Resolved
(i) That the current financial position be noted and supported the actions taken to address budget variances; and (ii) That the budget virements made for the second quarter of 2013/14 summarised in Appendix A be approved.
Cabinet noted this item on Thursday 14 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) That the current financial position be noted and supported the actions taken to address budget variances; and (ii) That the budget virements made for the second quarter of 2013/14 summarised in Appendix A be approved.
1.1To inform Full Cabinet of the financial position as at the end of September 2013. 1.2 This report to Full Cabinet summarises the reports to the individual Cabinet portfolio meetings. 1.3 This report also provides details of all the budget virements which have taken place during the second quarter, as required by Financial Regulations and the revised budget resulting from those virements, which Members are asked to approve. See Appendix A for more details.
2. Decision(s) Recommended
2.1Note the current financial position and determine whether any further actions are required to address budget variances. 2.2 Approve the budget virements made for the second quarter of 2013/14 summarised in Appendix A.
3.1Financial monitoring is carried out throughout the year by individual budget holders. Key income and expenditure risk areas are monitored monthly by Accountancy. Identified financial risks are discussed with Heads of Service and significant risks are reported monthly to Directorate Leadership Teams (DLTs) and the Corporate Leadership Team (CLT) to ensure that net expenditure is managed within approved budgets. 3.2 The 2013/14 budget includes savings of £7.178 million in line with the current Medium Term Financial Strategy (MTFS).
4. Revenue Budget – Forecast out-turn position
Forecast out-turn position for the current financial year 4.1 There is a forecast variance for Core Council of £1.575 million, and £429,000 for the DSG, which is summarised by portfolio below. The forecast includes the position on the delivery of all of the 2013/14 MTFS budget savings.
Cabinet Portfolio Revised Projected Variance Budget Outturn to Budget 2013/14 £m £m £m Leader and Resources 23.006 23.061 0.055 Education, Children and Young People 36.040 36.095 0.055 Health & Wellbeing 54.532 54.532 0 Environmental and Community 18.025 17.734 (0.291) Services Community Cohesion and Partnerships 2.026 1.967 (0.059) Economic Development and 3.593 3.303 (0.290) Regeneration Transport and Highways 6.459 6.821 0.362 Levies (including Non Domestic Rates) 37.824 39.454 1.630 Employers Pension Contribution 0 0.113 0.113 Core Council Sub-Total 181.505 183.080 1.575 Dedicated Schools Grant (DSG) 0.990 1.419 0.429 TOTAL 182.495 184.499 2.004
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 16 KB | Download |
PDF |
REVENUE AND CAPITAL MONITORING: QUARTER 2 (END OF SEPTEMBER) 2013/14)Report | 49 KB | DownloadRead as text |
Follow Cabinet at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... | Approved | Open |
| 17 Sep 2026 | Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... | Agreed | Open |
| 17 Sep 2026 | Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... | Decided | Open |
| 23 Jul 2026 | Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... | Approved | Open |
| 23 Jul 2026 | Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.