Resolved
Resolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be noted.
Berkshire Local Transport Body noted this item on Thursday 9 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be noted.
1. At your meeting in July 2022, you approved a less intensive approach towards the impact reports being considered at BLTB meetings to reflect the reduction in reporting requirements from government whilst still demonstrating the value of investment in infrastructure.
2. This report introduces the one-year impact report for the following scheme.
• Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway
3. You are recommended to note the report from the scheme promoter and the LEP conclusions.
Supporting Information
4. The LEP has a well-established and agreed process for the monitoring and evaluation of BLTB funded local transport schemes, which requires scheme promoters to produce one- and five-year- on post completion monitoring reports for each of their schemes. It has been agreed that the LEP will continue to carry out reviewing these evaluations, utilising a small amount of the funding from within the capital programme for monitoring and evaluation purposes. However, given the limited amount of funding, these reviews will continue to be light touch and proportionate and fit for purpose, whilst continuing to demonstrate the value of our investment and to inform future priorities.
5. With the reduction in reporting requirements from Central Government, the format and detail of the reports are now less prescriptive and enable the scheme promoter to tailor the reports to their own needs and make them directly relevant to supporting investment decisions going forwards.
6. The reports submitted by each of the scheme promoters continue to summarise the outcomes of the monitoring and evaluation undertaken following the completion of the schemes. The analysis gives an initial indication whether a scheme has been successful in achieving the related aims and objectives set and agreed at the start of the scheme development. It also seeks to demonstrate that the funding obtained has provided value for money and that any lessons learnt are captured as evidence to inform future decision making. The assessments focus on:
• Scheme build; • Delivered scheme; • Costs; • Scheme objectives; and • Impacts on the economy
South Wokingham Distributor Road – Eastern Gateway
7. Wokingham Borough Council received £5m in BRRP funding towards the cost of this £20.16m scheme the remaining from Wokingham Borough Council’s Capital Funding programme. Item 4 BLTB 9 November 2023 – One Year Evaluation Report 8. The Eastern Gateway scheme comprised of single carriageway road connecting Montague Park to the north with Waterloo Road to the south via a new roundabout. The scheme provided access across the Waterloo rail line in the form of a new road bridge with the previous railway crossing on Waterloo Road closing as part of the scheme proposals.
9. The objectives of scheme were to support housing delivery, replace the existing level crossing, relieve traffic using residential roads as rat runs whilst minimising the impact of traffic generated by the housing development. The scheme also sought to encourage sustainable and active transport by providing extensive pedestrian and cyclist facilities.
10. The scheme was opened to the public in February 2022 approximately 1 year after the proposed scheme opening date. This was mainly due to the COVID-19 outbreak and associated lockdowns that were in place at various times in 2020 and 2021 which delayed construction and significantly affected the scheme programme. There were also issues with coal tar and additional work to install a piling platform though these did not affect delivery significantly.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: South Wokingham Distributor Road: Eastern Gateway EvaluationAppendix | 5.1 MB | Download |
PDF |
One Year Evaluation ReportReport | 91 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
| 13 Jul 2023 | Election of Chair for 2023/24Resolved – That Councillor Brock be elected as Chair of BLTB for the 2023/24 municipal year. (Councillor Brock in the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.