RESOLVED – That the revised phasing programme, set out within the report, be approved on the basis that the retail stores may commence trading from April 2014. Councillor Allen wished it be recorded that he voted against the resolution, and that he considered Councillor Hulland may have a conflict of interest due to his role as a Cabinet Member and his involvement in Shirley Library.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
To seek approval to amendments to the phasing condition relating to the Parkgate development in Shirley.
Background
The planning application was allowed on appeal, following a public inquiry, in July 2011. The Inspector attached a number of conditions to the approval, some of which require certain details to be submitted to and approved by the Council before development commences (these are known as pre-commencement conditions). Others require approval of details prior to occupation and the remainder include on- going post occupation controls.
At the Planning Committee on the 13th June 2012 members approved the discharge of the more significant pre-commencement conditions, one of which related to the phasing of the development.
The condition states:
“Before the development hereby approved commences a phasing plan identifying all phases of development shall be submitted to and approved in writing by the Local Planning Authority. The phasing plan shall include .commencement and practical completion of all principal elements (including food stores, retail units within blocks H & J, and residential blocks A-F. Thereafter all phases of the development shall be completed and carried out in accordance with the phasing plan unless agreed in writing with the Local Planning Authority.”
The phasing was approved in the following terms (the numbers refer to week numbers starting with formal construction works – ie after demolitions and other site preparation):
Basement car park 1 – 92 Foodstore & other retail 1 – 79 Residential block A 14 – 65 Residential block B 19 – 79 Residential block C 25 – 92 Residential block D & E 46 – 92 Residential block F – Not programmed at this stage.
The June 2012 committee report noted the following:
“In considering this part of the phasing plan, it is important to ensure that appropriate controls are in place to ensure a co-ordinated and completed development takes place. This would be in contrast to a small limited implementation of one part only (e.g. the foodstore) that would leave the remainder of the site open which wouldn’t then provide the benefits envisaged (high quality public realm that benefits form natural surveillance and a perimeter block development) when considering the development as a whole.
The programming of the development achieves this as the main components of the scheme will be completed before the basement car park, which by condition has to be available before the stores can start trading.
Although it would have been desirable to have ensured block F is incorporated at this stage, it is not considered essential. Nevertheless it is understood that this block will be bought forward during the development programme, but at this stage dates can not be confirmed.”
The approved phasing indicated that the basement car park was the last element to be completed and that the residential development in blocks A to E would be completed before the retail stores started trading.
The proposals now before the Council seek to amend the phasing so that the foodstore and other retail units could start trading before the residential blocks are completed. The basement car park will still need to be completed before the stores can start trading.
The retail stores are expected to be ready to start trading in April/May 2014. The programme for the residential components is as follows:
Block Notes Practical Occupation Completion A Under construction by Bloor Homes April 2014 May 2014 B Under construction by Bloor Homes June 2014 July 2014 C Under construction by Bloor Homes August 2014 September 2014 D1 Under construction by BAM on August/September behalf of Shirley Advance via a 2014 contract that is already in place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.