Slough Borough Council
Audit and Corporate Governance Committee, Wednesday 12 November 2025 at 6.30pm

Internal Audit Mid-Year Progress Report

Noted Finance 5 papers

AI summarySlough's Audit Committee noted a 'partial assurance' audit of sickness absence management, which found only 17% of return-to-work meetings were recorded on the Agresso system, with nine management actions to be implemented by March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInternal audit gave partial assurance on sickness absence management
MoneyNot stated
What happens nextBy March 2026Management actions to be implemented, most by October or November 2025
Who it affectsLine managers, HR, payrollAll directorates, particularly Customer Services Centre practice cited as good

What was decided

The Committee noted the internal audits completed since the last meeting on 10 September, including the finalised sickness absence review.

The Committee acknowledged progress in securing an external reviewer to validate the council's self-assessment against the Global Internal Audit Standards (GIAS).

The Committee acknowledged progress on implementing the revised internal audit delivery model.

Why

Audit found significant weaknesses in how sickness absence is recorded, monitored and managed across the council, including late entry of absences, missing return-to-work records, and inconsistent use of formal stages. Report P1, P10, P11

In a sample of 24 sickness episodes, only 4 had a return-to-work form completed on Agresso, a 17% compliance rate. Report P5, P33

Line managers were found to be unaware of three of the four sickness absence triggers in the policy, and Agresso does not auto-notify managers when two key triggers are activated. Report P5, P19, P20

What happens next

A revised Managing Sickness Absence Policy is being prepared for Employment Committee endorsement, with several actions targeting October 2025, and standard procedure reinforcement by November 2025. Report P24, P39, P48

Changes to the Agresso system to allow line managers to initiate return-to-work forms, attach fit notes correctly, and send automatic trigger notifications are scheduled for March 2026, subject to Agresso team work package priorities. Report P34, P42, P52

The council's disciplinary process may be used to investigate misuse or omissions in recording absence, with action point 3 due March 2026. Report P28

Options considered

  • Rejected: Apply stage one formal meeting consistently to all trigger notifications (as done in Customer Services Centre). Cited as good practice by Customer Services Centre; audit found other managers apply discretion Report P7, P8, P9, P18
  • Rejected: Retain manual return-to-work forms on a shared drive (used in DSO/Environmental Services). Lack of confidence in Agresso document retention following an incident 2-3 years ago Report P15, P38, P39
  • Rejected: Retain fit notes on the employee's absence record on Agresso. Document gets archived, leaving no clear audit trail Report P15, P42

Implications

  • Risk: Audit identified a high-priority risk that return-to-work meetings are often not recorded, leaving the council without a clear audit trail of staff support and return arrangements. Report P31, P33
  • Staffing: Payroll is undertaking additional work calculating backdated sickness benefit and writing to employees about salary deductions because some managers do not record absence on Agresso promptly. Report P5, P14, P27
  • Other: Backfilling of roles during sickness absence is not covered in the HR policy; it rests with line managers to secure approval to recruit. Report P21
  • Legal: Council disciplinary process may be used to investigate any misuse or omission in recording absence, with revised policy stating reasons for absence must be recorded. Report P27, P28, P29
  • Equalities: Stage one formal absence meetings must be applied consistently; the Customer Services Centre model invites all staff to a first formal interview once they reach the 6-day trigger, with reference to Occupational Health and the Employee Assistance Programme. Report P8, P9, P18

Who and where

  • All directorates, sampled across the period 1 April 2024 to 31 January 2025 Report P14
  • Line managers (seven interviewed) Report P5, P51
  • HR Business Partners and Payroll and Pensions Lead Report P9, P14, P19
  • Customer Services Centre team (cited as good practice) Report P7, P8, P9
  • Direct Service Organisation, Environmental Services (manual RTW process) Report P15, P37

Timeline

  • April 2024: Managing Sickness Absence Policy approved Report P13
  • 1 April 2024 to 31 January 2025: Period covered by audit sample of 24 absences Report P14
  • June 2024: Policy implemented Report P13
  • January 2025: Sickness absence reporting added to Monthly HR DLT Reports Pack Report P20
  • 10 September 2025: Date of previous Committee meeting referenced in decision
  • October 2025: Revised policy to be endorsed by Employment Committee, with several management actions targeted for completion Report P24, P27, P52
  • November 2025: Standard Agresso completion procedure to be reinforced; new policy revision on formal meetings Report P39, P48
  • March 2026: Agresso system changes for RTW forms, fit note uploads, automatic trigger notifications, and disciplinary use action point 3 Report P28, P34, P42, P53

