Resolved
Resolved – (a) That the report be noted and that Weekes Drive and Mina Avenue be added to carriageway treatment schedule. (b) That Ennerdale Crescent, Cherry Avenue, Downs Road and Laurel Avenue be added to the footway treatment schedule.
Green & Built Environment Scrutiny Panel noted this item on Monday 26 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – (a) That the report be noted and that Weekes Drive and Mina Avenue be added to carriageway treatment schedule. (b) That Ennerdale Crescent, Cherry Avenue, Downs Road and Laurel Avenue be added to the footway treatment schedule.
To inform the Panel of the proposed programme of works to be carried out by the Council’s highway engineering team in 2007/2008.
2. Recommendation(s)/Proposed Action
The Committee is requested to note the report.
3. Key Priorities – Taking Pride in Slough and Making a Difference to Communities and our Environment
Priority 1 – Creating safe, environmentally friendly and sustainable neighbourhoods.
Aims 1.1 Deliver cleaner and safer neighbourhoods. 1.2 Adopt a green and sustainable approach to managing and developing the environment. 1.3 Protect and enhance public health and well being 1.4 Improve transport
4. Other Implications
(a) Financial
Initiatives set out in the report are funded from within existing budgets. . (b) Human Rights Act and other Legal Implications
There are no Human Rights Act Implications. 5. Supporting Information
5.1The highway engineering team manage the maintenance of the Council’s transport assets across the Borough.
5.2This report lists the proposed major works planned over the next 12 months. It does not include minor surfacing works, patching and routine maintenance works that will be ongoing throughout the year.
5.3Appendix A details the highway carriageway resurfacing and reconstruction works. Appendix B shows those roads that are deemed to be a high priority but for which there is no funding available this year. The list is in alphabetical order. This programme is determined by taking into account a number of factors, detailed below.
Budget Allocation
5.4Separate budgets are allocated to street lighting replacement (capital only),carriageway and footway maintenance (capital and revenue) and road and land drainage (capital only)
Street Lighting Carriageway / Footway Drainage
2007/2008 £551,000 £1,400,000 £167,000
Carriageway / Footway Programme Compilation
5.5Each year an independent team, using a number of different survey methods, tests a proportion of roads within the Borough. These include machine-based surveys (SCANNER, SCRIM and Deflectograph) as well as visual surveys carried out to a nationally agreed standard (CVI).
5.6Data from these surveys is used within a computerised analysis package – UKPMS – that prioritises the order of repair for sections of the network.
5.7In November 2006 Councillors were written to, asking for suggestions of roads and footways they felt were high priority in terms of needing repair.
5.8Throughout the year numerous requests for resurfacing from individuals and organisations are received.
5.9Feedback from consultations is taken into account when collating the list of roads for repair.
Local Inspections Feedback
5.10All roads are inspected regularly by the Council’s highway inspectors in order to ensure they are maintained in a safe condition. The Inspector’s assessment of the overall condition of the road is taken into account when collating the list of roads to repair. Street Lighting Programme Compilation
5.11Council records show where the oldest and most at risk columns are in the Borough. These streets are given priority in terms of column replacement. Footpaths where lighting is identified as poor are also prioritised. Streets with older columns tend to be the least well lit as older lighting standards allowed for poorer lights and fewer columns.
Drainage Improvement Programme Compilation
5.12The capital drainage programme is split into three distinct areas: - carriers, connections and soak-aways.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway App AAppendix | 11 KB | Download |
PDF |
Highway App BAppendix | 10 KB | Download |
PDF |
Highway App CAppendix | 10 KB | Download |
PDF |
Highway App DAppendix | 10 KB | Download |
PDF |
Highway App EAppendix | 11 KB | Download |
PDF |
Highway Engineering-Programme of WorksReport | 33 KB | DownloadRead as text |
Follow Green & Built Environment Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2008 | Thames Water- activity to reduce flooding in SloughResolved - That the Panel thanks Thames Water for the presentation and looks forward to future co-operation to resolv... | Decided | Open |
| 24 Jun 2008 | Installation of Burglar Alarms in Council Housing StockResolved - That the Panel urges People First to reapply for a grant for the provision of burglar alarms in Council ho... | Decided | Open |
| 24 Jun 2008 | Combating CounterfeitingResolved - That the report be noted. | Noted | Open |
| 24 Jun 2008 | Doorstep Crime InitiativesResolved - That the report be noted. | Noted | Open |
| 26 Mar 2008 | Drugs and Alcohol Action Team UpdateResolved – That the current position be noted and welcomed and that a further report be submitted to the Panel in six... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.