Slough Borough Council
Cabinet, Monday 17 August 2026 at 6.30pm

Pride In Place Impact Fund

Decided Executive 1 paper

AI summarySlough Cabinet approves use of £1.5m Pride in Place Impact Fund across three project strands and a contingency, with all funding to be committed by March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUse of £1.5m grant allocated across four workstreams
Money£1.5m grant, split into four pots£0.374m, £0.466m, £0.500m and £0.160m
What happens nextProcure works and award fundingFunding agreements and contracts to be in place by September 2026
Who it affectsCommunity groups, residents, ward membersExternal partners and all Slough wards except Britwell and Foxborough

What was decided

Cabinet is asked to approve the £1.5m Pride in Place Impact Fund allocation across externally delivered community projects (up to £0.374m), children's play area improvements (up to £0.466m), a new Neighbourhood Pride in Place Improvement Programme (£0.500m), and a contingency of up to £0.160m. Report P2, P21, P33

Authority is delegated to the Executive Director of Regeneration, Environment and Planning, in consultation with ward members and the Leader, to award funding under the Neighbourhood Programme. Report P3

An equitable ward allocation model of around £25,000 per eligible ward is chosen as the preferred approach for the Neighbourhood Programme, instead of a competitive borough-wide fund. Report P31, P74

Why

Slough was awarded £1.5m of Pride in Place Impact Funding by MHCLG in November 2025, with all funding required to be committed by the end of March 2027 or returned. Report P5, P11, P33

The grant is intended to deliver visible improvements to high streets, public spaces and community assets in areas of need, supporting the Council's Corporate Plan priorities. Report P5, P6, P19, 2.2

Officers and Commissioners considered a 'do nothing' option (returning the money) and rejected it, recommending the three-pronged allocation as better aligned with corporate objectives. Report P16, P17, P20, P21

What happens next

Following Cabinet approval, funding agreements and contracts will be put in place with the 15 recommended external project delivery partners to ensure funding is committed by September 2026. Report P22, P26

An open call for the Neighbourhood Programme will be launched, with ward members invited to submit expressions of interest assessed by an officer panel. Report P22, P74

Progress will be reported to MHCLG through the funding monitoring portal, with the next report due in October 2026; the s.151/Finance Director will sign off monitoring returns. Report P22, P38

The money

  • £1.5m Total Pride in Place Impact Fund grant awarded to Slough by MHCLG Report P2, P11
  • £0.374m Up to £0.374m on externally delivered community focused projects (Appendix A) Report P2
  • £ 373,621 Total recommended external projects funding (Appendix A) Report P29, P68
  • £0.466m Up to £0.466m on capital works to children's play areas (Appendix B) Report P2
  • 466,000 Total estimated cost of 26 children's play area improvements (Appendix B) Report P69
  • £0.500m Neighbourhood Pride in Place Improvement Programme capital allocation Report P2, P31
  • £0.160m Contingency to manage the programme and deal with unforeseen contingencies Report P2, P21, P34
  • £1.85m Total value bid by 27 external applicants against a £0.45m pot Report P26

Options considered

  • Rejected: Do nothing: return the £1.5m to MHCLG. Would not contribute to the Council's Corporate Plan aims and objectives Report P16, P17
  • Chosen: Approve the three-pronged capital allocations plus contingency. Delivers enhancements to public spaces and local areas consistent with the fund's aims and the Council's priorities Report P18, P19, P20, P21
  • Chosen: Neighbourhood Programme, Option 1: equitable allocation of about £25,000 per eligible ward. Visible borough-wide investment, supports local democratic leadership and fair geographic distribution Report P31, P74
  • Rejected: Neighbourhood Programme, Option 2: competitive borough-wide fund. Reduces geographic equity, lowers visibility and risks neighbourhood priorities being overlooked Report P31

Implications

  • Financial: The Council's s.151 officer must have oversight; uncommitted funds by 31 March 2027 must be returned to MHCLG, and any ongoing revenue maintenance costs must be met from existing revenue budgets. Report P33, P35, P36, P38
  • Legal: The Council is the accountable body and must comply with grant conditions, the Subsidy Control Act 2022, procurement law, fraud prevention requirements and a £10k capital de minimis threshold; third parties will be bound by grant agreements. Report P35, P37, P38, P39
  • Risk: Key risks include projects not being committed by 31 March 2027, objections delaying the open call, low community engagement, and future maintenance liabilities; mitigations include strong deliverability criteria, officer panels, clawback clauses and clear communications. Report P41, P42, P43, P44, P45
  • Equalities: An Equality Impact Assessment will be completed as part of programme implementation, with particular regard to improving access for residents experiencing disadvantage or barriers to participation. Report P50
  • Climate: Individual projects will be encouraged to maximise environmental benefit where practical, supporting greener public spaces. Report P48, P49
  • Other: Procurement will follow the Council's contract procedure rules for council-led works; external projects must follow their own procurement processes. Report P51

