Resolved
Resolved - That the report be noted.
Green & Built Environment Scrutiny Panel noted this item on Tuesday 4 September 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the report be noted.
This report describes some of the efforts being made by the Council to reduce energy usage in relation to lighting roads and footpaths.
2. Recommendation(s)/Proposed Action
The Panel is requested to note the report.
3. Key Priorities – Taking Pride in Slough and Making a Difference to Communities and our Environment
Priority 1 – Creating safe, environmentally friendly and sustainable neighbourhoods.
Aims 1.1 Deliver cleaner and safer neighbourhoods. 1.2 Adopt a green and sustainable approach to managing and developing the environment. 1.3 Protect and enhance public health and well being 1.4 Improve transport
4. Other Implications
(a) Financial
Initiatives set out in the report are funded from within existing budgets.
(b) Human Rights Act and other Legal Implications
There are no Human Rights Act Implications. 5. Supporting Information
Benefits of Well Lit Streets
5.1The Council manages a stock of approximately 10,000 street lights and 3,000 illuminated signs and bollards. These provide an invaluable service in terms of road safety, crime prevention and in reducing the fear of crime. The public have come to expect urban areas in the UK to be well lit at night and CCTV relies on well lit streets to work effectively. In addition the government sets standards for illumination of certain road signs and traffic islands.
Environmental Cost
5.2Street lights on average burn for 4000 hours per year and have an average power consumption of approximately 70watts. This amounts to 2,800,000kWh per year. Each 1 kWh produces an emission of 340 grams of CO2 and so the streetlights in Slough are responsible for the emission of 952 tons of CO2 each year – more than 250 times the amount a domestic property produces.
Financial Costs
5.3Overall the Council’s energy bill for street lights and illuminated signs and bollards is approximately £500,000 per year. This figure combined with the general increase in concern about the environmental impact of energy use has increased the need for the highways team to look into ways to make all highway lighting more energy efficient. Clearly a balance needs to be struck between the demands of local highway users and the cost and environmental impact of providing for those needs.
Lighting Programme
5.4In 2006 the Council approved an increased capital programme of replacement of street lights across the Borough. This money (£2million over 4 years) is being used to replace and improve many of the street lights across the Borough that have surpassed their design life and are now in a poor state of repair. In doing this the Council implements lighting schemes that provide a better quality of light, meeting the demands of local residents.
Energy Saving Initiatives
5.5The following table lists some of the initiatives the Council is taking to reduce the energy used to lights streets across the Borough. Energy Saving Initiative Status Notes - For Notes - Against Turn Off Lights May be trialled in In a very limited number of areas it is In residential and business areas the selected areas proposed to trial switching off lights likely impact on crime and fear of crime between 2m and 5am. It is likely that this will prevent this being implemented will be in some parks areas only. Some additional costs will be incurred upgrading equipment in order that lights can be turned on and off at specific times.
Dim lights To be trialled Lights on traffic through routes (mostly ‘A’ Potential for road safety to suffer. roads) will be reduced in brightness No lights in the Borough are currently between 2am and 5am where traffic flows equipped to be dimmed automatically. are greatly reduced. This will be There is a cost to upgrade lights so as monitored to assess the impact on road they can be dimmed. safety.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Energy Saving Initiatives in Street LightingReport | 85 KB | DownloadRead as text |
Follow Green & Built Environment Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2008 | Thames Water- activity to reduce flooding in SloughResolved - That the Panel thanks Thames Water for the presentation and looks forward to future co-operation to resolv... | Decided | Open |
| 24 Jun 2008 | Installation of Burglar Alarms in Council Housing StockResolved - That the Panel urges People First to reapply for a grant for the provision of burglar alarms in Council ho... | Decided | Open |
| 24 Jun 2008 | Combating CounterfeitingResolved - That the report be noted. | Noted | Open |
| 24 Jun 2008 | Doorstep Crime InitiativesResolved - That the report be noted. | Noted | Open |
| 26 Mar 2008 | Drugs and Alcohol Action Team UpdateResolved – That the current position be noted and welcomed and that a further report be submitted to the Panel in six... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.