Resolved
(i) That the progress made to date in on-going negotiation with HS2 Ltd of the Council’s HS2 “asks” be noted; and (ii) That it be agreed that Cabinet receive further updates on a monthly basis.
Cabinet noted this item on Thursday 10 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) That the progress made to date in on-going negotiation with HS2 Ltd of the Council’s HS2 “asks” be noted; and (ii) That it be agreed that Cabinet receive further updates on a monthly basis.
1.1Following submission of its response to the High Speed 2 Formal Environmental Statement consultation, the Council is involved in a process of negotiation with HS2 Ltd with the aim of securing alterations and / or improvements to the HS2 proposal. This report provides Full Cabinet with an update on progress made as a result of the on-going negotiations. 2. Decision(s) Recommended
2.1It is recommended that Full Cabinet: (i) Notes progress made to date in on-going negotiation with HS2 Ltd of the Council‟s HS2 „asks‟; and (ii) Agrees to receive further updates on a monthly basis.
Introduction 3.1 The High Speed Rail (London - West Midlands) Bill (HS2 Hybrid Bill) was deposited in Parliament, and received its first reading, in the House of Commons on Monday 25 November. 3.2 Consultation was subsequently carried out by Government on the associated HS2 Formal Environmental Statement (ES), a detailed statement assessing the likely significant effects of the project on the environment. Through consideration by the Council‟s HS2 Working Party, Overview and Scrutiny Management Board and Full Cabinet a formal consultation response was developed, agreed and submitted to the Government on 27 February 2014. 3.3 An independent assessor is currently reviewing, on behalf of the Government, all submissions received in response to the ES consultation. The review will report on 7 April 2014, to feed into second reading of the HS2 Hybrid Bill (which is currently anticipated to be in late April 2014). 3.4 The principles of HS2 will be established by second reading of the Bill, and a Select Committee subsequently set up to consider „petitions‟ relating to requests for change to the scheme. Second reading of the Bill will also set the timescale for commencement of the Select Committee process, and the deadline for submission of associated petitions. 3.5 The Council has appointed specialist Parliamentary Agents, Bircham Dyson Bell, to provide advice and represent the Council in the development and submission of petitions for consideration by the Select Committee. 3.6 HS2 Ltd is currently engaged with all potential petitioners, with the intention of negotiating away potential petitions. „Undertakings‟ and „assurances‟ can be issued (usually on behalf of the Secretary of Statement for Transport or the authority responsible for constructing HS2) to provide any commitments necessary to ensure that the asks of a potential petitioner can be met without needing to submit representations to the Select Committee.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 128 KB | Download |
PDF |
High Speed 2: Update on NegotiationsReport | 231 KB | DownloadRead as text |
Follow Cabinet at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... | Approved | Open |
| 17 Sep 2026 | Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... | Agreed | Open |
| 17 Sep 2026 | Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... | Decided | Open |
| 23 Jul 2026 | Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... | Approved | Open |
| 23 Jul 2026 | Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.