Resolved
That the minutes of the meeting held on the 17 July 2020 be received for information.
Cabinet decided this item on Thursday 13 August 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on the 17 July 2020 be received for information.
CABINET - 16 July 2020
MINUTES
Present: Councillors: I Courts, K Grinsell, K Hawkins, A Mackiewicz, K Meeson, T Richards OBE, A Rolf, R Sleigh OBE, J Tildesley, A Adeyemo, S Caudwell and F Nash
Officers: Nick Page, Paul Johnson, Deborah Merry, Andrew Kinsey, Mary Morrissey, Jenny Wood, Louise Rees, Ruth Tennant, Jonathan Bretherton (UGC) Sam Gilbert, Paul Langham and Jane Game.
1. APOLOGIES
None received.
2. DECLARATION OF INTEREST
Cllr Sleigh in relation to item 5 reminded Members he was Chairman of WMCA Investment Fund and Director of the UGC.
3. QUESTIONS AND DEPUTATIONS
None received.
4. MINUTES
The minutes of the meeting held on 18 June were presented for information only.
RESOLVED: That the minutes of the meeting held on the 18 June 2020 be received for information.
5. URBAN GROWTH COMPANY BUSINESS PLAN 2020 AND WORKING CAPITAL REQUIREMENTS
The Cabinet was:-
Invited to approve the UK Central Urban Growth Company (UGC) Business Plan for the period 2020-2021; and
Provided with an update on the cash flow requirements for the UGC and invited to approve an additional cash advance of £4.2m in order that it can meet its short term expenditure commitments due for project delivery milestones ahead of reimbursement by the Council via the West Midlands Combine Authority (WMCA).
Members were advised that the UGC Business Plan for 2020-2021 highlighted some of the achievements to date as well as setting the priorities for the UCG over the coming year. By approving the Business Plan, Cabinet would be providing the UCG with the confidence that the priorities and approach were supported by the Council as
1 CABINET - 16 July 2020
the sole shareholder. If approved the increase in the working capital available to the UCG would enable projects in the business plan to be progressed without delay.
The report went on to detail the positive impact the Business Plan would have regarding the safeguarding of jobs, delivering economic uplift, support a low carbon economy, address wider social economic and environmental benefits of investment. The cash advance of £4.2m would support a number of key projects included in the Business Plan for 2020 and approved by the WMCA. It was anticipated that the cash advance would be repaid by the end of the financial year 2020/21.
Members welcomed the report and recognised the benefits that would result from such an investment. Officers clarified a number of points concerning the payment mechanism and risks involved. The risk was limited as this was a cash flow issue and not a cash payment.
RESOLVED:
(i) That the Urban Growth Company Business Plan 2020 be approved; and
(ii) That the additional cash advance of £4.2million on project costs detailed in paragraphs 3.9 to 3.14 of the report be approved.
6. UPDATE ON APPLICATIONS TO FUNDING BODIES THAT SUPPORT THE COUNCIL'S PRIORITIES
The Cabinet was informed of the progress of external funding applications by the Council and invited to accept external funding to support the delivery of the Council’s priorities.
Members were advised that the Council had an ambitious agenda which could not be entirely funded by the Council’s own resources. Securing the external funding supported the delivery of the Council’s Growth and Development Investment Plan. The report provided details on the individual applications as set out in the report.
Members welcomed the report and noted that in accepting the funding, further work would be undertaken in developing specifics such as route detail.
RESOLVED: (i) That the submission of an application to West Midlands Combined Authority (WMCA) Better Streets Community Fund, to deliver walking and cycling improvements at Berkswell, Meriden (Project A) be noted;
(ii) That the submission of an application to the Department of Transport (DfT) Challenge Fund, to support the Council’s unclassified road network (Project B) be noted;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 240 KB | DownloadRead as text |
Follow Cabinet at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... | Approved | Open |
| 17 Sep 2026 | Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... | Agreed | Open |
| 17 Sep 2026 | Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... | Decided | Open |
| 23 Jul 2026 | Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... | Approved | Open |
| 23 Jul 2026 | Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.