Slough Borough Council
Cabinet, Monday 17 August 2026 at 6.30pm

Thames Valley Spatial Development Strategy (SDS) Development and Governance

Decided Executive 2 papers

AI summarySlough Cabinet received appendices setting out the Thames Valley Strategic Development Study budget at £4,735,700 total, with £2,521,700 still sought from MHCLG beyond the £764,000 grant confirmed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedTVSDS budget and funding breakdown noted
Money£4,735,700 total, £2,521,700 still requiredIncludes £617,700 contingency on £4,118,000 sub-total
What happens next30 month delivery assumedTechnical study costs still need verifying
Who it affectsThames Valley partner authoritiesPre and post Local Government Reorganisation

What was decided

Cabinet received the appendices for item 49, which set out the funding and finance annex, the high level programme timeline and the governance and resources annex for the TVSDS. Report P1

Why

The appendices detail projected indicative costs across resources and technical support, commissions for studies, evidence and support, a 15 per cent contingency, and how the funding is to be split between MHCLG grant, work in kind and local authority contributions. Report P2, P3

What happens next

Technical study costs need verifying, with possible savings through joint commissioning; the project assumes a 30 month delivery programme running into 2028/29. Report P2, P3

The money

  • £614,600 Resources and technical support, 2026/27 work in kind Report P2
  • £724,000 Resources and technical support, 2027/28 work in kind Report P2
  • £755,000 Resources and technical support, 2028/29 work in kind Report P2
  • £2,393,000 Commissions, studies, evidence and support across all years Report P2
  • £1,725,000 Commissions 2026/27 Report P2
  • £4,118,000 Sub-total of project costs Report P2
  • £617,700 Contingency at 15 per cent Report P2
  • £4,735,700 Total estimated funding required Report P2
  • £764,000 Revenue MHCLG grant funding Report P3
  • £300,000 Work in kind across three years at £100,000 each Report P3
  • £1,150,000 Local contributions across three years Report P3
  • £2,214,000 Confirmed funding sub-total Report P3
  • £2,521,700 Additional MHCLG funds still required Report P3

Options considered

  • Rejected: Joint commissioning of studies to reduce cost. Possible savings identified but not adopted; technical study costs need verifying Report P3

Implications

  • Financial: A funding gap of £2,521,700 remains between confirmed sources and the £4,735,700 total cost, requiring further MHCLG support. Report P2, P3
  • Risk: Technical study costs are unverified and Oxfordshire's £150,000 contribution only runs until Local Government Reorganisation. Report P3

Who and where

  • Partner authorities across the Thames Valley, including Oxfordshire Report P3
  • Future unitary councils created through Local Government Reorganisation from April 2027 Report P3

Timeline

  • 2026/27: First year of programme delivery, with £1,725,000 of commissioned work Report P2, P3
  • April 2027: Local Government Reorganisation assumed to take effect, with £50,000 per partner authority contribution Report P3
  • 2027/28: Second year of delivery, including higher commission spend Report P2
  • 2028/29: Final year of the assumed 30 month programme Report P2, P3

Plain English for the jargon

  • TVSDS: Thames Valley Strategic Development Study referenced in the appendices
  • MHCLG: Ministry of Housing, Communities and Local Government, the grant funder
  • WIK / WiK: Work in kind, non-cash contributions valued at £100,000 per year
  • LGR: Local Government Reorganisation, expected from April 2027
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49

Resolved

View the decision text for item 49.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Cabinet

Annex 1 – Funding and Finance

TVSDS Projected Indicative Budget - Working Draft Costs Operations 2026/27 Work In- 2027/28 Work In- 2028/29 Work In- Total Kind Kind Kind (WiK) (WiK) (WiK) Resources and Technical £614,600 £100,000 £724,000 £100,000 £755,000 £100,000 support 2,393,000 Commissions Studies/Evidence/Support 1,725,000 £825,000 £500,000 £400,000 Sub-Total £4,118,000 Contingency @15% £617,700 Total Estimated funding required: £4,735,700

Revenue MHCLG Grant Funding £764,000 unknown unknown £764,000 Work -in-Kind (WIK) £100,000 £100,000 £100,000 £300,000 Contributions Local Contributions (see £150,000 £500,000 £500,000 £1,150,000 note 2) Sub-Total £2,214,000 Proposed additional MHCLG Funds required £2,521,700 Notes 1. Assumes 30 month delivery programme 2. Local contribution divided per council pre and post LGR - est. £50k per partner authority from April 2027.Oxfordshire paying £150k until LGR. WiK is flexible and may be shared between FSA workstreams and SDS. 3. Technical study costs need verifying. Savings possible if joint commissioning. Annex 2 – High Level Programme & indicative timeline (working draft) Annex 3 - Governance and resources

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendicesReport 302 KB DownloadRead as text
PDF
Thames Valley Spatial Development Strategy (SDS) Development and GovernanceReport 129 KB Download

At this meeting

Whole meeting
47Declarations of InterestDecided 48Pride In Place Impact FundDecided
49Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThis decision

Who was there

9 of 13 attended
WC
Councillor Wal ChahalChair, present
EA
Councillor Ejaz AhmedVice-Chair, present
IA
Councillor Iftakhar AhmedCommittee Member, present
PB
Councillor Puja BediCommittee Member, present
NK
Councillor Nadeem KhawarCommittee Member, present
GM
Councillor Gurcharan MankuCommittee Member, present
ZS
Councillor Zafar SattiCommittee Member, present
IS
Councillor Ishrat ShahCommittee Member, present
MS
Councillor Mabu ShaikCommittee Member, apologies
AW
Councillor Anna WrightCommittee Member, present
NP
Nicholas PontoneDemocratic Services Officer, expected
MI
Councillor Mark InstoneGuest, in attendance

All 13 on the meeting page

On this subject at Slough

Search all
  1. Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThis decision
  2. Section 75 Agreement with the NHS Thames Valley Integrated Care Board to govern the delivery of the Better Care Fund 2026-2027Decided
  3. Thames Valley Devolution - Expression of InterestDecided
  4. Report from the Thames Valley Police and Crime CommissionerNoted
  5. Thames Valley Berkshire Capital Programme UpdateNoted
  6. Thames Valley Berkshire Capital Programme UpdateNoted

More from Slough Cabinet

All decisions
MeetingDecisionOutcome
19 Oct 2026 Declarations of InterestView the decision text for item 1. Decided Open
19 Oct 2026 Minutes of the Meeting held on 21st September 2026View the decision text for item 2. Decided Open
19 Oct 2026 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. Decided Open
19 Oct 2026 Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. Decided Open
19 Oct 2026 Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies