Resolved
Resolved – (a) That the update on the external audit and timescale for finalising the 2016/17 financial statements be noted. (b) That an extraordinary meeting be convened in early November to consider the financial statements for approval.
Audit and Corporate Governance Committee noted this item on Wednesday 11 October 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – (a) That the update on the external audit and timescale for finalising the 2016/17 financial statements be noted. (b) That an extraordinary meeting be convened in early November to consider the financial statements for approval.
The purpose of this report is to update Members on the progress of external audit of the 2016/17 financial statements.
2. Recommendation(s)/Proposed Action
That Audit & Corporate Governance Committee is requested to comment on and note the report.
3a. Slough Joint Wellbeing Strategy Priorities
The actions contained within the attached reports are designed to improve the governance of the organisation and will contribute to all of the strategic priorities.
Priorities:
Protecting vulnerable children Increasing life expectancy by focussing on inequalities Improving mental health and wellbeing Housing
3b. Five Year Plan Outcomes
The actions contained within this report will assist in achieving all of the five year plan outcomes
4. Other Implications
(a) Financial
There are no financial implications of this report.
(b) Risk Management Recommendation Risk/Threat/Opportunity Mitigation(s) That Audit & Corporate This report concerns risk Governance Committee management across the is requested to Council comment on and note the attached report
(c) Human Rights Act and Other Legal Implications
There are no Human Rights Act or other legal implications in this report
(d) Equalities Impact Assessment
There is no identified need for an EIA.
5. Supporting Information
5.1.1 Members of the Audit and Corporate Governance Committee would normally have the opportunity to receive and question the Council’s external auditors at this meeting regarding the audit of the 2016/17 financial statements. The Committee would also be asked to approve the financial statements.
5.1.2 The Council is required to submit a signed copy of its financial statements to the external auditors, BDO, by the 30th June 2017. The Council completed this requirement in line with statutory deadlines.
5.1.3 Over the summer period the external auditors, BDO (independently appointed by the Audit Commission for the 2016/17 financial year) conduct a review of the financial statements produced and provide two opinions:
1) An opinion on the financial statements themselves; and
2) A Value for Money opinion.
5.1.4 The expected report for tonight’s meeting would normally cover these two opinions and detail how the Council complies, or otherwise, with these opinions. BDO would also include recommendations for the Council going forward.
5.1.5 It has not been possible to provide the financial statements to this meeting and the external auditors have not been able to produce their reports. Both sides have worked hard over the past few months to arrive at an agreed position but the following factors have led to a delay in signing off the opinion and the statements.
5.1.6 For the first time SBC is required to produce Group Accounts. The creation of the Slough Urban Renewal (SUR) has complicated the production of the year end accounts. The SUR financial information has not been consolidated into the Council’s accounts during both 2014/15 and 2015/16 because the Council’s 50% share was not deemed to be material. The 2016/17 statements were initially assumed to not be material and were reflected in the policies and notes along the same lines as previous years. 5.1.7 For 2016/17, BDO have required us to consolidate the SUR accounts into our financial statements and they are in the process of completing the audit of these new statements. This has been complicated by the fact that the SUR auditors (who are also BDO) are only required to sign off the accounts by the end of September 2017 and their accounting year runs until December 2016. This means that an element of estimation is required which we have been told requires additional auditing resources.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Statements 2016/17Report | 83 KB | DownloadRead as text |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... | Approved | Open |
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.