Resolved – (a) That Bracknell’s The Deck be given conditional financial approval in the sum of £955,882 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 of the report and subject to the following condition: i. Confirmation from a LEP appointed solicitor the scheme conformed to State Aid requirements. (b) That the response of the LEP appointed solicitor regarding State Aid compliance be circulated to all members of BLTB; and that if any substantive concerns were raised with the LEP that consideration would be given to convening an additional meeting of BLTB if those issues could not be resolved.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to Bracknell’s ‘The Deck’ town centre scheme, which includes partial demolition/strip out and subsequent redevelopment of the former Bentall’s Department Store and former McDonald’s in the town centre.
2. The proposed redevelopment will include:
• 3,207 sqm of Food and beverage uses (use class A3/A4/A5); • 2,148 sqm of Assembly and leisure uses (use class D2); • Public event area; • Roof covering; • Public realm improvements; and • Associated highway works.
3. Whilst the scheme was originally developed by the private sector, changing market conditions have resulted in the developer stating that they are no longer able to fund the demolition and construction of the Deck as a result of uncertainties around the return on investment. This demonstration of market failure affects the overall viability of the scheme for the private sector and evidences the need for public sector investment.
4. The strategic case demonstrates alignment with national, regional and local strategic priorities and provides underlying evidence of the need for ‘The Deck’ scheme as part of the on-going regeneration of Bracknell Town Centre.
Recommendation
5. You are recommended to give Bracknell’s The Deck conditional financial approval in the sum of £955,882 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below and subject to the following condition:
5.1Confirmation from a LEP appointed solicitor the scheme conforms to State Aid requirements.
Other Implications
Financial
6. Notification was received on 18 September 2020 that scheme 2.05 Newbury: Sandleford Park would not be able to complete the scheme as originally specified and that £900k of the £2.9m Local Growth Deal funding allocated for the project would be returned.
7. Combined with existing unallocated Local Growth Fund (LGF) monies of £55,882, the total figure of unallocated Local Growth Fund monies is £955,882.
8. The LEP is currently in the sixth and final year of the LGF, with all money to be expended by March 2021.
9. As the existing BLTB pipeline of projects has recently been exhausted, and with a requirement to spend by March 2021, the LEP Board recommends to the BLTB that schemes from the recent Getting
Item 9: Financial Approval 2.47 Bracknell: Town Centre – “The Deck” Building Fund (GBF) pipeline are considered for funding. However, key for any scheme wanting to utilise LGF funding will be the ability to obtain an approved business case and complete any project by March 2021.
10. The process for identifying projects for the GBF created a pipeline of 27 projects, of which 6 have been funded. Of the remaining projects on the prioritised pipeline, only “The Deck” scheme for Bracknell Town Centre regeneration will be able to be fully delivered by Q1 2021.
11. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
12. The risk management arrangements already put in place by the Local Transport Body are as follows:
• The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes • Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme • The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.