Risk Management Update Quarter 4 2021/22

Agreed Finance 2 papers

Audit and Corporate Governance Committee agreed this item on Tuesday 1 March 2022. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

It was agreed that the Lead Member and Executive Director of People (Adults) would be requested to attend the next ordinary meeting to provide an update on the delivery of the ASC transformation programme. · An update on progress of the Disposal of Assets was provided. A Member expressed concern that there was no start date for commencing disposals. The Director of Finance reminded the Committee that following approval by Cabinet in September 2021 – to appoint external support to advise and manage the programme of asset disposals; the final stages of procurement process was underway with work due to start March 2022. It was essential that due diligence was carried out and that the Council secured best value possible. Speaking under Rule 30, Councillor Strutton sought clarification regarding any assets that had been sold, referring specifically to the town centre Moxy Apartments. The Executive Director, Place and Community that whilst there had been sales at the referred development, these were separate to the Asset Disposals Strategy. · Members sought details regarding the costs associated with Temporary Accommodation (TA) for the current financial year and forecast for the next year, and the average duration for length of stay in TA. It was noted that details would be included in the next Committee report. The Chair raised the current conflict in Ukraine and asked what impact this had had on demands for TA. It was explained that the Council was monitoring the situation closely and respond as necessary and that the CRR would be updated to reflect the potential impact on TA as a result of the conflict in Ukraine. · Financial Sustainability – details to be provided outside of the meeting on training arrangements for Members and that the risk associated with £20m p/a savings be updated. A number of questions were asked relating to progress on the recruitment of a permanent financial team to both reduce the reliance on agency/interim staff and ensure long term stability. Work was ongoing to recruit and retain staff within the finance department, including the right calibre of staff in specialist roles and appointing to trainee roles with a long term aim of developing such roles in an effort to retain individuals in the long term. · Elections and Electoral registration – it was noted that the risks identified related to the May 2022 local elections and that the CRR would be updated accordingly ahead of the local elections in 2023. The Chair requested that an extraordinary meeting be scheduled for mid/late April to allow the Committee to receive a further update on the issues raised. Resolved – That details of the report, including revisions to the risk register, be noted and an extraordinary meeting be arranged for mid/late April 2022.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

Risk 1: Delivery of the Adult Social Care (ASC) Transformation Programme Risk Owner: Executive Director of People (Adults) Description: Current Controls:

If the adult social care transformation programme does not  Adult social care business case and implementation plans deliver changes in a timely and effective way there will be a  Adult social care transformation board – reporting into negative impact on quality of service with residents directly recovery and renewal board affected, savings will not be achieved and a balanced budget will  Tracking of actions and savings not be delivered.  Support and challenge from People Too consultant partners Consequence:  Better Care Fund (BCF) additional contribution to ASC confirmed. Additional income of £0.75m for 21/22 and Increasing number of people waiting for assessment, service or £0.46m for 22/23 review. Increasing number of safeguarding cases. Provider failures and reduced quality. Demand increasing. Use of agency Actions Required: increasing.  Manage increased income from client contributions – by Budget not balanced, savings not delivered, cost and price end of March 22 by Marc Gadsby increasing. Based on the Financial Assessment and Charging Workstream, live from July: Health funding to support the changes may be withdrawn New Client invoices raised to the value of £275,000 Backdated invoices raised the value of £775,000 Debt collected to the value of £382,000 Our target linked to this workstream is £300k for this year.  Deliver the workstream actions in the adult social care transformation programme by end of March 23 by Marc Gadsby and Jane Senior - Good progress being made – monthly reporting of progress to ASC transformation programme board, monthly project report to Exec Board and weekly financial tracking progress to lead members and directors.

Inherent Risk Residual Risk Target Risk Likelihood 6 5 4 Impact 3 3 2 Score 18 15 8 Date last updated: 9th February 2022 Risk 2: Covid Pandemic Risk Owner: Executive Board Description: Current Controls:

Further waves of covid infections overwhelm our ability and /or  Slough Local Outbreak Management Plan our partners ability to provide services to required standards and  Weekly covid silver staff continue to work under this pressure.  3 x weekly outbreak meeting  1 x weekly partner outbreak meeting Consequence:  Local contact tracing in place  Use of covid grants Increased demand on health and care systems. resulting in  Continue efforts to increase vaccination rates system pressures that impact ability to transform services or  Revision of local covid plan provide value for money and service quality.  Revised contact tracing plan  Staff wellbeing Increase in death rate and long term conditions arise which increasing demand on council services Actions Required:

Significant impact on workforce availability due to illness  Agreement on priority use of covid grants -Silver command  Priority areas for spend confirmed in revised Local Schools and local businesses impacted – closures Outbreak Management Plan – regular monitoring of covid grants and expenditure ongoing. Stretched council resources to manage the work  Return to workplace hybrid working policy

Staff wellbeing and health deteriorates

Additional unforeseen costs arise due to continuing impact of pandemic.

Inherent Risk Residual Risk Target Risk Likelihood 5 4 3 Impact 4 4 3 Score 20 16 9 th Date last updated: 9 February 2022 Risk 3: Temporary Accommodation Risk Owner: Executive Director of Place and Community Description: Current Controls:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register February 2022Report 460 KB DownloadRead as text
PDF
Risk Management Update Quarter 4 2021/22Report 113 KB Download

At this meeting

Whole meeting

Who was there

3 of 13 attended
WS
Councillor Waqas SabahChair, present
AW
Councillor Anna WrightVice-Chair, apologies (illness)
SA
Councillor Safdar AliCommittee Member, apologies (on leave)
PB
Councillor Preston BrookerCommittee Member, present
JD
Councillor Jemma DavisCommittee Member, absent
GS
Councillor Gurdeep S. GrewalCommittee Member, present
IH
Councillor Iram HussainCommittee Member, apologies
IZ
Iqbal ZafarCo-Optee, apologies
SK
Shabana KauserClerk, expected
HP
Hugh PeartPublic, expected
AW
Angela WakefieldOfficer, expected
HS
Councillor Harjinder S. GahirGuest, in attendance

All 13 on the meeting page

On this subject at Slough

Search all
  1. Risk Management Update Quarter 4 2021/22This decision
  2. Risk Management UpdateNoted
  3. Risk Management StrategyApproved
  4. Risk Management Update Quarter 2 2023/24Noted
  5. Risk Management Update - Quarter 1 2023/24Noted
  6. Risk Management Update - Quarter 4 2022/23Noted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open