External Audit Plan 2025/26

Approved Committee 2 papers

AI summaryWest Mercia Energy Joint Committee approved WR Partners' draft external audit plan for 2025/26 at a fee of £15,950, a 3% rise on 2024/25.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWR Partners commissioned to audit 2025/26 accounts
Money£15,950Audit fee for 2025/26, up £450 (3%) on 2024/25
What happens nextSeptember Joint CommitteeWR Partners to complete main audit work in July
Who it affectsWest Mercia Energy accountsYear ended 31 March 2026

What was decided

Approved the draft audit plan for 2025/26 as presented by WR Partners at Appendix 1. Report 2.1

Approved commissioning WR Partners to undertake the audit in accordance with the plan. Report 2.2

Why

To provide the Joint Committee with continued assurance regarding stewardship of funds. Report 1.1, 5.1

The Joint Committee has previously chosen to maintain an annual external audit even though it is no longer legally required. Report 5.1, P15

What happens next

WR Partners will conduct main audit work on the 2025/26 accounts in July. Report 5.3

WR Partners will bring their report to the September Joint Committee. Report 5.3

The money

  • £15,950 Fee for the 2025/26 audit Report 4.1
  • £450 (3%) Rise against the 2024/25 audit fee Report 4.1
  • £15,500 Fee for the 2024/25 audit Report 4.1

Implications

  • Legal: Recommendations are compatible with the Human Rights Act 1998. Report 3.1
  • Equalities: No direct environmental, equalities or climate change consequences arise from this report. Report 3.2

Who and where

  • West Mercia Energy Joint Committee Report 1.1, 5.1
  • Member councils of West Mercia Energy, including Herefordshire Council Report P16

Timeline

  • 1st April 2015: Local Audit and Accountability Act 2014 implemented; joint committees no longer required to have accounts separately audited. Report 5.1, P15
  • 28 September 2015: Joint Committee agreed to continue with an annual external audit for assurance. Report 5.1, P15
  • July (year ending 31 March 2026): WR Partners to conduct main audit work on the WME accounts. Report 5.3, P17
  • September (year ending 31 March 2026): WR Partners to bring their audit report to the Joint Committee. Report 5.3

Plain English for the jargon

  • West Mercia Energy (WME): A joint committee of local authorities whose accounts are being audited.
  • WR Partners: External auditor appointed to carry out the 2025/26 audit.
  • Materiality levels: Thresholds set by the auditor for the significance of misstatements, as set out in the Service Plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

That the Joint Committee: 1. approve the draft audit plan for 2025/26 as presented by WR Partners attached at Appendix 1. 2. approve the commissioning of WR Partners to undertake the audit in accordance with the audit plan.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to West Mercia Energy Joint Committee

Summary

1.1It has been previously agreed for the Joint Committee to continue with an external audit to provide the Joint Committee the necessary continued assurance regarding stewardship of funds.

1.2This report provides the Joint Committee with the proposed external audit plan for 2025/26 for consideration and approval.

Recommendations

It is recommended that the Joint Committee:

2.1approve the draft audit plan for 2025/26 as presented by WR Partners attached at Appendix 1.

2.2approve the commissioning of WR Partners to undertake the audit in accordance with the audit plan.

REPORT

3. Risk Assessment and Opportunities Appraisal

3.1The recommendations contained in this report are compatible with the provisions of the Human Rights Act 1998.

3.2There are no direct environmental, equalities or climate change consequences arising from this report. 3.3 WR Partners’ audit work was conducted in accordance with the International Standard on Auditing (UK).

Financial implications

4.1The fee for the 2025/26 audit is £15,950, a £450 (3%) rise against the fee for 2024/25 of £15,500.

Background

5.1At the Joint Committee of 28 September 2015, it was highlighted that from 1st April 2015 implementation of the Local Audit and Accountability Act 2014 meant that joint committees are no longer required to have their accounts separately prepared and audited. At this Joint Committee it was agreed to continue with an annual external audit in order to provide the Joint Committee with the necessary continued assurance regarding stewardship of funds.

5.3WR Partners will conduct their main audit work on the WME accounts for 2025/26 in July and will bring their report to the September Joint Committee.

5.4The attached WR Partners Service Plan sets out the scope of the audit to be undertaken, identifies risks and audit responses to these and outlines materiality levels.

List of Background Papers (This MUST be completed for all reports, but does not include items containing exempt or confidential information)

Joint Committee 28th September 2015 – Local Audit and Accountability Act

Member Councillor P Stoddart of Herefordshire Council (Chair of the Joint Committee)

Appendices Appendix 1 – WR Partners Audit Service Plan for West Mercia Energy (year ended 31 March 2026)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Audit Plan 2025/26Report 87 KB DownloadRead as text
PDF
Item 6: Appendix 1: Audit Service Plan 2026Appendix 498 KB Download

At this meeting

Whole meeting

Who was there

4 of 8 attended
PS
Peter StoddartChairman, present
GB
Graham BiggsCommittee Member, apologies
RE
Roger EvansCommittee Member, present
RW
Rob WilsonCommittee Member, apologies
ZH
Zona HanningtonVice Chairman, present
OV
Ollie VickersCommittee Member, present
IC
Ian CresswellCommittee Member, apologies
RW
Rob WhartonCommittee Member, apologies

On this subject at Shropshire

Search all
  1. External Audit Plan 2025/26This decision
  2. External Audit - Audit findings report 2025/26Decided
  3. Third line assurance: External Audit, Shropshire Council and Shropshire County Pension Fund Audit PlansNoted
  4. Third line of assurance: External Audit: Shropshire Council Audit Findings Report 2024/25Noted
  5. External Audit - Audit findings report 2024/25Decided
  6. Third Line Assurance: External Audit Letter on Financial Position Based on Period 4Noted

More from Shropshire West Mercia Energy Joint Committee

All decisions
MeetingDecisionOutcome
25 Sep 2026 Statement of Accounts 2025/26 and Annual Governance Statement 2025/26That the finalised Statement of Accounts 2025/26 be signed by the Chairman and the Treasurer. That the Annual Governa... Noted Open
25 Sep 2026 External Audit - Audit findings report 2025/26That the contents of the audit findings report presented by WR Partners be considered and endorsed. Decided Open
25 Sep 2026 Distribution of SurplusThat the retention of accumulated surplus of £1.594 million be approved. That the distribution of accumulated surplus... Approved Open
25 Sep 2026 Risk Management UpdateThat the medium risks presented be considered and endorsed. Decided Open
25 Sep 2026 Anti-Slavery and Human Trafficking PolicyThat the WME Anti-Slavery and Human Trafficking Policy be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies