The Cabinet Member for Resources and Delivering Value (i) Noted the current status of the Capital ICT Projects Programme; (ii) Approved the request to give the Director of Resources and Deputy Chief Executive delegated authority to approve spending of up to £300,000 from the contingency fund allocated to support the implementation of the new Adults and Children’s Social Care ICT system; (iii) Approved the recommendation to progress with the Oracle Cloud Project and the requirement to commit all of the ICT capital funding for the next three years 2019/20 – 2021/22 (£2,250,000 in total) to the project; (iv) Noted that there will be a requirement to re-phase the three year capital funding to fit with the likely payment profile for the Oracle Cloud Project and also the likely requirement to set aside a capital budget for other (non-Oracle) ICT projects. This will be done as part of a future update to the corporate capital programme; and (v) Approved the transfer of outstanding balances from the completed projects listed below to the Capital Programme ICT Projects Fund:- a) £7,787 from the Further Oracle Exploitation Phase 2 project. b) £32 from the Agile Working project. c) £6,064 from the Oracle Reporting Phase 2 project. d) £2,582 from the Social Care Resourcing (2018/19) funding. e) £341 from the Exacom CIL & S106 Public Facing Module project.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Resources & Delivering Value Decision Session
Purpose of report
1.1The purpose of this report is to update the Cabinet Member for Resources and Delivering Value on the current status of the Capital ICT Projects Programme. 1.2 The report also seeks approval for delegated authority to approve funding requests from the new Adults and Children’s Social Care system contingency fund. 1.3 The report seeks approval to progress with the project to migrate the Council’s Oracle E-Business Suite to the Oracle Cloud. 1.4 This report also seeks permission from the Cabinet Member to approve the transfer of outstanding balances from completed projects to the Capital Programme ICT Projects Fund.
2. Decision(s) recommended
2.1To note the current status of the Capital ICT Projects Programme. 2.2 To approve the request to give the Director of Resources and Deputy Chief Executive delegated authority to approve spending of up to £300,000 from the contingency fund allocated to support the implementation of the new Adults and Children’s Social Care ICT system. 2.3 To approve the recommendation to progress with the Oracle Cloud Project and the requirement to commit all of the ICT capital funding for the next three years 2019/20 – 2021/22 (£2,250,000 in total) to the project. 2.4 To note that there will be a requirement to re-phase the three year capital funding to fit with the likely payment profile for the Oracle Cloud Project and also the likely requirement to set aside a capital budget for other (non-Oracle) ICT projects. This will be done as part of a future update to the corporate capital programme. 2.5 To approve the transfer of outstanding balances from the completed projects listed below to the Capital Programme ICT Projects Fund.
a) £7,787 from the Further Oracle Exploitation Phase 2 project. b) £32 from the Agile Working project. c) £6,064 from the Oracle Reporting Phase 2 project. d) £2,582 from the Social Care Resourcing (2018/19) funding. e) £341 from the Exacom CIL & S106 Public Facing Module project.
Background
3.1The Capital ICT Projects Programme for 2018-19 had a budget of £1,066,000. Of this funding all but £19,138 has been committed to the 14 projects that make up the current Capital ICT projects Programme. The £19,138 is available to spend on future ICT projects approved by the Cabinet Member.
3.2A further capital allocation of £750,000 is due to the Capital ICT Projects Programme in each of the 2019/20, 2020/21 and 2021/22 financial years.
4. Progress on current projects
4.1This section highlights progress on projects that were previously reported to the Cabinet Member for Resources and Delivering Value in both October and December 2018. The funds allocated to the projects, the spend to date, the predicted total spend on the project and any variance is shown in Appendix 1, Section A ‘Current Projects (previously reported to members)’.
4.2The council has contracted with its existing supplier, Civica UK, for the supply of upgraded Income Management software including new software for the Council’s web site. Officers report that there are three outstanding pieces of work for this project for which updates are provided below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Resources & Delivering Value Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
Discretionary crisis fund policyThe Cabinet Member for Resources and Delivering Value; (i) Approved the Council’s revised Discretionary Crisis Fund P...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.