Audit & Risk Management Update - Quarter 4 2019/20

Noted Finance 3 papers

Audit and Corporate Governance Committee noted this item on Thursday 5 March 2020. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

Resolved – That details of the Audit & Risk Management Update Quarter 4 2019/20 be noted
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

Purpose of report

The purpose of this report is to:

 Report to Audit & Corporate Committee on the progress of finalising draft Internal Audit reports  Report to the Committee on the progress of the implementation of Internal Audit recommendations

2. Recommendation(s)/Proposed Action

That the Committee is requested to comment on and note the attached reports

3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan

3a. Slough Joint Wellbeing Strategy Priorities –

The actions contained within the attached reports are designed to improve the governance of the organisation and will contribute to all of the emerging priorities

3b. Five Year Plan Outcomes

The actions contained within this report will assist in achieving all of the five year plan outcomes

4. Other Implications

(a) Financial

There are no financial implications of proposed action (b) Risk Management

Recommendation Risk/Threat/Opportunity Mitigation(s) That Audit & Corporate This report concerns risk Governance Committee management across the is requested to Council comment on and note the attached reports

(c) Human Rights Act and Other Legal Implications

There are no Human Rights Act or other legal implications in this report

(d) Equalities Impact Assessment - There is no identified need for an EIA

5. Supporting Information

5.1Finalising Internal Audit Reports

5.1.1 The table below shows those “Assurance” Internal Audits that remain in draft and were to be finalised by 11th February 2020

Audit Audit Audit Assurance Date to be Comments Plan Sponsor Level Finalised by Year Capital 19/20 Neil Wilcox Reasonable 31st January Query with one Expenditure Assurance 2020 action

5.2Monitoring Management Actions

5.2.1 The Risk and Insurance Officer regularly monitors the progress of the implementation of the Management Actions made. Below is a graph that shows the percentage of High and Medium risk recommendations, from the current and two preceding audit years, that have either been implemented, are in progress, or no action has been taken.

Progress of Agreed Management Actions as at 24th Feb 2020 1% 6% 12% Completed Superseded In Progress 81% No Action 5.2.2 Attached at Appendix 1 is a list of outstanding Medium actions that are outstanding

5.2.3 The percentage of completed actions increased to 81% from last quarters 70%

5.2.4 On a quarterly basis RSM our Internal Auditors conduct a follow up audit to review progress made by the Council to implement the previously agreed management actions.

5.2.5 The latest follow up audit from RSM shows that the Council has made “reasonable progress” in implementing the agreed management actions

5.2.6 Attached at Appendix 2 is a list of the “High” Recommendation Actions that remain Outstanding past the target date.

Current Position Previous Audit Committee No Action Partially Complete No Action Partially Complete 0 1 0 5

6. Comments of Other Committees

There are no comments from other Committees

7. Conclusion

The Committee is requested to consider and note the appendices.

8. Appendices Attached

Appendix 1 – Details of outstanding Medium agreed management actions

Appendix 2 – Details of outstanding High agreed management actions

Background papers

None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Overdue Medium Rated ActionsAppendix 1 50 KB Download
PDF
Overdue High Rated ActionsAppendix 2 30 KB Download
PDF
Audit & Risk Management Update: Quarter 4 2019/20Report 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
WS
Councillor Waqas SabahChair, present
AW
Councillor Anna WrightVice-Chair, present
SA
Councillor Safdar AliCommittee Member, present
SA
Councillor Sabia AkramCommittee Member, present
DS
Councillor Dilbagh S. ParmarCommittee Member, present
SS
Councillor Satpal S. ParmarCommittee Member, present
TP
Councillor Ted PlentyCommittee Member, present
AS
Alan SunderlandCo-Optee, present
IZ
Iqbal ZafarCo-Optee, present
PC
Parish Councillor Preston BrookerAttendee, apologies
PC
Parish Councillor Andrea EscottAttendee, absent
PC
Parish Councillor Iftakhar AhmedAttendee, present

All 17 on the meeting page

On this subject at Slough

Search all
  1. Audit & Risk Management Update - Quarter 4 2019/20This decision
  2. 2018/19 Updated Audit Plan and Revised Risk AssessmentNoted
  3. Audit and Risk Management Update Quarter 3 2019/20Agreed
  4. Audit and Risk Management Update - Quarter 2 2019/20Agreed
  5. Audit and Risk Management Update - Quarter 1 2019/20Noted
  6. Audit and Risk Management Update - Quarter 2 2018/19Noted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open