Audit and Risk Committee, Monday 25 March 2013 at 6.30pm

Risk Management

Noted Finance 1 paper

Audit and Risk Committee noted this item on Monday 25 March 2013. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

Resolved – That the Risk Management Strategy report be noted.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Risk Committee

SLOUGH BOROUGH COUNCIL

REPORT TO: Audit & Risk Committee DATE: 25th March 2013

CONTACT OFFICER: Phil Brown, Senior Risk & Insurance Officer (For all enquiries) (01753) 875673

WARD(S): All

PART I FOR COMMENT AND CONSIDERATION

RISK MANAGEMENT STRATEGY 2013/14

Introduction

At the Audit and Risk Committee of the 8th November 2013 the amended Risk Management Strategy was adopted by the committee.

Within the strategy four main actions were identified, these were:

• Move from the current 3x3 scoring matrix to a more sophisticated 5x5 matrix

• The JCAD risk management system is upgraded to a web based system hosted by JC Applications.

• Once the system has been upgraded guidance notes will be issued on how to use the upgraded system

• Each departmental risk register will be quality assured by the Risk Management Group on a rolling basis.

The adopted strategy stated that these actions were planned over the next 24 months. However it transpires that the vast majority of these actions have now been completed.

As the majority the actions have now been completed it is necessary to draw up a more challenging strategy.

2013/14 Strategy

It has been agreed that as part of the annual audit of risk management RSM Tenon the Council’s appointed Internal Auditors will assist in developing a strategy for 2013/14 that meets the needs identified within their annual review. The RSM Tenon review will be completed by 31st April 2013. One key issue that has already been identified is the quality and relevance of the current risks registers. The risk registers have been found to remain static i.e. there are few if any changes and in some cases lack detail. In order to remedy this the Corporate Risk Management Group have agreed an action plan for the coming year .

The actions that have been identified are detailed below.

Action Outcome By whom By when Ensure that the The Corporate Risk Assistant Sept 2013 Corporate Risk Register will be more Director Finance Register is dynamic, reflecting & Audit systematically the key risks to the updated at least every authority. quarter by CMT. The risk register will incorporate action plans on how the each individual corporate risk is to be managed

At each Corporate Risk Registers will be Corporate Risk On-going Risk Management more individualistic Management Group a selection of with fewer generic Group Risk Registers will be risks. subject review by the Corporate Risk Management Group.

Assist in the creation There will be a risk Risk & insurance Sept 2013 of risk registers for register that reflects Officer/Corporate key partnerships the risks posed to the Policy authority by each key partnership

Continue to monitor More Risk registers Risk & insurance On-going and assist in the will be up to date and Officer updating of risk to a higher quality registers. and relevance

Reporting non- compliance to the Relevant Corporate risk Management Group

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk ManagementReport 67 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 7 attended
MN
Councillor Mohammed NazirChair, present
FA
Councillor Frank AbeCommittee Member, present
PB
Councillor Preston BrookerCommittee Member, present
NC
Councillor Nimrit ChohanCommittee Member, present
AD
Councillor Arvind DhaliwalCommittee Member, present
AK
Councillor Antreev K. DhillonCommittee Member, absent
AK
Ajay KwatraCommittee Member, present

On this subject at Slough

Search all
  1. Risk ManagementThis decision
  2. Risk Management UpdateNoted
  3. Risk Management StrategyApproved
  4. Risk Management Update Quarter 2 2023/24Noted
  5. Risk Management Update - Quarter 1 2023/24Noted
  6. Risk Management Update - Quarter 4 2022/23Noted

More from Slough Audit and Risk Committee

All decisions
MeetingDecisionOutcome
12 Mar 2015 Minutes of the last Meeting held on 11 December 2014Resolved – That the minutes of the meeting held on 11 th December 2014 be approved as a correct record. Approved Open
12 Mar 2015 Audit and Risk Management Update: Quarter 3 2014/15Resolved – (a) That the Quarter 2 Management Update be noted. (b) That the protocol for internal audit procedures for... Noted Open
12 Mar 2015 Internal Audit Strategy 2015/16Resolved – That the Internal Audit Strategy 2013/14 to 2015/16, including the annual plan for 2015/16, be approved. Approved Open
12 Mar 2015 External Audit Plan 2014/15 and 2015/16Resolved – (a) That the External Audit Plan for the year ending 31 March 2015 be approved. (b) That the External Audi... Approved Open