Resolved – (a) That the remaining £450,000 of GBF money be allocated to a transport project that would contribute to the implementation of the Recovery & Renewal Plan (RRP) and Strategic Economic Plan (SEP). (b) That it be agreed that scheme 2.37 Bracknell: A322-A329 Corridor Improvements receive an additional allocation of £450,000 GBF, to take the total funding allocated for the scheme to £850,000. A full business case, reviewed by the LEPs independent assessor, Hatch Regeneris , would be presented for financial approval at the July 2021 BLTB.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To present the case for allocating the remaining £450,000 of Getting Building Fund (GBF) monies to a Bracknell transport project. This proposes an increment to an already approved Local Growth Fund (LGF) Bracknell project, scheme 2.37: Bracknell A322 A329 Corridor Improvements.
Recommendation
2. You are asked to support the recommendation that the remaining £450,000 of GBF money is allocated to a transport project that will contribute to the implementation of the Recovery and Renewal Plan (RRP) and Strategic Economic Plan (SEP).
3. You are asked to approve that scheme 2.37 Bracknell: A322 A329 Corridor Improvements receives an additional allocation of £450,000 GBF, to take the total funding allocated for this scheme to £850,000. A full business case, reviewed by the LEPs independent assessor, Hatch Regeneris, will be presented for financial approval at the July 2021 BLTB.
Other Implications
Financial
4. In July 2020 Thames Valley Berkshire LEP secured £7.5m Getting Building Fund money from central government. £7,050k has been allocated to other Berkshire projects, including Langley High Street Improvements phase 3 (£1.643m) which was approved by BLTB in November 2020. The remaining funds have been allocated to skills and business projects, approved by the LEP Board.
Risk management
5. The risk management arrangements already put in place by the Local Transport Body are as follows:
The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes. Hatch Regeneris have been appointed to act as Independent Assessors for all LEP-funded schemes.
Human Rights Act and Other Legal Implications
6. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Item 5: BLTB 11 March 2021 Allocation of the remaining Getting Building Fund monies Supporting Information
7. £450,000 Getting Building Fund has been returned to the LEP for re-allocation following re- assessment of an earlier agreed GBF skills project. The GBF programme requires that any projects selected must be delivered by 31 March 2022 at the latest. Funding therefore needs to be allocated now to ensure delivery within HMG timescales.
8. The approved pipeline of schemes, agreed at the November 2020 BLTB meeting, was reviewed and discussions held with owners of the prioritised project list to identify suitable schemes to fit the tight delivery timescales and the funding available. The Bracknell A322 Smart Corridor project was ranked 4 of 16 projects and was deemed by the LEP to be the top project that could meet the requirements. This project is scalable and builds upon the current LGF project 2.37 Bracknell: A322 A329 Corridor Improvements that is already on site. It is therefore proposed that the additional funds are issued as a project extension rather than issuing programme entry to a new scheme.
Transport Project
9. The Bracknell A322/A329 Corridor Improvements project will continue to deliver significant improvements to one of the key highway corridors in Thames Valley Berkshire, between the M4 (J8/9/10) and M3 (J4), i.e. from Maidenhead, Reading, Wokingham, Bracknell to Camberley, the Blackwater Valley and beyond. These junction improvements along the A322/A329 corridor are required to facilitate the Council’s current adopted growth plans for around 11,000 dwellings.
10. In January 2019, programme entry status was awarded to scheme 2.37 Bracknell A322/A329 Corridor Improvements and allocated £1,200,000. A further £800,000 was allocated at the July 2019 BLTB meeting, bringing the total funds allocated to the scheme to £2,000,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.