Solihull Metropolitan Borough Council
Cabinet, Thursday 17 September 2026 at 6.00pm

Kingshurst Village Centre Regeneration - Phase 2

Agreed Executive 1 paper

AI summarySolihull Cabinet approves Phase 2 of the Kingshurst Village Centre regeneration, contracting Willmott Dixon to build a new Community, Health and Retail building, six homes and a vicarage at a total cost of £23.868m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedAward of contract to Willmott Dixon authorised
Money£23.868m total project costFunded from borrowing, grants, CIL, receipts and reserves
What happens nextWillmott Dixon to be appointedLetter of intent before contract signing for utility work
Who it affectsKingshurst residents and visitorsNew community, health, retail, housing and vicarage facilities

What was decided

Cabinet approved construction of Phase 2, comprising an integrated Community, Health and Retail building, six new dwellings, a new vicarage and enabling infrastructure, and authorised entry into a contract with Willmott Dixon. Report P8, P9

Cabinet approved the funding of the contract and project costs from the sources set out in paragraphs 6.4.1 to 6.4.4 and Appendix 2. Report P10

Cabinet noted that a breakdown of the consultation sessions with residents would be shared with Members, and approved the £0.285m revenue budget for 2026/27 being placed in a reserve to meet borrowing costs in 2027/28 and 2028/29, with the residual balance paid into a sinking fund from 2029/30. Report P11, P12

Why

The centre has been in decline, the existing GP surgery is not fit for modern clinical use, and the preferred option delivers the highest value for money, with a benefit-cost ratio of 2.6:1. Report P30, P43, P58

Phase 2 is needed to relocate key services from the existing Marston Drive building so it can be demolished, unlocking a further 47 affordable homes in Phase 3. Report P57

The CHR building will co-locate GP, pharmacy, dental, optician, public health and community services, supporting prevention, tackling health inequalities and reducing pressure on acute NHS services. Report P60, P63, P71

What happens next

Officers will issue a letter of intent to Willmott Dixon, if needed, to allow utility provider instructions, then sign the JCT 2016 Design and Build contract. Report P9, P97

A formal bid for Homes England grant funding towards the six houses will be submitted, with a decision expected within six weeks, and a binding funding agreement with WMCA is to be entered into. Report P35, P36

Enterprise Zone Partnership Board written approval is being sought ahead of Cabinet, with a verbal update given at the meeting, and the £0.285m MTFS allocation will be moved to a reserve and later a sinking fund. Report P34, P93, P96

The money

  • £23.868m Total cost of Phase 2, including CHR building, vicarage, six homes, enabling works and project team costs Report P86
  • £21.217m General Fund element of the project cost Report P87, P89
  • £2.651m Housing Revenue Account element of the project cost Report P87, P91
  • £0.285m Annual MTFS revenue allocation for 2026/27, to be set aside in a reserve then sinking fund Report P94, P96
  • £0.053m Forecast uncommitted annual MTFS balance from 2029/30 for the sinking fund Report P96

Options considered

  • Rejected: Do not progress Phase 2 (do nothing). Existing centre would continue to deteriorate, critical local services and facilities would be lost, and the vacant brownfield site would continue to incur management and maintenance costs Report P41, P43, P44, P45
  • Rejected: Retain and refurbish the existing Marston Drive and GP practice buildings instead of rebuilding. Buildings are considered life-expired and refurbishment is likely uneconomic, the scheme would not deliver the comprehensive regeneration the community supported in consultation, and no budget is in place Report P46, P48, P49, P50, P51, P52
  • Chosen: Proceed with the proposed Phase 2 development (preferred). Delivers the highest value for money at a BCR of 2.6:1, supports health, community and housing objectives, and unlocks Phase 3 affordable homes Report P30, P53, P54, P58

Implications

  • Financial: Total capital cost of £23.868m, of which £21.217m sits on the General Fund and £2.651m on the Housing Revenue Account, with prudential borrowing supported by future tenant rents. Report P86, P87, P89, P91, P93
  • Financial: The £0.285m annual MTFS allocation is to be ringfenced in a reserve in 2026/27 to cover borrowing costs in 2027/28 and 2028/29, then redirected into a sinking fund from 2029/30 to mitigate landlord risks on the CHR building. Report P94, P96
  • Legal: A JCT 2016 Design and Build contract will be entered into with Willmott Dixon under the Constructing West Midlands Framework, with legal due diligence carried out by the Council's Legal Services team. Report P97, P98, P109
  • Equalities: The scheme is expected to have positive impacts across all protected characteristics, with particular benefits for children, older people, people with disabilities and those needing maternity support; a Fair Treatment Assessment will be monitored throughout the project. Report P70, P106
  • Climate: The project responds to the Council's Climate Change Declaration and Net Zero Action Plan, aiming to improve energy efficiency of dwellings and use zero carbon technologies in residential and commercial elements. Report P76
  • Risk: Risks around delivery timescales, funding, affordability, community confidence and long-term sustainability are managed through contractor engagement, independent cost reviews, value engineering, a project risk register and a sinking fund. Report P99, P100, P101, P102, P103, P105
  • Staffing: Solihull Community Housing's offices will relocate from Endeavour House into the new CHR building, and the CHR will be supported by anchor tenants including GP services commissioned by the Integrated Care Board and the Co-op. Report P18, P105, P113