Plain English for the jargon

  • RTW: Return to Work (meeting held after a period of sickness absence)
  • Agresso (Unit 4): The council's HR and finance system used to record sickness absence
  • Fit note: A document from a doctor or healthcare professional covering sickness absence lasting more than seven days
  • GIAS: Global Internal Audit Standards
  • Partial assurance: Audit opinion where significant weaknesses exist in the control framework, making it inadequate or at risk of becoming so
  • DLT: Departmental Leadership Team, the monthly HR report recipient
  • OH: Occupational Health services
  • EAP: Employee Assistance Programme
  • CSC: Customer Services Centre, cited in the audit for good practice
  • DSO: Direct Service Organisation, the environmental services team that uses manual return-to-work forms
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item46

Resolved

Resolved – (a) That the internal audits completed throughout the year and the specific findings from those audits finalised since the last Committee meeting on 10 September be noted. (b) That the progress being made to secure an external reviewer to validate the self-assessment against the Global Internal Audit Standards (GIAS) be acknowledged. (c) That the progress being made to implement the revised delivery model be acknowledged.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

Executive summary

Partial Assurance There are significant weaknesses in the framework of governance, risk Partial management and control such that it could be or could become inadequate and ineffective.

Introduction The Managing Sickness Absence review is part of the agreed internal audit plan for 2024/25. The effective management of sickness absence is in the interests of both the Council and their staff, and robust sickness absence policies can, if implemented properly, help improve attendance at work, the health and wellbeing of staff and ultimately customer services. Sickness absence can have a significant impact on both performance and costs to the organisation and therefore needs to be managed in a consistent, supportive, and effective way so that operational and service levels are maintained.

Objective The objective of this review is to assess the adequacy of design and operating effectiveness of the key controls established to ensure directorate adherence to the Council’s Managing Sickness Absence Policy and supporting guidance.

Key Findings

The following are the key findings from the audit: • Policy and Procedures in place: An up-to-date sickness absence policy is accessible to staff that clearly outlines the employee and line managers responsibilities for the management of short and long-term sickness absence, supported by a suite of letter templates covering informal and formal meetings. • Failure to record sickness absences on Agresso on a timely basis: Audit informed of instances of sickness absences not recorded on Agresso on a timely basis resulting in Payroll having to calculate sickness benefit relating to absences that occurred in prior periods and undertaking additional work writing to employees informing them of deductions from their salary. • RTW meetings not always recorded on Agresso: For a random sample of twenty-four sickness absences that covered all Directorates, the Agresso (Unit 4) Systems Team ran a query within Agresso to identify whether a RTW form had been completed based on the first day of absence. The findings showed a compliance rate of 17%. Semi-structured interviews were held with seven line managers and Audit informed that in the case of one

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IA Progress Report: Appx 1 Managing Sickness Absence Final AuditReport 1.1 MB DownloadRead as text
PDF
IA Progress Report: Appx 2 Bank Reconciliations Final Internal Audit ReportReport 880 KB Download
PDF
IA Progress Report: Appx 3 Financial Control Direct DebitsReport 1 MB Download
PDF
IA Progress Report: Appx 4 Financial Controls over Procurement and PaymentsReport 760 KB Download
PDF
Internal Audit Mid-Year Progress ReportReport 210 KB Download

At this meeting

Whole meeting

Who was there

9 of 13 attended
FO
Councillor Frank O’KellyChair, present
AE
Councillor Andrea EscottVice-Chair, present
RA
Councillor Robert AndersonCommittee Member, apologies
MI
Councillor Mark InstoneCommittee Member, present
SM
Councillor Subhash MohindraCommittee Member, present
MN
Councillor Mohammed NazirCommittee Member, present
NR
Councillor Neel RanaCommittee Member, present
ZS
Councillor Zafar SattiCommittee Member, present
DT
Councillor Dhruv TomarCommittee Member, present
RS
Rupa Sidpara Co-Optee MemberCo-Optee, expected
JS
Jen Simpson Co-Optee MemberCo-Optee, present
MS
Mike SmithOfficer, expected

All 13 on the meeting page

On this subject at Slough

Search all
  1. Internal Audit Mid-Year Progress ReportThis decision
  2. Internal Audit Plan and Charter 2026/27Approved
  3. Internal Audit Mid-Year Progress ReportNoted
  4. Finance and Commercial Internal Audit Recommendations UpdateNoted
  5. Digital, Data and Technology Internal Audit Recommendations UpdateNoted
  6. Internal Audit Progress ReportNoted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open