CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Slough Borough Council
Audit and Risk Committee, Thursday 8 November 2012 at 6.30pm

Internal Audit Progress Report

Noted Finance 1 paper

Audit and Risk Committee noted this item on Thursday 8 November 2012. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

Resolved – (a) That the Internal Audit Progress Report be noted. (b) That the Chair would meet the Head of Internal Audit prior to the next meeting to discuss progress.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Risk Committee

Slough Borough Council

Internal Audit Progress Report Audit and Risk Committee Meeting: 8 November 2012 Introduction th The internal audit plan for 2012/13 was approved by the Audit and Risk Committee on the 5 March 2012. This report provides an update on progress against that plan and summarises the results of our work to date. Since the last Audit and Risk Committee held in September 2012 the following audit reports, relating to the 2012/13 plans have been finalised: • Penn Wood School (14.12/13); and • Business Rates (25.12/13) A summary of the key issues contained within these report and the high priority recommendations made is detailed in the report below. KEY ISSUES Of the 13 RSM Tenon audit reports issued to management in respect of the 2011/12 Internal Audit plan, three of these still remain in draft. (Note – RSM Tenon provided the IA service for Quarter 4 of 2011/12 only). Of the 33 reports which have been issued to management in respect of the 2012/13 Internal Audit plan, 20 of these still remain as draft reports. Of these 20, 12 of these have been outstanding for more than 30 working days, with the average time that draft reports remain outstanding being 35 days. Whilst management assurance has been provided in the audit debrief meetings that the weaknesses identified as part of these audits will be addressed, in the absence of a completed action plan, assurance cannot be provided over the time-frame for the completion of these, or whether suitable priority has been given to addressing the issues raised. Of the 33 reports issued to the Council to date for the current financial year, the breakdown with regards to the levels of assurance provided, is as follows (20 of these reports remain in draft and are subject to management agreement / responses received from management):

Audit opinions Green Amber / Amber / Red Advisory Total Green Red Assurance levels 6 7 11 8 1 33 2012/13 to date

The breakdown in the type of recommendations for the year to date is highlighted below:

1 Recommendation grade Total High Medium Low Other

Recommendations raised 2012/13 – to 35 96 69 7 177 date

Of the 32 reports issued for the current year to date where a formal opinion has been provided, 8 of these have resulted in a red opinion (please note six of the eight remain in draft at this stage). Whilst four of the red opinions relate to audits of schools, we have issued red opinions in respect of the following areas relating to the Councils control framework: • Declaration of Interests (Final) • Business Rates (Final) • Contract Management (Draft) • Contract Management – Block Nursing Contracts (Draft) It is therefore imperative that actions to address the weaknesses identified within these reports are undertaken on a timely basis to ensure that these systems can operate effectively in the future. Failure to do so may impact on our ability to provide an unqualified Head of Internal Audit Opinion for the year, which may also have implications for the Annual Governance Statement. As part of our audit follow up process we will undertake a detailed follow up review in respect of all of these audits to provide assurance regarding the extent to which previous recommendations have been implemented. Other Matters Planning and Liaison:

Monthly meetings have been arranged with the Interim Assistant Director, Finance. We have also attended the most recent meeting of the Risk Management Group and provided guidance on the proposed content of the Risk Management Policy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress ReportReport 208 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 7 attended
MN
Councillor Mohammed NazirChair, present
FA
Councillor Frank AbeCommittee Member, absent
PB
Councillor Preston BrookerCommittee Member, present
NC
Councillor Nimrit ChohanCommittee Member, absent
AD
Councillor Arvind DhaliwalCommittee Member, present
AK
Councillor Antreev K. DhillonCommittee Member, present
AK
Ajay KwatraCommittee Member, apologies

On this subject at Slough

Search all
  1. Internal Audit Progress ReportThis decision
  2. Internal Audit Plan and Charter 2026/27Approved
  3. Internal Audit Mid-Year Progress ReportNoted
  4. Internal Audit Mid-Year Progress ReportNoted
  5. Finance and Commercial Internal Audit Recommendations UpdateNoted
  6. Digital, Data and Technology Internal Audit Recommendations UpdateNoted

More from Slough Audit and Risk Committee

All decisions
MeetingDecisionOutcome
12 Mar 2015 Minutes of the last Meeting held on 11 December 2014Resolved – That the minutes of the meeting held on 11 th December 2014 be approved as a correct record. Approved Open
12 Mar 2015 Audit and Risk Management Update: Quarter 3 2014/15Resolved – (a) That the Quarter 2 Management Update be noted. (b) That the protocol for internal audit procedures for... Noted Open
12 Mar 2015 Internal Audit Strategy 2015/16Resolved – That the Internal Audit Strategy 2013/14 to 2015/16, including the annual plan for 2015/16, be approved. Approved Open
12 Mar 2015 External Audit Plan 2014/15 and 2015/16Resolved – (a) That the External Audit Plan for the year ending 31 March 2015 be approved. (b) That the External Audi... Approved Open
12 Mar 2015 Members Attendance RecordResolved – That the Members Attendance Record be noted. Noted Open