Who and where

  • Kingshurst residents and the wider North Solihull community, who will gain a new community, health, retail, library and café facility, plus six new social rented homes Report P1, P2, P56, P70
  • Solihull Community Housing (SCH) staff, whose offices will relocate into the new CHR building from Endeavour House Report P18, P19
  • GP, pharmacy, dental, optician and public health tenants and patients of the new CHR building, including the ICB which is supporting GP lease negotiations Report P19, P105, P113
  • Local parish council, ward members and community organisations engaged through drop-in sessions in November 2025, March 2026 and July 2026 Report P80, P82
  • Future residents of Phase 3, as Phase 2 is required to unlock a further 47 affordable homes by enabling demolition of the Marston Drive building Report P57
  • The Diocese and the parish served by the new vicarage included in the scheme Report P1, P8, P56

Timeline

  • 27 April 2022: Full planning permission granted for the whole development (PL/2021/03072/MAJFDW) Report P15
  • June 2023: Cabinet approved delivery of Phase 1 comprising 25 social rented dwellings and park enhancements Report P16
  • September 2024: Construction of the 25 new homes in Phase 1 completed Report P16
  • January 2025: Cabinet delegated authority to proceed to RIBA Stage 4 design and costing for Phase 2 Report P16
  • 17 November 2025: Mayor, residents and pupils from St Anthony's Primary School took part in a bulb planting event as part of the park contractor's social value contribution Report P17
  • December 2025: Cabinet approved design works, FBC preparation and the relocation of SCH into the new CHR building; Kingshurst Park enhancements completed Report P17, P18
  • February 2026: Willmott Dixon appointed under the existing PCSA to undertake the internal redesign and RIBA Stage 4 costing Report P22
  • June 2026: Willmott Dixon submitted the full RIBA Stage 4 Cost Package and contract offer; WMCA Investment Panel endorsed the FBC Report P26, P35
  • July 2026: Full Business Cases submitted to Birmingham City Council and the WMCA Investment Board approved the FBC for Investment Programme funding Report P27, P34, P35
  • 2026/27: £0.285m revenue budget held in reserve rather than spent Report P94
  • 2027/28 and 2028/29: Reserve used to meet borrowing costs until tenant rents are received Report P94
  • From 2029/30: Residual £0.053m per annum of the MTFS allocation contributed to a sinking fund against landlord risks on the CHR building Report P96

Plain English for the jargon

  • CHR building: Community, Health and Retail building, the integrated facility at the heart of Phase 2, with GP, pharmacy, dental, optician, library, community and café space
  • Phase 2: Construction of the CHR building, a new vicarage, six social rented homes and associated infrastructure works
  • Phase 3: A later phase expected to deliver 47 affordable homes on the Marston Drive site after it is vacated
  • MTFS: Medium Term Financial Strategy, the Council's multi-year revenue budget and planning framework
  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spend
  • CIL: Community Infrastructure Levy, a developer contribution used to fund infrastructure
  • JCT 2016 Design and Build: A standard form construction contract placing both design and build responsibility with the contractor for a lump sum
  • PCSA: Pre-Construction Services Agreement, an early engagement contract used before the main construction contract is signed
  • RIBA Stage 4: The Royal Institute of British Architects' detailed design stage, used here to fix the contract price
  • BCR: Benefit Cost Ratio, the ratio of monetised benefits to costs used in the Economic Case
  • FBC / OBC: Full Business Case and Outline Business Case submitted to external funders
  • WMCA: West Midlands Combined Authority, a regional body providing Investment Programme funding
  • EZRIF / Enterprise Zone: Enterprise Zone Regional Investment Fund, a funding mechanism for the former Greater Birmingham and Solihull LEP area
  • CWM Framework: Constructing West Midlands Framework, a procurement framework used to appoint Willmott Dixon
  • FTA: Fair Treatment Assessment, the Council's equality impact assessment for the project
  • EBNS: East Birmingham North Solihull, a WMCA-defined regeneration area covering Kingshurst
  • ICB: Integrated Care Board, the NHS body supporting the GP provider and reimbursable rent
  • Sinking fund: A reserve built up over time to meet future one-off or major costs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED that 1. the positive progress made since the last report to Cabinet in December 2025 be noted. 2. the construction of Phase 2 of the Kingshurst Regeneration Project, comprising an integrated Community, Health and Retail (CHR) building, associated enabling works, and the delivery of six new dwellings alongside a new vicarage and associated infrastructure works be approved. 3. the Director for Economy and Infrastructure and the Director of Resources be authorised, in consultation with the Leader of the Council, to enter into contract with Willmott Dixon for the construction of Phase 2 of the Kingshurst Regeneration Project and, prior to entering into contract, to provide a letter of intent to Willmott Dixon to allow instructions to be placed with utility providers. 4. it be approved that the costs associated with the award of contract to Willmott Dixon and associated project costs be funded through the various sources summarised at paragraphs 6.4.1 to 6.4.4 of the report and as detailed in Section 1 of Appendix 2 to the report. 5. it be approved that the £0.285m revenue budget for 2026/27 is contributed to a reserve for the purpose of meeting borrowing costs in 2027/28 and 2028/29 as set out in paragraphs 6.4.5 to 6.4.6 to the report. 6. it be approved that the residual balance of the annual £0.285m MTFS allocation is contributed to a sinking fund from 2029/30 for the purpose of mitigating future financial risks to the Council arising from its role as landlord of the CHR building as set out at paragraph 6.4.7 of the report. 7. the Director of Economy and Infrastructure and the Director of Resources be authorised, in consultation with the Leader of the Council, to approve and sign the contractual agreements associated with the award of grants from the Enterprise Zone, West Midlands Combined Authority (WMCA) and Homes England.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Cabinet

Executive summary

This report seeks Cabinet approval to progress Phase 2 of the Kingshurst Regeneration Project into delivery. Building on the successful completion and positive progress of earlier phase 1 works and Kingshurst Park improvements, Phase 2 represents a significant milestone in the wider regeneration of Kingshurst and will deliver a new integrated Community, Health and Retail (CHR) facility, associated enabling works, six new dwellings, a replacement vicarage and associated infrastructure including new highways and car parking.

The proposals contained within this report will enable the project to move from the development stage into the construction phase of the project, supporting the continued transformation of Kingshurst through improved community infrastructure, enhanced healthcare provision, new retail opportunities and the delivery of affordable housing. The scheme has been developed through extensive partnership working and aligns with the Council’s strategic objectives for inclusive growth, place-making, health improvement and community wellbeing.

Cabinet is asked to approve the progression of the project and to delegate authority to the Director for Economy and Infrastructure and the Director of Resources, acting in consultation with the Leader of the Council, to enter into a construction contract with Willmott Dixon for the delivery of Phase 2. The delegation will also enable a letter of intent to be issued, if required, to facilitate early utility provider instructions and maintain project programme milestones.

The report seeks further approval for the funding arrangements associated with the construction contract and related project costs, as detailed within the report and accompanying private appendix. In addition, authority is requested for the Director of Economy and Infrastructure and the Director of Resources, acting in consultation with the Leader of the Council, to agree and execute the necessary contractual arrangements linked to grant funding from the Enterprise Zone, West Midlands Combined Authority (WMCA) and Homes England.

2. Decision(s) Recommended

That Cabinet:

Notes the positive progress made since the last report to Cabinet in December 2025.

Approves the construction of Phase 2 of the Kingshurst Regeneration Project, comprising an integrated Community, Health and Retail (CHR) building, associated enabling works, and the delivery of six new dwellings alongside a new vicarage and associated infrastructure works.

Delegates authority to the Director for Economy and Infrastructure and the Director of Resources, acting in consultation with the Leader of the Council, to enter into contract with Willmott Dixon for the construction of Phase 2 of the Kingshurst Regeneration Project and, prior to entering into contract, to provide a letter of intent to Willmott Dixon to allow instructions to be placed with utility providers.

Approves that the costs associated with the award of contract to Willmott Dixon and associated project costs be funded through the various sources summarised at paragraphs 6.4.1 to 6.4.4 of this report and as detailed in Section 1 of Appendix 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kingshurst Village Centre Regeneration: Phase 2Report 404 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
JH
Jackie HillOfficer, expected
RW
Rachael WardOfficer, expected
KG
Councillor Karen Grinsell Leader, Lead Member for Children & EducationCommittee Member, present
HD
Councillor Heather Delaney Deputy Leader, Economy, Business & Skills PortfolioCommittee Member, present
TD
Councillor Tony Dicicco Adult Social Care and Health PortfolioCommittee Member, present
KH
Councillor Ken Hawkins Environment & Infrastructure PortfolioCommittee Member, apologies
AM
Councillor Andy Mackiewicz Climate Change & Planning PortfolioCommittee Member, present
MP
Councillor Mark Parker Housing PortfolioCommittee Member, present
DP
Councillor Dave Pinwell Resources PortfolioCommittee Member, present, as expected, virtual
WQ
Councillor Wazma Qais Communities PortfolioCommittee Member, present
SG
Councillor Samantha Gethen Reform UK Group Leader (Non-Voting Member)Committee Member, present
AA
Councillor Ade Adeyemo Liberal Democrat Group Leader (Non-Voting Member)Committee Member, present

All 17 on the meeting page

On this subject at Solihull

Search all
  1. Kingshurst Village Centre Regeneration - Phase 2This decision
  2. Kingshurst Village Centre RegenerationApproved
  3. Kingshurst Village Centre RegenerationApproved
  4. Kingshurst Village Centre RegenerationApproved
  5. Kingshurst Village Centre RegenerationApproved
  6. Kingshurst Village CentreNoted

More from Solihull Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... Approved Open
17 Sep 2026 Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... Decided Open
23 Jul 2026 Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... Approved Open
23 Jul 2026 Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... Agreed Open