The purpose of this report is to update the Committee about the issue of the indexation provisions in the Council’s contract with Slough Enterprise Limited (formerly known as Slough Accord Limited), a subsidiary of Amey UK Plc, following the last meeting of the Committee.
2 Recommendation(s)/Proposed Action
The Committee is requested to note the contents of this report.
3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan
The delivery of all these strategic priorities is dependent on the highest possible standards of openness, honesty and accountability. The Council’s learning and actions in response to the findings of this report will serve to enhance the delivery of these priorities.
4 Other Implications
(a) Financial
The financial implications arising from this report appear within the body of the Report.
(b) Human Rights Act and Other Legal Implications
There are no Human Rights Acts implications arising from this report. The Legal implications appear within this Report.
Equalities Impact Assessment
There is no identified need for an EIA arising from the subject matter of this Report. 5 Supporting Information
5.1At its previous meeting on 13 December 2018, the Committee requested an update about the indexation issue under the Council’s environmental services contract with Slough Enterprise Limited which expired on 30 November 2017.
5.2The issue can be summarised as follows:
5.2.1 It is common ground between the Council and the Contractor that the formula for indexation set out in the contract contained an obvious error and could not be operated in the form contained in the contract.
5.2.2 In or around 2006 and 2007 the Council and the Contractor agreed the manner in which the formula would be applied and the contract was operated on that basis from that time.
5.2.3 In or around 2014 Officers considered that the indexation calculations made by the Contactor since the agreement reached in or around 2006 and 2007 were incorrect and the officers prepared a spreadsheet showing the differences between their calculations and those of the contractor. This spreadsheet is appended as a confidential appendix to this Report. This spreadsheet is the basis for the case that there may have been an overpayment to the Contractor under the contract.
5.2.4 Certain parts of the calculations appear to be consistent with the manner in which it is considered that the contract would be interpreted by the Court but it is difficult to understand the methodology lying behind other parts of the Officers’ calculations.
5.3The essential issue, therefore, is over the methodology behind the calculations of the officers set in the spreadsheet appended to this Report.
5.4The Officer responsible for the preparation of the appended spreadsheet left the employ of the Council in early May 2017.
5.5Since the last meeting of the Committee the Council have engaged the external consultants, Ethical Commercial Services Limited, who are presently assisting the Council with the Council’s commercialisation and contract management projects, to carry out a review of this matter. They have reviewed the matter. They too are unable to deconstruct the methodology behind the officer’s calculations contained in the appended spreadsheet.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Amey Indexation Update ReportReport | 73 KB | DownloadRead as text |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... | Approved | Open |
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.