. Report 3.2, 9.2
  • June or July: Internal Audit is directed to report progress on governance and financial control and the new booking system.

Plain English for the jargon

  • First line assurance: The management update on corrective actions and control improvements at The Lantern [3.1] [9.2].
  • The Lantern: A Shrewsbury facility with a community library, IT suite, meeting rooms and community hall [P1].
  • Assurance level: The audit rating, which was UNSATISFACTORY with no improvement from the previous audit [P8].
  • Budget monitoring: Oversight and variance analysis, identified as inadequate [P5].
  • Call off logs: Logs created for all invoicing [P19].
  • Public liability compliance: Collecting evidence of hirers' insurance coverage [P6].
  • Booking system: The new system providing a common framework for internal and external property bookings [3.2].
  • Payroll documentation: Records supporting staff hours and payments, described as incomplete [P6] [P23].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item70

Resolved

a. to note the corrective actions already undertaken and planned with all recommendations either complete or in progress of completion based on the implementation of the new booking system with assurance audits in place. b. that progress be reported by Internal Audit in June or July to demonstrate improvements in governance and financial control to finalise the improvements with the new booking system implemented which would provide the new structure and framework for all internal and external bookings across Shropshire Councils entire portfolio of properties.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit & Governance Committee, 5 pages

Executive summary

Background

The Lantern is a multi-purpose facility in Shrewsbury offering services including a Community Library, IT Suite, Meeting Rooms, and a Community Hall. The previous 2021/22 audit provided an Unsatisfactory assurance level due to several control weaknesses in financial management, income processing, and governance procedures.

Contact: Matt Jordan 01743 252668 1 27th November 2025 – First Line Assurance – The Lantern Management Update

2.2Current Audit Findings (2024/25)

The 2024/25 follow-up audit found limited progress, with 21 recommendations identified: • 13 Significant recommendations • 8 Requires Attention recommendations. • 0 Fundamental or Best Practice recommendations

Key concerns include:

• Income Management: Lack of reconciliations, incorrect ledger postings, and noncompliance with financial procedures. • Budget Monitoring: Inadequate budget oversight and variance analysis. • Payroll & Staff Hours: Lack of clear documentation and potential non-compliance with working time regulations. • System Controls & Cyber Risks: Continued reliance on an ineffective booking system and security concerns over access management. • Public Liability Compliance: Failure to collect evidence of hirers' insurance coverage, posing financial and legal risks.

2.3Assurance Level

Assurance Level: UNSATISFACTORY (No improvement from the previous audit).

2.495% of recommendations are complete from the audit. 2.5. One recommendation (5%) has been completed so far as is reasonably practicable.

Recommendations

3.1That the Audit Committee notes the corrective actions already undertaken and planned. The current situation is all recommendations are either complete or in progress of completion based on the implementation of the new booking system with assurance audits in place.

3.2That responsible officer reports back on progress within six months of this report to demonstrate improvements in governance and financial control to finalise the improvements with the new booking system implemented. The new booking system will provide the new structure and framework for all internal and external bookings across the Shropshire Councils entire portfolio of properties.

Contact: Matt Jordan 01743 252668 2 27th November 2025 – First Line Assurance – The Lantern Management Update

Report 4. Risk Assessment and Opportunities Appraisal

4.1The audit has highlighted high financial and operational risks, particularly in:

• Financial control weaknesses, leading to potential losses or mismanagement of income. • Governance failures in budget monitoring, income tracking • Staff payroll compliance.

4.2Addressing these risks presents an opportunity to:

• Improve financial resilience through tighter controls on income processing. • Enhance operational efficiency by resolving staffing and procedural inconsistencies. • Strengthen compliance with public sector financial governance standards.

4.3Risk table

Risk Mitigation Financial Control Automated system now in place to remove risk Budget Monitoring Call off logs created for all invoicing Staff Payroll Compliance Procedure reviewed and implemented to remove risk

Financial implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Recommendations TableAppendix 1 3 pages Download
PDF
First line assurance: The Lantern Management UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Shropshire

Search all
  1. First line assurance: The Lantern Management UpdateThis decision
  2. First line assurance: Project Management Office Management UpdateNoted
  3. First line assurance: Adult Social Care Outturn Management UpdateAgreed
  4. First line assurance: Internal Control Management UpdateNoted
  5. First Line Assurance: ASC Outturn Update (Period 13)Noted
  6. First line assurance: Deferred Payments Management UpdateNoted

More from Shropshire Audit & Governance Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of the previous meeting held on the 25 June 2026That the Minutes of the meeting of the Audit & Governance Committee held on the 25 June 2026 be approved as a true re... Approved Open
15 Jul 2026 Second line assurance: Annual Treasury ReportTo approve the actual 2025/26 prudential and treasury indicators in this report. 2. To note the annual treasury manag... Approved Open
15 Jul 2026 Overall assurance: Annual Governance Statement and Code of Corporate Governance 2025/26to note the Draft Annual Governance Statement 2025/26 and Code of Corporate Governance. to request that external audi... Noted Open
15 Jul 2026 Second line assurance: Approval of the Council's Draft Statement of Accounts 2025/26To approve the draft Statement of Accounts. Approved Open
15 Jul 2026 Exclusion of Press and PublicThat in accordance with the provision of Schedule 12A of the Local Government Act 1972, Section 5 of the Local Author... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies