Resolved

RESOLVED – Members approved that the Section 106 Agreement be varied to provide the requirement for a financial contribution to be made only if the triggers referred to in the report (and update note) are exceeded, and appropriate Permitted Development rights are excluded accordingly ..
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Planning Committee

Purpose of report

To seek approval to removal of the requirement for the developer to provide a financial contribution towards the provision of highway works on the A34 Stratford Road.

Background

The application is for the removal of a planning obligation for a £560k contribution (index linked from 2002) for highway works at A34 Stratford Road/Monkspath Hall Road roundabout secured as part of development at Solihull Business Park.

Solihull Business Park was granted planning consent for 46,450sqm of B1 office space in 2002. A planning condition attached to the consent secured the implementation of works to improve capacity at A34 Stratford Road/Monkspath Hall roundabout prior to the occupation of 6,968sqm of floor space.

In March 2004, it was agreed between the highway authority and the developer that £560k would be paid to the Council in lieu of the capacity improvement scheme required by planning condition so as to allow the highway authority to better plan and deliver a scheme to take account of the wider growth that, at the time, was considered likely to come forward on the A34 Stratford Road corridor.

A scheme was subsequently identified comprising the part signalisation of A34 Stratford/Monkspath Hall roundabout with a total estimated scheme cost of £1.5million plus costs associated with the acquisition of some land in private ownership. The complete funding for the scheme was predicated on pooling section 106 contributions from a number of developments that, at the time, were considered likely to come forward and which would have had material traffic impacts at A34 Stratford Road/Monkspath Hall Road roundabout. Whilst a further Section 106 contribution for £500k was agreed as part of an approved B&Q superstore development at the Dave and Busters/David Lloyd Gym site at Highlands Road in 2008, this development has not been implemented and the site has now been developed as car showrooms with no Section 106 transport obligations due to their limited impact on the network. No other appropriate development has since come forward and the only planning obligations relating to the A34 Stratford Road /Monkspath Hall roundabout is that related to Solihull Business Park.

In 2009 a planning application was submitted for Solihull Business Park which refreshed the 2002 outline consent. The approval for this application included the £560k Section 106 sum with the trigger being the commencement of any further development at the site. In 2011 consent was granted to provide 16,000sqm of mixed use B1, B2 and B8 development within the site. The transport assessment for this application demonstrated that a B1/B2/B8 led development would result in the Business Park generating significantly fewer trips than the 46,450sqm wholly B1 led scheme approved in 2002. The transport assessment did not however include a junction assessment to evaluate the relative impact of the alternative development on the A34 Stratford Road/Monkspath Hall roundabout and, in the absence of any evidence to the contrary, the £560k contribution was again considered necessary, sought and agreed for this development.

At present, the permitted floor areas at Solihull Business Park are split into 14 plots. Five of the plots have been developed and provide a total of 5,585sqm of B1 office space, two plots have been developed into a Porsche showroom, a further two have extant consent for further 1,850 of B1 office space but are undeveloped and the remaining five plots have extant consent for B1/B2/B8.

Proposed Development and Traffic Impact

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Location PlanPlan 520 KB Download
PDF
Variation to Legal Agreement attached to Planning Application 2010/2032Report 49 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
DB
Councillor David BellChairman, present
HA
Councillor Howard AllenCommittee Member, present
DC
Councillor Don CornockCommittee Member, present
KH
Councillor Ken HawkinsVice-Chairman, present
RH
Councillor Robert HullandCommittee Member, present
AM
Councillor Alan MartinCommittee Member, present
GS
Councillor Glenis SlaterCommittee Member, present
JW
Councillor John WindmillCommittee Member, present
KG
Councillor Karen GrinsellSubstitute, present as substitute
JR
Councillor Jim RyanCommittee Member, apologies

More from Solihull Planning Committee

All decisions
MeetingDecisionOutcome
17 Jun 2026 Birmingham Airport Night Flying Policy Sub-CommitteeRESOLVED That Councillors Bob Grinsell (Chairman), Jane Lamden and David Hoey were elected to sit on the Birmingham A... Decided Open
27 May 2026 Appointment of chairmanRESOLVED Councillor Bob Grinsell was elected Chairman for the Municipal Year 2026/27. Decided Open
27 May 2026 Appointment of vice-chairmanRESOLVED Councillor James Bradley was elected Vice-Chairman for the Municipal Year 2026/27. Decided Open
21 May 2025 Appointment of ChairmanRESOLVED Councillor Bob Grinsell was elected Chairman for the Municipal Year 2025/26. Decided Open
21 May 2025 Appointment of Vice-ChairmanRESOLVED Councillor Prish Sharma was elected Vice-Chairman for the Municipal Year 2025/26. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies