Resolved
View the decision text for item 10.
Cabinet decided this item on Monday 17 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 10.
To provide an update on the HQ relocation project and the proposed use of different assets.
The Cabinet is requested to note:
a) Council progress in making 25 Windsor Road (25WR) available to use as the Council’s HQ;
b) The remainder of the Ground Floor and the entire 4th Floor at 25WR are being fitted-out to support the requirement to accommodate:
approximately 180 staff being transferred back in-house from Arvato; a Post Room and an IT Workshop.
c)The 5th floor will continue to be made available for commercial let to a third party.
3.1Since Cabinet agreed to acquire 25WR, in May 2018, a number of decisions have been taken that could impact on the original business case.
3.2Given the level of interest in the Council’s forthcoming move to a new HQ.at 25 WR it was thought timely to present members with an update of progress so far.
4 Progress to date
4.1Officers are anticipating, subject to the ongoing availability of third party resources, the completion dates of 25WR as follows: Ground Floor – July 2019 1st Floor - July 2019 2nd Floor – August 2019 3rd Floor – September 2019 4th Floor – November 2019 Ground Floor North - December 2019
Construction 4.2 Bouygues were appointed with responsibility for implementing the internal fit-out of the building. Key tasks that have been delivered are as follows:
Design; Fit out of the Ground Floor South including the Council Chamber, Communications Room and Civic Suite; Installation of infrastructure to introduce enhanced Audio Visual solutions including live streaming of public meetings.
Technology 4.3 From the technology perspective, the main challenges have been around the role of Arvato. Upon receipt of SBC’s Termination Notice, Arvato placed all 25WR project work on hold, which had a consequent knock-on effect on the overall programme. Officers have subsequently negotiated the continuation of key projects. Therefore the core IT elements relating to 25WR are now progressing on schedule:
Network connectivity is installed at 25WR and tested. The new Wi-fi solution and Domain Controller are progressing to plan. UPS installation for resilience is scheduled for June 16th.
Unified Communications Telephony 4.7 SBC have engaged direct with Virgin Media and are arranging a “lift & shift” of existing IPMM SMP telephony into 25WR to enable occupation from Day 1. This is viewed as a purely short term arrangement to enable a more robust solution to be developed by the end of 2019.
Remote Working 4.8 Remote Working was identified as a clear Phase 2 activity in the Transformation Business Case, approved by Cabinet on 15th April 2019. Therefore, new desktop IT will not be introduced immediately for the moves, we will lift and shift PCs and IGels. As we progress through the transformation journey, smart technology will be rolled out to support smart working and digital initiatives. However, a significant amount of remote working equipment already exists within the organisation. HR have been undertaking workshops to assist staff with new ways of working prior to the 25 WR moves. Three significant work areas have also been identified as “pilots” and additional devices are being procured to support this.
Audio Visual Work 4.9 This workstream is now progressing well using a solution provided by ProAv an independent supplier procured via Bouygues. ProAv have presented an effective solution to enable live streaming of public meetings in the Council Chamber, enabling our residents to view meetings online i.e. planning. CCTV 4.10 CCTV has progressed with an additional Virgin line being put in place to allow live visibility via the control room.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HQ Town Centre Relocation UpdateReport | 77 KB | DownloadRead as text |
Follow Cabinet at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Declarations of InterestView the decision text for item 1. | Decided | Open |
| 19 Oct 2026 | Minutes of the Meeting held on 21st September 2026View the decision text for item 2. | Decided | Open |
| 19 Oct 2026 | 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. | Decided | Open |
| 19 Oct 2026 | Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. | Decided | Open |
| 19 Oct 2026 | Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.