SLOUGH BOROUGH COUNCIL AUDIT PLAN TO THE AUDIT AND CORPORATE GOVERNANCE COMMITTEE Audit for the year ended 31 March 2017
Date of issue: 18 April 2017 CONTENTS INTRODUCTION ....................................................................................... 1
YOUR BDO TEAM ..................................................................................... 2
ENGAGEMENT TIMETABLE .......................................................................... 3
AUDIT SCOPE AND OBJECTIVES.................................................................... 4
MATERIALITY ......................................................................................... 5
OVERALL AUDIT STRATEGY ........................................................................ 6
KEY AUDIT RISKS AND OTHER MATTERS ......................................................... 7
INDEPENDENCE ..................................................................................... 18
FEES .................................................................................................. 19
APPENDIX I: MATERIALITY ........................................................................ 20
APPENDIX II: INDEPENDENCE ..................................................................... 22 INTRODUCTION
PURPOSE AND USE OF OUR REPORT
The purpose of this report is to highlight and explain the key issues which we believe to be relevant to the audit of the financial statements and use of resources of the Council for the year ended 31 March 2017. It forms a key part of our communication strategy with you, a strategy which is designed to promote effective two-way communication throughout the audit process. Planning is an iterative process and our plans, reflected in this report, will be reviewed and updated as our audit progresses. This report has been prepared solely for the use of the Audit and Corporate Governance Committee. In preparing this report, we do not accept or assume responsibility for any other purpose, or to any other person to whom it is shown or into whose hands it may come. If others choose to rely on the contents of this report, they do so entirely at their own risk.
1 YOUR BDO TEAM
Core team Name Contact details Key responsibilities
Janine Combrinck Janine Combrinck Tel: 020 7893 2631 Oversee the audit and sign the audit report Engagement Lead Engagement Lead [email removed]
Nick Bernstein Tel: 020 7486 5888 Management of the audit Nick Bernstein Project Manager Project Manager [email removed]
Michael Asare Bediako Tel: 020 7893 3643 Day to day management and Michael Asare Bediako supervision of the audit Supervisor [email removed] Supervisor
Gordon Secker Tel: 01603 756910 Day to day lead of the on-site Gordon Secker audit team Senior Senior [email removed]
Janine is the Engagement Lead and has the primary responsibility to ensure that the appropriate audit opinion is given on the financial statements. In meeting this responsibility, she will ensure that the audit has resulted in obtaining sufficient and appropriate evidence to provide reasonable, but not absolute, assurance that: • the financial statements are free from material misstatement, whether due to fraud or error • the Council has made proper arrangements for securing economy, efficiency and effectiveness in its use of resources. Janine is also responsible for the overall quality of the engagement.
2 ENGAGEMENT TIMETABLE
TIMETABLE
The timeline below identifies the key dates and anticipated meetings for the production and approval of the audited financial statements and completion of the use of resources audit.
CONTINUOUS COMMUNICATIONS
Audit and Corporate Audit and Corporate Governance Committee Governance Committee receives audit plan receives audit completion 11 July 2017 report and approves Statement of Accounts 28 September 2017
NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Plan 2016/17Report | 153 KB | DownloadRead as text |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... | Approved | Open |
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.