It was agreed that the Committee would be kept up to date to ensure they were confident that that issues identified in audits had been addressed. Resolved - (a) That the report be noted. (b) That Members be updated on the progress of implementing recommendations in future meetings by reports presented by management. Internal Audit will also carry out some independent testing throughout the year and report back to the committee.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
Internal Audit Progress Report Audit and Risk Committee Meeting: 25 March 2013 Introduction th The internal audit plan for 2012/13 was approved by the Audit and Risk Committee on the 27 March 2012. This report provides an update on progress against that plan and summarises the results of our work to date. Since the last Audit and Risk Committee held in November 2012 the following 19 audit reports, relating to the 2012/13 plans have been finalised: Additional Devolved Budgets to Schools (3.12/13) Baylis Court Nursery School (11.12/13); Budget Setting Process (13.12/13); Council Tax (18.12/13) Gold Projects – Project Management Arrangements (19.12/13); Housing Management System (23.12/13) Procurement (24.12/13); Children’s and Families Assessment Teams (26.12/13) James Elliman Primary School (27.12/13) Recruitment (28.12/13); Data Protection Act (29.12/13); IQRA Islamic School (30.12/13); Arbour Vale (31.12/13); Contract Management – Block Nursing Contracts (32.12/13); St Ethelberts School (34.12/13); Tenancy Fraud (35.12/13); Safeguarding – Risk Assessment Process (38.12/13); Payroll (40.12/13); Estates and Facilities Management (43.12/13).
A summary of the key issues contained within these report and the high priority recommendations are detailed in the report below from page 4. KEY ISSUES Two RSM Tenon audit reports in respect of the 2011/12 Internal Audit plan remain in draft. (Note – RSM Tenon provided the IA service for Quarter 4 of 2011/12 only). Of the 48 reports which have been issued to management in respect of the 2012/13 Internal Audit plan, 16 of these still remain as draft reports. Of these 16, 11 of these have been outstanding for more than 30 working days (average time 11 draft reports outstanding is 88 working days). Whilst management assurance has been provided in the audit debrief meetings that the weaknesses identified as part of these audits will be addressed, in the absence of a completed action plan, we cannot provide assurance that these weaknesses are being addressed in a timely manner. It is therefore possible that these weaknesses and risks are not being effectively managed. The Audit and Risk Committee should be reminded that management have directed some of the Internal Audit plan of work at areas of concern or where weaknesses where known. This should be considered when reviewing the level of assurance opinions provided below and the proportion of red opinions. Of the 48 reports (including the 16 that remain in draft) issued to the Council to date for the current financial year, the breakdown of the levels of assurance provided is as follows:
1 Assurance Levels 2012/13 to date Green Amber Amber Red Advisory Total 15% Green Red 23%
Assurance 7 11 18 11 1 48 opinions 2012/13 23%
39%
Green Amber Green Amber Red Red
The breakdown in the type of recommendations for the year to date is highlighted below:
Recom mendation categorisations in 2012/13 High Medium Low Total reports to date: 19% 33% Recommendations 55 142 95 292 raised 2012/13
48% High Medium Low
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
External Audit Plan 2014/15 and 2015/16Resolved – (a) That the External Audit Plan for the year ending 31 March 2015 be approved. (b) That the External Audi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.