(i) That the re-use of land at 2 Ipswich Walk to provide a new general purpose temporary accommodation facility to be managed by Solihull Community Housing be approved; (ii) That it be agreed to transfer the land from the General Fund portfolio to the Housing Revenue Account portfolio; (iii) That the basis of capital funding for the proposed development be agreed; and (iv) That it be agreed to grant delegated authority to the Director of Resources and Cabinet Portfolio for Environment & Housing to approve the final detailed capital funding arrangements following the procurement process .
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1To outline a proposal to re-use land at 2 Ipswich Walk, Chelmsley Wood to develop a new general purpose temporary accommodation facility to be managed by Solihull Community Housing within the Housing Revenue Account portfolio. 1.2 To seek agreement to the allocation of capital development funding for the proposed development as outlined in section 7 of the report. 2. Decision(s) Recommended
(i) To approve the re-use of land at 2 Ipswich Walk to provide a new general purpose temporary accommodation facility to be managed by Solihull Community Housing. (ii) To agree to transfer the land from the General Fund portfolio to the Housing Revenue Account portfolio. (ii) To approve the basis of capital funding for the proposed development (iv) To grant delegated authority to the Director of Resources and Cabinet Portfolio for Environment & Housing to approve the final detailed capital funding arrangements following the procurement process.
Background
3.1The land covered by this report is shown in Appendix ‘A’ and is in the Council’s General Fund.
3.2Stonham Housing Association (part of Home Group) currently operates a registered care home for 16 people on this site. Stonham has occupied the building since 1989 and the current lease, agreed in 2002, is for 30 years. 3.3 The building dates from the 1960’s and does not now provide suitable accommodation. Home Group is therefore developing a new purpose built scheme at the new Smith’s Wood Village Centre to replace the service at Ipswich Walk. As a result, the building will become vacant in April 2015. 3.4 There is a need to agree the re-use of the land so that when the site is vacated a plan for its redevelopment can immediately be put into effect. Proposal 3.5 It is proposed that the current building is demolished and SCH develop a new modern, purpose-built temporary accommodation facility for homeless persons. The building will be used for general homeless persons rather than those with particular specialist needs. 3.6 Depending on the final design, the development will provide between 15-25 apartments. There will be on-site management and support for residents and the building will provide communal space to make provision for personal development relating to employment support and health and lifestyle, for example. The precise nature of the on-site support, how this is provided and inclusion of office accommodation is subject to further discussion between the Council and SCH. 3.7 Subject to the agreement of Cabinet, the next steps will be that SCH will prepare a detailed planning application, and a capital funding bid will be made to the Homes and Communities Agency.
4. Evaluation of Alternative Option(s)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.