Resolved
Resolved – (a) That the future schedule of one and five-year impact reports be noted. (b) That Members be updated via email or a report to the next meeting on the position regarding the overdue impact reports.
Berkshire Local Transport Body noted this item on Thursday 9 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – (a) That the future schedule of one and five-year impact reports be noted. (b) That Members be updated via email or a report to the next meeting on the position regarding the overdue impact reports.
1. At your meeting in July 2022, you approved a less intensive approach towards the impact reports being considered at this meeting to reflect the reduction in reporting requirements from government whilst still demonstrating the value of investment in infrastructure.
2. This report summarises the future programme of one-year and five year impact reports and indicates when they are due.
3. You are recommended to note the future schedule of one and five-year impact reports.
Supporting Information
4. The LEP has a well-established and agreed process for the monitoring and evaluation of BLTB funded local transport schemes, which requires scheme promoters to produce one- and five-year- on post completion monitoring reports for each of their schemes. With the reduction in the level of capital funding overseen by the LEP the monitoring and evaluation process was reviewed and made proportionate and fit for purpose, whilst continuing to demonstrate the value of our investment and to inform future priorities.
5. The format and detail of the reports are now less prescriptive and enable the scheme promoter to tailor the reports to their own needs and make them directly relevant to supporting investment decisions going forwards.
6. The reports submitted by each of the scheme promoters continue to summarise the outcomes of the monitoring and evaluation undertaken following the completion of the schemes. The analysis gives an initial indication whether a scheme has been successful in achieving the related aims and objectives set and agreed at the start of the scheme development. It also seeks to demonstrate that the funding obtained has provided value for money and that any lessons learnt are captured as evidence to inform future decision making. In particular the assessments focus on:
• Scheme build; • Delivered scheme; • Costs; • Scheme objectives; and • Impacts on the economy
Future Programme of Reports
7. Whilst there are no monitoring reports due to be reported to this meeting, it is a good opportunity to set out the programme of monitoring reports delivered to date and outline when future reports are due to be completed. Item 9 explains how BLTB may operate in the future so this report acts as a useful reference document as to when reports are expected. A new mechanism will need to be agreed as to how these reports are assessed and reviewed going forward as again the LEP has
Item 6 BLTB 9 March 2023 – One Year Evaluation Reports – Status Update been carrying out scrutiny, with the appointment of an interim transport consultant, following the decision not to renew the contract with Hatch Regeneris.
8. We currently anticipate that for the BLTBs to be held in July and November 2023 that the following reports will be submitted.
July 2023
One-Year Impact Reports
• Scheme 2.36 – Wokingham: Coppid Beech Park and Ride • Scheme 2.37 – Bracknell: A322 A329 Corridor Improvements • Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway
November 2023
One-Year Impact Reports
• Scheme 2.23 – Reading: South Reading MRT Ph 3-4
9. The full listing and schedule of impact reports is as follows:
Ref. Scheme Name Completion 1 Year Impact Report 5- Year Impact Report date
2.01Newbury: King’s Road Link Not yet TBC TBC Road completed
2.02Bracknell: Warfield Link Road Oct 18 Published Mar-20 Due Nov-24
2.03Newbury: London Road Mar-17 Published Jul-18 Overdue Industrial Estate
2.04Wokingham Roads -Arborfield Nov-20 Published Jul-22 Due Nov-26 Cross Relief Rd
2.05Newbury: Sandleford Park Dec-21 Overdue TBC
2.06Reading Green Park Station May-23 Due Jul-24 Due July-28
2.07Bracknell: Coral Reef Apr-16 Published Nov-17 Overdue Roundabout
2.08Slough Rapid Transit Phase 1 Mar 19 Published Mar-20 Due Mar-24
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
One Year Evaluation Reports: Status UpdateReport | 109 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.