Resolved
Resolved – That details of the report be noted.
Audit and Corporate Governance Committee noted this item on Monday 9 December 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That details of the report be noted.
Audit Progress Report Slough Borough Council Year ending 31 March 2019 December 2019 Commercial in confidence
Contents Section Page Introduction 03 Progress at December 2019 04 Audit Deliverables 05 Audit Work Progress Update 06
© 2019 Grant Thornton UK LLP. Confidential and information only. Audit Progress Report | November 2019 2 Commercial in confidence
Introduction
This paper provides the Audit and Corporate Governance Committee with a Julie Masci report on progress in delivering our responsibilities as your external auditors. Engagement Lead T 029 2034 7506 Members of the Committee can find further useful material on our website, where we have a section dedicated to our E [email removed] work in the public sector. Here you can download copies of our publications www.grantthornton.co.uk . If you would like further information on any items in this briefing, or would like to register with Grant Thornton to receive regular email updates on issues that are of interest to you, please contact either your Engagement Lead or Engagement Manager./
Sophie Morgan-Bower Engagement Manager T 0117 305 7757 E [email removed]
© 2019 Grant Thornton UK LLP. Confidential and information only. Audit Progress Report | November 2019 3 Commercial in confidence
Progress at December 2019
Financial Statements Audit Value for Money We have completed planning for the 2018/19 financial statements audit The scope of our work is set out in the guidance issued by the National and have issued a detailed audit plan, setting out our proposed Audit Office. The Code requires auditors to satisfy themselves that; "the approach to the audit of the Council's 2018/19 financial statements. Council has made proper arrangements for securing economy, efficiency and effectiveness in its use of resources". We reported to you in July 2019 and September 2019 that we have experienced some delays in respect of the opening balances for The guidance confirmed the overall criterion as: "in all significant respects, Property, Plant and Equipment during the course of the interim audit, the audited body had proper arrangements to ensure it took properly and that we are not able to confirm the opening balance position to date. informed decisions and deployed resources to achieve planned and We have experienced further delays which we communicate to you sustainable outcomes for taxpayers and local people". below. The three sub criteria for assessment to be able to give a conclusion overall The statutory deadline for the publication of the Council’s accounts are: remained unchanged at 31 July 2019 and the Council has published its •Informed decision making unaudited accounts by this date. •Sustainable resource deployment In this context, we note that the delivery of the 2018-19 audit has been further delayed due to issues with the production of working papers to •Working with partners and other third parties support the financial statements. In particular, these significant delays Details of our initial risk assessment to determine our approach were have resulted in a slippage of the timetable with regards to Income and included in our Audit Plan. We identified three significant Value for Money Expenditure testing. Risks – Medium Term Financial Strategy, Principles and Values of Sound We continue to regularly discuss our plan and timetable with officers to Governance and Internal Control; and Children’s Social Care services – and complete the audit, with the intention of presenting our audit findings are currently carrying out our audit work on this. report and opinion in early 2010. We will report our work in the Audit Findings Report and give our Value For Further details are provided on pages 6 to 8 of this report. Money Conclusion at the next Audit & Corporate Governance Committee meeting.
© 2019 Grant Thornton UK LLP. Confidential and information only. Audit Progress Report | November 2019 4 Commercial in confidence
Progress at December 2019
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit Progress ReportReport | 323 KB | DownloadRead as text |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... | Approved | Open |
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.