North West Relief Road

Decided Committee 1 paper

AI summaryShropshire Council formally cancels the North West Relief Road, with the S151 officer asked to adjust capital accounts after around £32m of sunk costs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedDfT funded road project formally cancelled after pause since June 2025
MoneyAbout £32m sunk costs
What happens nextCapital Programme adjustmentsS151 officer to make accounting transactions and report to external auditors
Who it affectsNorth west Shropshire transport schemeProject cancelled on affordability grounds during council financial emergency

What was decided

The North West Relief Road, a DfT funded project, is formally cancelled. Report 3.1

The S151 officer is asked to make appropriate Capital Programme and accounting adjustments. Report 3.2

The cancellation is recommended on grounds of affordability, given sharp cost rises since 2018 and the council's financial emergency. Report 4.2, 4.6, 6.1

Why

The estimated cost has risen very significantly since 2018, and the council cannot fund the shortfall locally. Report 4.1, 6.1, P21

Attempts to increase DfT grant funding beyond the original agreement to match the higher costs have been unsuccessful. Report 6.1, P18

The project has been paused since June 2025 to stop further costs while its future was considered, and a financial emergency was declared by Cabinet on 10 September 2025. Report 4.1, 4.6, 6.2

What happens next

The S151 officer will put accounting transactions into the statement of accounts for sunk costs of about £32m, with some possibly reattributed to neighbouring schemes including the Oxon Link Road. Report 4.3

The council will hold dialogue with the Department for Transport and other organisations that supported the early phases of the project. Report 4.4

Adjustments will reflect the government's response to the council's bid for Exceptional Financial Support, and will be subject to external audit. Report 4.5

The money

  • approximately £32m costs previously sunk into the NWRR project up to the date it was paused, set out in Appendix 1 Report 4.3

Options considered

  • Chosen: Cancel the NWRR project. Costs have risen beyond what the council and DfT grant can fund, given the declared financial emergency Report 3.1, 4.1, 4.2, 6.1, 6.3

Implications

  • Financial: Sunk costs of about £32m will need to be accounted for, with a demand on borrowing if not reattributed to other schemes. Report 4.1, 4.3
  • Legal: Accounting adjustments must comply with capital accounting requirements and will be scrutinised by external auditors. Report 4.5
  • Climate: The residual carbon impact of about 55,904 tCO2e will not be realised, and the council's existing carbon baseline is unaffected. Report 5.3, 5.6
  • Financial: Decisions and accounting are linked to the council's bid for Exceptional Financial Support from government. Report 4.5
  • Risk: The council will need to engage with DfT and other funders about the early phases of the project. Report 4.4
  • Other: Some sunk costs may be reattributed to neighbouring road schemes, including the Oxon Link Road. Report 4.3

Who and where

  • Shropshire Council's general fund and capital programme Report 4.1, 4.3
  • Department for Transport and other early-phase project funders Report 4.4
  • Neighbouring road schemes including the Oxon Link Road Report 4.3
  • Local members: Ed Potter (Loton), Jon Tandy (Bicton Heath), Rhys Gratton (Harlescott), Ben Jephcott (Bagley), Alex Wagner (Quarry and Coton Hill), Rob Wilson (Copthorne), Brendan Mallon (Tern) Report P25

Timeline

  • Since 2018: Estimated project cost has increased very significantly Report 4.1
  • June 2025: Project paused to prevent further costs while future is considered Report 4.1, 6.2
  • 10 September 2025: Cabinet declared a financial emergency Report 4.6
  • 26 February 2026: Council formally cancels the NWRR and asks S151 officer to make accounting adjustments Report 3.1, 3.2

Plain English for the jargon

  • NWRR: North West Relief Road, the DfT funded road project considered in this report
  • S151 officer: The council's chief finance officer, designated under section 151 of the Local Government Act 1972, responsible for proper administration of financial affairs
  • DfT: Department for Transport
  • tCO2e: Tonnes of carbon dioxide equivalent, a standard unit for comparing greenhouse gas emissions
  • Exceptional Financial Support: A form of central government support for councils facing severe funding pressures
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item80

Resolved

RESOLVED A. That the North West Relief Road (DfT funded project) is formally cancelled. B. That the S151 officer be requested to make appropriate Capital Programme and accounting adjustments following the decision in paragraph A.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Council

Recommendations

3.1That the North West Relief Road (DfT funded project) is formally cancelled.

3.2To request that the S151 officer make appropriate Capital Programme and accounting adjustments following the decision in paragraph 3.1.

Report 4. Financial Implications

4.1It is noted that the estimated cost of the project has increased very significantly since 2018. The full costs for the project would fall on the Council and principally would become a demand on borrowing with the consequences for the Council’s general fund budget. It is also noted that the project has been paused since June 2025 and that DfT have been made aware of the need for Council to confirm any decision to cancel it.

4.2This report is therefore recommending that the NWRR project be cancelled on the basis of affordability.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
North West Relief RoadReport 256 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

67 of 74 attended
DB
Duncan BorrowmanChairman, present
GG
Gary GrovesVice-Chair, present
HK
Heather KiddLeader, present
AW
Alex WagnerDeputy Leader, present
SA
Sho AbdulCommittee Member, present
CB
Caroline BagnallCommittee Member, present
EB
Elizabeth BarkerCommittee Member, present
BB
Bernie BentickCommittee Member, present
NB
Neil BentleyCommittee Member, present
EB
Ed BirdCommittee Member, present
JB
Jeremy BlandfordCommittee Member, present
AB
Andy BoddingtonCommittee Member, present

All 74 on the meeting page

On this subject at Shropshire

Search all
  1. North West Relief RoadThis decision
  2. Shrewsbury North West Relief Road - Compulsory Purchase OrderApproved
  3. Proposed Dwelling North West Of Pleasant View Rowley Shropshire (24/01047/REM)Decided
  4. Shrewsbury North West Relief Road – Funding DelegationApproved
  5. Land North West of The Old Smithy, Longslow, Market Drayton, Shropshire, TF9 3QY (23/03515/OUT)Decided
  6. Land North of Whittington Road, Oswestry (23/00225/FUL)Agreed

More from Shropshire Council

All decisions
MeetingDecisionOutcome
14 May 2026 Election of ChairmanRESOLVED that Councillor Duncan Barrowman be elected as Chairman of Shropshire Council to hold office until the Annua... Decided Open
14 May 2026 Appointment of Vice ChairmanRESOLVED that Councillor Gary Groves be appointed as Vice-Chairman of Shropshire Council to hold office until the Ann... Decided Open
14 May 2026 MinutesThat the of the meeting held on 26 February 2026, as circulated with the agenda papers, be approved and signed as a c... Approved Open
14 May 2026 Scrutiny Reorganisation/Housing Supervisory BoardThat the Housing Supervisory Board be removed from the Constitution. 2. That the Scrutiny Committees and their terms ... Approved Open
14 May 2026 Constitution of Committees and Allocation of Seats to Political GroupsThat the Council confirms the constitution of committees and the allocation of seats to each of the political groups ... Decided Open