Cabinet Urgency procedure - Leader's Action, Wednesday 27 July 2022 at 2.00pm

Corporate Energy Purchase Contracts (August 2022 - March 2025)

Approved Executive 2 papers

Cabinet Urgency procedure - Leader's Action approved this item on Wednesday 27 July 2022. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

Recommendations approved.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Cabinet Urgency procedure - Leader's Action

SLOUGH BOROUGH COUNCIL

REPORT TO: Cabinet - Urgency procedure - Leader's Action

DATE: 27th July 2022

SUBJECT: Corporate Energy Purchase Contracts (August 2022 – March 2025)

CHIEF OFFICER: Richard West

CONTACT OFFICER: Jason Newman/Savio DeCruz

WARD(S): All

PORTFOLIO: Cllr James Swindlehurst

KEY DECISION: Yes

EXEMPT: No

DECISION SUBJECT TO CALL IN: No

APPENDICES A: Appendix A - RMS - Power and Gas 2022-25_Strategy

1 Summary and Recommendations

This report outlines the extraordinary state of the wholesale energy market, and the options for purchasing energy volume under our two new commercial contracts:

 Corona Gas (commercial gas contract)  EDF electricity (commercial electricity contract)

The report recommends the approval of a new risk management strategy (RMS) to ‘purchase in advance’ all our commercial energy volume for the remainder of 2022/23. This strategy is following the Council’s brokers advice to limit our significant exposure to ever increasing Winter wholesale energy prices. Following this decision, the strategy will be to then review the market for financial years 2023/24 and 2024/25 based on energy volume and price.

The change in approach has come through the commodity market being extremely volatile following the war in Ukraine and with no certainty over what will happen next in the market. Officers are recommending that with this approval, the mitigation plan to reduce energy consumption is also adopted to further reduce the impact on the budget.

Officers have had discussions with the three PFI schools to notify them of the proposed decision. The expectation is that the schools will remain with the Council for 22/23 but either way the Council’s general fund will not be exposed to their decision. Recommendations:

Cabinet is recommended to:

1.1

i. Approve a change to the purchasing strategy to manage the risk of price volatility;

ii. Note that a report will be presented to Cabinet in Autumn 2022 on an energy volume reduction strategy.

Commissioner Review

“Commissioners are happy to support the report.”

2 Report

2.1Energy Contracts

2.2Slough Borough Council procured 7 new energy contracts in early April 2022. The 7 contracts covered housing, PFI schools, corporate assets and highways assets (Street lighting). These contracts have allowed the Council to still spot purchase to reduce some of the exposure to the Council.

2.3The Non-Half Hourly (NHH) Commercial, NHH Housing, Gas Housing, Half Hourly (HH) Housing and Unmetered Service (UMS) portfolios have been locked in to fixed priced contracts. The Unit rates and standing charges are fixed for full contract duration. Only HMRC taxes CCL & VAT are passed through at cost.

2.4The exposure to the General Fund for all contracts HH, NHH, Commercial and Unmetered Supplies is forecast at £3.4m. A further £1.4m is to be recharged to the PFI schools and £1.2m to social housing.

2.5The General Fund base budget for energy in 2022/23 financial year is £2.4m. The on- going fluctuation in the market now means that there is an in-year pressure of £1m.

2.6To further limit the exposure to all funds, officers are now recommending with advice from the Council’s brokers eEnergy, that the remaining energy is purchased for August 2022 to the end of the financial year.

2.6Once the energy price has been fixed there are proposals to reduce consumption across our street lighting, through changing street lighting lux levels, and NHH commercial assets (through asset disposal).

Energy Contracts and Stakeholders

2.19In summary we have awarded new energy supply contracts across our wide asset portfolio and have some legacy issues and costs still to resolve from our previous suppliers. Table 5 summaries the energy contracts, key stakeholders, and forecast energy in contract costs for 22/23. 2.20 Table 5 Slough Energy Contracts, forecast costs, and Stakeholders

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RMS: Power and Gas 2022-25_StrategyAppendix A 214 KB Download
PDF
Corporate Energy Purchase Contracts (August 2022: March 2025)Report 647 KB DownloadRead as text

At this meeting

Whole meeting
1Declarations of InterestDecided
2Corporate Energy Purchase Contracts (August 2022 - March 2025)This decision

Who was there

1 of 1 attended
JC
Councillor James C. SwindlehurstAttendee, present

On this subject at Slough

Search all
  1. Corporate Energy Purchase Contracts (August 2022 - March 2025)This decision
  2. Corporate Energy Procurement Strategy and Contracts (April 2022 - March 2025)Decided

More from Slough Cabinet Urgency procedure - Leader's Action

All decisions
MeetingDecisionOutcome
6 Jul 2026 Extra Care Housing Care and Support Service: Award of Contract to Hales Group LtdResolved – 1. Approved the award of the contract for the Extra Care Housing Care and Support Service at The Pines and... Approved Open
26 Mar 2026 Upton Hospital DevelopmentResolved – That it be agreed to: (a) Lease the site within Upton Hospital for the purpose of development of a new nei... Agreed Open
23 Oct 2025 Collection Fund Income Maximisation Partner - Contract AwardResolved – (a) That the award of the contract to Inform Holdings Ltd, trading as Analyse Local for a period of 3-year... Approved Open
11 Apr 2025 Mandatory licencing of Houses in Multiple Occupation feeResolved – That the changes to the mandatory Houses in Multiple Occupation (HMOs) licence fee as set out in Appendix ... Approved Open
30 Oct 2023 Procurement of Replacement of Fleet VehiclesResolved – (a) Approved entering into a new one-year vehicle contract lease with the new supplier Dawson Group Enviro... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies