(i) That the commencement of the second stage of design development, planning and procurement for Windy Arbor and Yorkswood Primary Schools based upon their draft design briefs be approved; and (ii) That an increase in the provisional budget to £6.9m be approved.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1This report seeks approval to commence with the next stage of the design and procurement process for Windy Arbor and Yorkswood Primary Schools, the seventh and eighth schools within the North Solihull Primary Programme.
2. Decision(s) Recommended
2.1Cabinet is asked to approve: (i) Commencement of the second stage of design development, planning and procurement for Windy Arbor and Yorkswood Primary Schools based upon their draft design briefs (accessible via the following link, http://eservices.solihull.gov.uk/mgInternet/ieListMeetings.aspx?CId=149&Year= 0);
(ii) A provisional budget for each school.
Background
Progression of the North Solihull Primary Programme 3.1 Cabinet approved an update to the Strategic Plan for North Solihull Primary Programme on the 10 December 2013. 3.2 Since then Cabinet has accepted the tender for rebuilding Phase 3, Fordbridge and Coleshill Heath Primary Schools and now is asked to approve the next stage of the remodelling proposals for Windy Arbor and Yorkswood. 3.3 Progress on St Anthony’s and St John the Baptist Catholic Primary Schools will be reported separately during the Spring 2014. Windy Arbor and Yorkswood 3.4 In line with the Strategic Plan, Windy Arbor and Yorkswood will be the first schools to be remodelled, on their existing sites, under this programme. The approach will be, essentially, predicated on refurbishing the schools, but the term remodelling also reflects the attempt to treat these schools, their stakeholders and communities in the same way as the new schools. The draft design briefs for each school are available online. 3.5 This report sets out: The current school place planning requirements (highlighted within the strategic plan) for Yorkswood; The education vision and design principles for the new schools determined in full consultation with the schools, community and stakeholders; The essential elements of the briefs that will form the basis for moving forward into the second stage of detailed design, planning and procurement for the remodelling proposals. 3.6 The final scheme proposals will be reported to Cabinet at the end of this stage and prior to any start on site.
4. Matters Arising
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.