Resolved
The Cabinet Member RESOLVED : a) to approve the refreshed Policy attached at Appendix A . The Cabinet Member considered representations from Councillor A Hodgson which can be viewed online
CPH Resources Decision Session approved this item on Thursday 2 April 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet Member RESOLVED : a) to approve the refreshed Policy attached at Appendix A . The Cabinet Member considered representations from Councillor A Hodgson which can be viewed online
The purpose of this report is to seek the Cabinet Member for Resources approval for the Council’s refreshed Risk Management Policy. Please note that Audit Committee endorsed the Policy at their meeting on the 9th March 2020.
2. Decision(s) recommended
2.1The Cabinet Member for Resources are asked to approve the refreshed Policy attached at Appendix A.
3. Matters for Consideration
3.1The Council recognises that there are risks in everything it does and has a duty to manage these risks in a balanced, structured and cost effective way. Approval and publication of this Risk Management Policy and Procedure demonstrates this intention. The document:
- is fully supported by Members, the Chief Executive and the Corporate Leadership Team who are accountable for effective risk management within the Council; - explains the Council’s underlying approach to risk management, documenting the roles and responsibilities of Members, officers and other key parties for the ongoing management of risk, as well as explaining key aspects of the Council’s risk management process; and - forms part of the Council’s overall internal control and governance arrangements.
3.2The Policy has been reviewed following the recent External Risk Management Health Check (which was undertaken by Gallagher Bassett) to ensure that our existing risk management arrangements continue to be proportionate and the most appropriate for the Council. There have been no significant changes to the Policy which was reviewed by CLT on the 11th February and endorsed by Audit Committee on the 9th March 2020. 4. What options have been considered and what is the evidence telling us about them?
4.1Not applicable for this report.
5. Reasons for recommending preferred option
5.1Not applicable for this report.
6. Implications and Considerations
6.1How the proposals in this report contribute to the delivery of Council Plan priorities:
Priority: Contribution:
Securing inclusive economic growth. None.
Planning & delivery for Solihull’s low None. carbon future (to include biodiversity implications).
Managing demand and expectation None. for public services.
Developing our approach to services None. for adults and children with complex needs. Risk management is a systematic way of identifying Making the best use of our people how to manage uncertain events and outcomes. It and physical assets. is a consistent, robust approach (including the culture, resources and processes) established to identify significant risks and reduce them to the lowest acceptable level. Used effectively, risk management supports the Council to exploit potential opportunities and promote innovation, as well as safeguarding it against potential threats.
6.2Consultation and Scrutiny:
6.2.1 The review process included consultation with the Corporate Leadership Team and endorsement by Audit Committee. 6.3 Financial implications:
6.3.1 It is not envisaged that this review will incur any direct additional financial resources.
6.4.1 The Council has a statutory duty to have in place arrangements for managing risk.
6.5.1 Failure to maintain an effective approach to risk management may lead to the Council being: - unable to meet its statutory obligations; - unable to demonstrate effective corporate governance arrangements; - open to criticism from External Audit.
6.6.1 No direct implications.
7. List of appendices referred to
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 618 KB | Download |
PDF |
Risk Management Policy ApprovalReport | 163 KB | DownloadRead as text |
Follow CPH Resources Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | ApologiesApologies for absence were received from A. Felton (Director of Resources) due to other Council business. | Decided | Open |
| 14 Sep 2026 | Declarations of Pecuniary or Conflicting Interest from MembersNo Declarations of Interest were received. | Decided | Open |
| 14 Sep 2026 | Questions and DeputationsNo questions or deputations were received. | Decided | Open |
| 14 Sep 2026 | Applications for Discretionary Rate ReliefHaving considered the report, the Cabinet Portfolio Holder for Resources: | Decided | Open |
| 14 Sep 2026 | Debt Monitoring Report - Quarter 1 2026/27Having considered the report, the Cabinet Portfolio Holder for Resources: | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.