Who and where

  • Community and voluntary sector groups receiving external project funding (15 recommended projects across the borough) Report P26, P68
  • Children and families using 26 children's play areas identified for investment (excluding Salt Hill Park and Upton Court Park) Report P30, P69
  • Residents and ward members in all Slough wards except Britwell and Foxborough, who are invited to submit expressions of interest under the Neighbourhood Programme Report P78, P74
  • MHCLG as the funder, who will receive monitoring returns via the funding portal Report P22, P38

Timeline

  • November 2025: Slough awarded £0.750m for 25/26 and £0.750m for 26/27 under the Pride in Place Impact Fund Report 2.1
  • February 2026: Initial MHCLG progress report submitted and accepted Report P22
  • June 2026: Second MHCLG report submitted and accepted Report P22
  • July 2026: Cabinet previously approved adding the £1.5m to the capital programme Report P33
  • 17 August 2026: Cabinet decision on allocation of the fund across four workstreams
  • September 2026: Target for funding agreements with external project delivery partners to be in place; next MHCLG report due Report P22, P26, P43
  • October 2026: Further ward-based project information to be reported to MHCLG Report P22
  • 31st March 2027: All £1.5m must be committed, otherwise unspent funds returned to MHCLG Report P11, P33, P45

Plain English for the jargon

  • PIPIF (Pride in Place Impact Fund): Capital grant from MHCLG awarded to 95 places to deliver visible improvements to high streets, public spaces and community assets, to be committed by 31 March 2027.
  • MHCLG: Ministry of Housing, Communities and Local Government, the UK Government department providing the grant.
  • Neighbourhood Pride in Place Improvement Programme: A new £0.500m Slough programme inviting ward members to propose local capital projects of around £25,000 per eligible ward.
  • De minimis threshold: The £10k minimum capital spend per asset required by the Council's capitalisation policy for expenditure to be treated as capital.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48

Resolved

View the decision text for item 48.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet is recommended to:

(a) Approve the use of the £1.5m Pride in Place Impact Fund grant funding added to the capital programme in July 2026 to deliver the projects as follows: (i) Up to £0.374m on externally delivered community focused projects as set out in Appendix A (ii) Up to £0.466m on capital works on children’s play areas across the Borough as set out in Appendix B (iii) £0.500m under a Neighbourhood Pride in Place Improvement Programme in accordance with the policy at Appendix C . iv) Up to £0.160m contingency to be utilised to manage the programme and deal with any unforeseen contingencies.

(b) Delegate to the Executive Director of Regeneration, Environment & Planning in consultation with ward members and the Leader of the Council, to make decisions to award funding to projects under the Neighbourhood Pride in Place Improvement Programme.

Reason:

In the 2025 Spending Review, the Government announced funding for up to 350 places as the cornerstone of support for communities. This included 95 places selected for the Pride in Place Impact Fund. The funding will be delivered by local authorities in England, Scotland and Wales and targeted at areas ‘in need’ with the aim of building strong, resilient, prosperous, and inclusive communities.

The Pride in Place Programme as a whole will target transformation over the longer term with the Pride in Place Impact Fund providing immediate support to ensure areas are able to deliver visible improvements to high streets and improve places and spaces of community value. Slough has been awarded PIPiF of £1.5m to March 2027, with all funding to be committed by that date. The funding is all capital with no revenue allocation. PIPIF is distinct from the wider PIP programme which provides significantly more funding over a period of ten years and requires significant stakeholder engagement including the establishment of neighbourhood boards. This is not a requirement of the PIPIF programme. The approach taken as set out below has been developed in consultation with lead Members.

Commissioner Review

This investment provides a unique opportunity to enable the Council to deliver not only on its own corporate priorities, but also to respond quickly and effectively to the priorities of local people and stakeholders. As the accountable body it is essential that robust governance and administration processes are in place with appropriate due diligence on receiving bodies and deliverability of match funded sources.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pride In Place Impact FundReport 226 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
WC
Councillor Wal ChahalChair, present
EA
Councillor Ejaz AhmedVice-Chair, present
IA
Councillor Iftakhar AhmedCommittee Member, present
PB
Councillor Puja BediCommittee Member, present
NK
Councillor Nadeem KhawarCommittee Member, present
GM
Councillor Gurcharan MankuCommittee Member, present
ZS
Councillor Zafar SattiCommittee Member, present
IS
Councillor Ishrat ShahCommittee Member, present
MS
Councillor Mabu ShaikCommittee Member, apologies
AW
Councillor Anna WrightCommittee Member, present
NP
Nicholas PontoneDemocratic Services Officer, expected
MI
Councillor Mark InstoneGuest, in attendance

All 13 on the meeting page

On this subject at Slough

Search all
  1. Pride In Place Impact FundThis decision
  2. Pride in Place - Britwell and FoxboroughDecided

More from Slough Cabinet

All decisions
MeetingDecisionOutcome
19 Oct 2026 Declarations of InterestView the decision text for item 1. Decided Open
19 Oct 2026 Minutes of the Meeting held on 21st September 2026View the decision text for item 2. Decided Open
19 Oct 2026 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. Decided Open
19 Oct 2026 Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. Decided Open
19 Oct 2026 Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies