The Cabinet Portfolio Holder agreed:- i) The delegation of financial authority to the University of Warwick Science Park for the operational expenses of the Centre and subject to the conditions set out under paragraph 3.4 of the report; ii) The establishment of a new Property Investment reserve as set out at paragraph 3.6 of the report; and iii) The virements as set out at paragraph 3.7 of the report.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Resources & Delivering Value Decision Session
Purpose of report
1.1To set out a range of operational management procedures for the operation of Blythe Valley Innovation Centre that will shortly transfer to the direct control of the Council.
2. Decision(s) recommended
2.1It is recommended that the Cabinet Portfolio Holder agrees:-
i) The delegation of financial authority to the University of Warwick Science Park for the operational expenses of the Centre and subject to the conditions set out under paragraph 3.4
ii) The establishment of a new Property Investment reserve as set out at paragraph 3.6.
iii) The virements as set out at paragraph 3.7.
3. What is the issue?
3.1The Cabinet Portfolio Holder previously considered a report in November 2016 that agreed the transfer of the Innovation Centre from Blythe Valley Innovation Centre Limited to the Council. The report noted that following the Councils purchase of 100% of the shares in the Company there was no longer any reason to keep the Centre in the Company structure and that administrative efficiencies could be achieved by transferring the asset to the Council.
3.2Since then officers have been working through the detailed legal, financial, procurement and operational issues with the result that the Centre is due to transfer to the Council with effect from the 1st July 2018.
3.3The Centre has proved to be successful with occupancy rates consistently in the 90%- 95% range. On that basis a key principle as set out in the original report was that from an operational point of view the tenants at the centre should see as little change as possible on a day to day basis. In practical terms this means that, for now, the Centre will continue to be managed by the University of Warwick Science Park (UWSP) on the Councils behalf. A management agreement is currently in place between UWSP and BVIC Limited and this would be novated to the Council.
3.4As a consequence of this it will be necessary to delegate the financial authority to incur expenditure on the Councils behalf to UWSP. It is recommended that the Cabinet Portfolio Holder approves this delegation on the basis that:-
Expenditure is in line with the Centres annual budget. For 2018 this has been approved by the Director of BVIC Limited (attached at Appendix A) but from 2019 onwards would be presented to both the Property Investment Board (PIB) and the Cabinet Portfolio Holder for Resources and Delivering Value for approval.
UWSP comply with their own rules for contracts where expenditure is below OJEU thresholds. These have been reviewed by officers and are considered to be sufficiently robust. In the event that expenditure exceeds OJEU thresholds then a separate report will be required to the Cabinet Portfolio Holder and the Councils Rules for Contracts will be followed.
The Councils Internal Audit service will have the right to inspect all Centre related financial records and to review the operation of the facility as and when they see fit.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Resources & Delivering Value Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.