Resolved
Resolved – That the revised Corporate Risks and Sub-Risks as at Quarter 1 FY25/26 (August 2025) be noted.
Audit and Corporate Governance Committee noted this item on Wednesday 10 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the revised Corporate Risks and Sub-Risks as at Quarter 1 FY25/26 (August 2025) be noted.
The Audit and Corporate Governance Committee is recommended to note the revised Corporate Risks and Sub-Risks as at Quarter 1 FY25/26 (August 2025).
Reason:
1.2Summarising the Council’s corporate risks for the Audit & Governance Committee ensures that Members are advised of the key risks facing the Council, and the extent to which they are being managed.
1.3Producing information in a format that supports the communication of the Council’s risk profile to Members is important to demonstrate good governance, and provide assurance that officers understand the nature of the Corporate Risks we face and are managing them effectively.
Commissioner Review This report is outside the scope for pre-publication commissioner review; please check the Commissioners’ instruction 5 to CLT to sign off papers for further details. 2. Report
Introductory paragraph
2.1The Council deals with risk every day from managing its infrastructure, delivering its services, managing its supply chains, maintaining safe systems for staff and residents and delivering on its strategic aims. Effective risk management is concerned with identifying material risks, assessing them in a consistent manner, and managing them to levels that are acceptable.
2.2To produce the Q1 2025/26 corporate risk report a full review of each of the current corporate risks was undertaken. The corporate risk report was initially presented at the Risk Management Board on the 21st August 2025 and after rigorous challenge it was signed off. The corporate risk report was then presented to the CLT on the 27th August and following discussion and challenge it was agreed that corporate risk CR02 should be renamed to Failure to meet demands on Adult Social Care within budget to better reflect the scope of the risk. It was also agreed that CR11 – Failure to become a best value council was too wide ranging and it is proposed to remove the risk and replace with a more focused one. Meetings to be arranged, before returning to CLT for review and approval. The CLT then approved the Q1 FY25/26 corporate risk report.
2.3The Q1 FY25/26 position is that the Councils risk exposure has marginally improved this quarter, however the overall exposure remains elevated but is being actively managed within the resource constraints. One risk score has improved, and one risk score has deteriorated. All corporate risks are reported as being in a stable position with no notable milestones missed in respect of the delivery of identified treatment plans.
2.4Of the fourteen identified corporate risks, ten are rated as red (risk score between 20 – 25), and four are rated as amber (risk score between 15 – 19). As the risk management programme becomes more mature there has been a marked confidence that the improved risk control environment will lead to further corporate risk scores improving by quarter 2 FY25/26.
2.5The full breakdown of our risks and sub-risks is provided in the table below.
Q1 FY25/26 Corporate Risk and Sub-Risk Summary Note:
Red risks are high-impact, high-likelihood risks that pose a severe threat to our objectives, operations, or strategic initiatives.
These risks require immediate attention and robust mitigation strategies. Score Impact Likliehood Current Target Prev. Qtr movement/ CR ref. Corporate Risk - Sub-Risk Score score Score Score Score Outlook last quarter
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Report Quarter 1Report | 1.3 MB | DownloadRead as text |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... | Approved | Open |
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.