Resolved
Resolved – That the report comprising the Internal Audit Progress Report; implementation of Internal Audit Recommendations; and update on anti-fraud activities be noted.
Audit and Risk Committee noted this item on Thursday 19 September 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the report comprising the Internal Audit Progress Report; implementation of Internal Audit Recommendations; and update on anti-fraud activities be noted.
The purpose of this report is to:
• Report to members on Internal Audit progress to date in 2013-14. • Report to members on the progress of the implementation of Internal Audit recommendations. • Update members on anti-fraud activity and the summary corporate risk register.
2 Recommendation(s)/Proposed Action
The Audit & Risk Committee is requested to comment on and note the reports.
3 Slough Joint Wellbeing Strategy Priorities
The actions contained within the attached reports are designed to improve the governance of the organisation and will contribute to all of the emerging Slough Joint Wellbeing Strategy Priorities
Priorities:
• Economy and Skills • Health and Wellbeing • Regeneration and Environment • Housing • Safer Communities
4 Other Implications
4.1Financial
There are no financial implications of proposed actions 4.2 Risk Management
This report concerns risk management across the Council
4.3Human Rights Act and Other Legal Implications
n/a
4.4Equalities Impact Assessment
There is no identified need for an EIA.
5 Supporting Information
5.1Overview
5.1.1 RSM Tenon have completed a number of audits from their work during the first quarter of 2013-14. The most important item to highlight for members is the draft Children’s service procurement audit. This audit received a draft red opinion from RSM Tenon.
5.1.2 As part of the Head of Internal Audit opinion report taken to the Audit Committee in June 2013, RSM Tenon highlighted procurement as an area of significant weakness. Within the Annual Governance Statement for 2012-13, approved at the June Audit Committee, the first issues raised in respect of 2012-13 related to procurement, and specifically:
“The audit of procurement, undertaken throughout the year have identified that whilst there was a procurement framework in place, this was not being complied with consistently and a result the Council cannot gain assurance that value for money was being obtained through the procurement process”
5.1.3 On the basis of the recent draft Children’s service procurement audit and the previous internal audit reports in respect of procurement, management have authorised that all staff with responsibilities for procurement undertake mandatory training in light of internal audit’s work on procurement and the requirements to ensure compliance with the Council’s own procurement rules and policies.
5.1.4 It should also be noted that overall Internal audit reports are continued to be finalised at a more appropriate rate than in the previous financial year. Of the 2012-13 internal audits, 4 remain outstanding. Of the 2013-14 Q1 internal audits, there are 9 outstanding, 6 of which are schools.
5.1.5 The Council continues to monitor the progress of internal audit recommendations. As at the beginning of September, of the high and medium risk recommendations raised 79% have seen action being taken to progress these or these have been superseded.
5.1.6 The Council has also been completing its work against the Audit Commission’s National Fraud Initiative (NFI) data-matching exercise. 5.2 Internal Audit Q1 2013-14 progress report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportAppendix A | 654 KB | Download |
PDF |
Audit & Risk Management Update: Quarter 1 2013-14Report | 108 KB | DownloadRead as text |
Follow Audit and Risk Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Mar 2015 | Minutes of the last Meeting held on 11 December 2014Resolved – That the minutes of the meeting held on 11 th December 2014 be approved as a correct record. | Approved | Open |
| 12 Mar 2015 | Audit and Risk Management Update: Quarter 3 2014/15Resolved – (a) That the Quarter 2 Management Update be noted. (b) That the protocol for internal audit procedures for... | Noted | Open |
| 12 Mar 2015 | Internal Audit Strategy 2015/16Resolved – That the Internal Audit Strategy 2013/14 to 2015/16, including the annual plan for 2015/16, be approved. | Approved | Open |
| 12 Mar 2015 | External Audit Plan 2014/15 and 2015/16Resolved – (a) That the External Audit Plan for the year ending 31 March 2015 be approved. (b) That the External Audi... | Approved | Open |
| 12 Mar 2015 | Members Attendance RecordResolved – That the Members Attendance Record be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.