Resolved
Resolved- (a) That additional columns be provided for consideration by the Overview and Scrutiny Committee showing other costed options, including a weekly collection of recyclables. (b) That Cabinet should consider these further options.
Green & Built Environment Scrutiny Panel decided this item on Tuesday 4 September 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved- (a) That additional columns be provided for consideration by the Overview and Scrutiny Committee showing other costed options, including a weekly collection of recyclables. (b) That Cabinet should consider these further options.
To inform members of the outcomes of the work carried out by White Young Green and WRAP regarding the predicted performance and cost of various waste and recycling collection options in Slough.
2.0Recommendation(s)/Proposed Action
2.1The Scrutiny Panel is requested to note the content of the report and to make recommendations to Cabinet in respect of preferred options outlined in Appendices 1 and 2 that should be considered for public consultation.
3.0Key Priorities – Taking Pride in Slough and Making a Difference to Communities and our Environment
Priority 1: Creating safe, environmentally friendly and sustainable neighbourhoods.
Recycling services contribute to the above corporate priority and towards the aims of:
1.1Delivering cleaner and safer neighbourhoods: Promotion of recycling and communicating that discarded waste and litter is a missed recycling opportunity are key to improving cleanliness. There are well established links between environmental conditions and crime, and fear of crime.
1.2Adopt a green and sustainable approach to managing and developing the environment: Sustainable waste management and the provision of a range of convenient recycling opportunities is an essential part of delivering this aim and managing non-renewable resources. 4.0 Other Implications
(a) Financial
Approximate gross costs for the various options are shown in appendix 1. The options are described in more detail in appendix 2. If members decide to adopt new arrangements for refuse collection and recycling on the basis of the options presented in this report, additional capital and revenue expenditure required will have to allocated as part of the 2008/9 three year budget setting process, and an option appraisal will be submitted to assist with deliberations. All options, with the exception of Option 1 will require an additional £1 million capital for purchase of bins. Options 4 and 6 also require additional capital of £360-£400k for kitchen waste containers. A further expansion of the green waste scheme borough wide would incur an additional capital cost £150k for the provision of 7000 more bins.
(b) Human Rights Act and other Legal Implications
There are no legal or direct Human Rights Act implications for the proposed action.
5.0Supporting Information
5.1Increasing Slough’s Recycling Rate
Good recycling performance is important to conserve energy and material resources, reduce the borough's carbon footprint, combat climate change and to reduce waste being landfilled.
5.2Timetable for the Introduction of Plastics Recycling and Progression of the Municipal Waste Management Strategy
5.21Unavoidable budget pressures due to wider funding issues faced by the Council, and the need to review collection policies in a changing waste management environment have necessitated a delay in changing kerbside recycling collections to allow plastic bottles to be included. This has created a window of opportunity allowing the council to look at and consult on long term collection strategies to make sure that collection services are properly integrated and that they work to deliver the next stage of the Council’s Municipal Waste Management Strategy.
5.22A review of the Council’s Municipal Waste Management Strategy (March 2002) has been undertaken to establish progress to date and to determine some options for the next steps to be taken in waste management and collection. The Council’s Municipal Waste Management Strategy 2002 outlines the development of recycling in Slough with progress from Option 3 to Option 5 identified in the report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Refuse and Recycling Options AppraisalReport | 121 KB | DownloadRead as text |
Follow Green & Built Environment Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2008 | Thames Water- activity to reduce flooding in SloughResolved - That the Panel thanks Thames Water for the presentation and looks forward to future co-operation to resolv... | Decided | Open |
| 24 Jun 2008 | Installation of Burglar Alarms in Council Housing StockResolved - That the Panel urges People First to reapply for a grant for the provision of burglar alarms in Council ho... | Decided | Open |
| 24 Jun 2008 | Combating CounterfeitingResolved - That the report be noted. | Noted | Open |
| 24 Jun 2008 | Doorstep Crime InitiativesResolved - That the report be noted. | Noted | Open |
| 26 Mar 2008 | Drugs and Alcohol Action Team UpdateResolved – That the current position be noted and welcomed and that a further report be submitted to the Panel in six... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.