Resolved
That the progress of the Green Prospectus be noted and that the Progress Report be approved.
Cabinet noted this item on Thursday 11 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress of the Green Prospectus be noted and that the Progress Report be approved.
1.1To consider progress of the Council’s 18/19 Green Prospectus and seek approval of the Green Prospectus Progress Report.
2. Decision(s) recommended
To note progress of the Green Prospectus and approve the Progress Report. 3. What is the issue?
3.1The refreshed 18/19 Green Prospectus was approved at the Cabinet Member for Managed Growth’s Decision Making Session on the 19th June 2018. 3.2 To reflect the strategic focus being placed on sustainability and the cross-cutting nature of many of the issues, the Green Prospectus is now been considered by Full Cabinet. 3.3 As per agreed governance arrangements find attached at Appendix 1, the progress report detailing progress against agreed actions/targets. 3.4 In addition to each action having a RAG rating, we have continued to make use of symbols to demonstrate where grant funding has been utilised, where a project is of an innovative nature and when the activity has involved a high degree of partnership working. 3.5 An overall RAG rating and summary has been produced for each of the 6 themes. 3.6 The progress report illustrates the wide variety of projects that are being delivered across all the sustainability themes. It is important that all themes are advanced in order to ensure overall sustainability is delivered and to avoid one sustainability theme being advanced at the expense of others. 3.7 Building on good practice - A number of projects build on previous good practice and effective partnerships that have been built up over a number of years. For example:- (a) The current Warm Homes funded project which secured up to £743k of external funding to support the installation of up to 250 first time gas central heating systems builds on other energy related projects delivered as part of the Home Energy Efficiency and Affordable Warmth Strategy.
(b) The Council has built up very effective partnerships with the business, community and school sectors over a number of years. This supports the delivery of successful engagement activities. In November 2018 the Love Solihull initiative was awarded gold in the Environmental Best Practice Local Authority category in an award run by the Green Organisation.
(c) Our excellent relationship with schools supports the delivery of successful initiatives such as the Model Climate Change Conference for secondary schools, Modeshift, the Greener Solihull Schools Awards and the Ashden ‘Less CO2’ programme.
3.8Leading by example – A number of projects demonstrate how the Council is demonstrating leadership. For example:- (a) Delivering year on year reductions in carbon emissions from council operations. Notably the implementation of the Street Lighting Strategy (2012-2022) has resulted in a 46% reduction in emissions (2017/18 emissions compared to a 2009/10 baseline), reducing energy cost by around £400k a year.
In recognition of our successful LED street lighting scheme it is being featured in a series of articles being produced by Friends of the Earth aimed at encouraging energy efficiency among councils.
(b) In September 2018 the Council signed up to the voluntary Emissions Reduction Pledge (ERP 2020) and adopted a 45% carbon emission reduction target by 2021 (based on 2009/10 emissions).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 418 KB | Download |
PDF |
SOLIHULL GREEN PROSPECTUS –PROGRESS REPORTReport | 108 KB | DownloadRead as text |
Follow Cabinet at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... | Approved | Open |
| 17 Sep 2026 | Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... | Agreed | Open |
| 17 Sep 2026 | Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... | Decided | Open |
| 23 Jul 2026 | Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... | Approved | Open |
| 23 Jul 2026 | Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.