Green & Built Environment Scrutiny Panel approved this item on Monday 26 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved – (a) That the Panel notes the outstanding matters on Langleywood estate and the progress on the adoption of open spaces. (b) That a report on unadopted new roads be brought to the next meeting of the Panel. (c) That the Officer will provide contact details for the Developer’s resident help line for Councillor Plimmer .
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
Report to Green & Built Environment Scrutiny Panel
Purpose of report
To provide information in response to a request from the September 2006 Cabinet regarding adoption of roads. Progress on open space adoption has also been included.
Recommendation
The Panel is requested to resolve that the report be noted and consider whether it wishes Officers to take any further action.
3. Key Priorities – Taking Pride in Slough and Making a Difference to Communities and our Environment
Priority 1 – Creating safe, environmentally friendly and sustainable neighbourhoods.
1.1Deliver cleaner and safer neighbourhoods. 1.2 Adopt a green and sustainable approach to managing and developing the environment. 1.3 Protect and enhance public health and well being 1.4 Improve transport Priority 2 – Improving lives for those in need and creating thriving communities.
2.3Provide affordable, decent and safe homes
Priority 4 – Ensuring excellence in customer services
4.1Deliver excellent customer focused services in an excellent customer environment 4.2 Engage, listen and empower communities. 4.3 Deliver better integrated services through Slough Focus and other partnerships. 4.4 Deliver excellent internal and external relations.
4. Other Implications
(a) Financial
There are no direct financial implications arising from the report itself.
(b) Human Rights and other Legal Implications
There are no direct implications arising from the report itself. In terms of Human Rights Act, individuals and property owners were afforded the opportunity to comment via the planning application process.
5 Adoption Status of Minor Access Roads- Ditton Park
5.1This site has two section 38 agreements. The majority of the site has been developed by Taylor Woodrow. Bellway Homes developed Dalton Green and Dewar Spur only.
5.2The adoption procedure is lengthy and dependant on a combination of factors including the adoption of the sewers within the access roads by Thames Water, repairing of street lighting faults and completion of minor remedial work.
5.3Dalton Green and Dewar Spur have been satisfactorily constructed and will be adopted once Thames Water adopt the sewers beneath the respective access roads. The agreement to adopt the sewers is for the development as a whole therefore Bellway Homes are currently having the road adoption delayed by the non adoption of the sewers by Thames Water.
5.4A comprehensive list of required remedial works was sent by the Highways Section to Taylor Woodrow on 21 August 2006. Taylor Woodrow have agreed to the works contained within the list and have completed around 50% with the remaining 50% expected to be completed within the next 2-3 months.
5.5Thames Water are yet to adopt the sewers on the development. This has the potential to delay the adoption of the associated access roads. Taylor Woodrow have indicated that there is not a problem with the adoption of the sewers and expect all remedial works to be completed within the next 2-3 months. However once Thames Water are happy with the remedial works a further 12 months maintenance period will be required. This will delay the adoption of the access roads by 12 months. 5.6 Around 6 of the highway soakaways (in the north west corner of the site) contain standing water, even in dry conditions. The Highways Section has asked Taylor Woodrow to set up a site meeting with the Environmental Agency confirming that there are no problems with these soakaways.
5.7Once the remaining remedial works are completed, the sewers are adopted by Thames Water and the Environment Agency approve the questioned soakaways, the Council will be able to adopt the access roads within this development.
6 Open Spaces
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Drugs and Alcohol Action Team UpdateResolved – That the current position be noted and welcomed and that a further report be submitted to the Panel in six...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.