Resolved
Conditional approval as per Officer recommendation.
Planning Committee approved this item on Wednesday 26 August 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Conditional approval as per Officer recommendation.
1.1This request is for approval of plans and specifications relating to works associated with the construction of a High Speed Rail Interchange Station and associated external works, including short-stay, taxi and drop-off car parking, public realm, earthworks and other associated works. The request is made by HS2 Ltd’s appointed Station Design Services Contractor (SDSC) under Schedule 17 of the High Speed Rail (London-West Midlands) Act 2017 (the Act), rather than the Town and Country Planning Act 1990.
1.2Having regard to the parameters by which the local planning authority, as a Qualifying Authority, may consider them the plans and specifications are considered to be acceptable, subject to conditions.
1.3Long stay car parking is excluded from the Schedule 17 submission and is covered by a separate reserved matters application under the Act. This is because whilst this form of car parking benefits from deemed planning permission provided for by Section 20 of the Act, Section 23 of the Act confirms that the detail of this car parking is to be submitted as reserved matters under the Town and Country
1 (Development Management Procedure) (England) Order 2015 (as amended) rather than under Schedule 17 of the Act.
1.4This request for approval should be read in conjunction with submissions PL/2020/00291/HS2DIS and PL/2020/00275/MAROT, comprising; a request for approval under Schedule 17 of the Act for the construction of a People Mover system on an elevated viaduct, together with 4 no. station stops, a maintenance depot and associated external works; and an application for approval of Reserved Matters for details of access, appearance, landscaping and layout for the provision of car parking (excluding short stay, taxi and drop off parking) at Interchange Station, respectively. These submissions can be found elsewhere on this agenda.
2.1The proposed station is specified as a Schedule 1 work in the Act. Work No.3/1 applies as set out below:
“Work No. 3/1 - A railway (10.9 kilometres in length) commencing by a junction with Work No. 2/146 at its termination, passing north-westwards and terminating by a junction with Work No. 3/25 at a point 440 metres north of the junction of Solihull Parkway with Blackfirs Lane. Work No. 3/1 includes bridges over the Rugby to Birmingham Line, Works Nos. 3/10A and 3/18; viaducts over Truggist Lane, Work No. 3/3, Meriden Road, Bayley’s Brook, the River Blythe and the M42 Motorway; and a new station (Birmingham Interchange Station).”
2.2Schedule 1 of the Act (Paragraphs 1 (1) and 1 (2)) sets out certain construction requirements, including in relation to the carrying out of Scheduled Works. In particular, such works need to be:
• Carried out within the horizontal Limits of Deviation (LoD) shown on the deposited plans referenced in the Act; and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PL/2020/00289/HS2DIS: Land and buildings at the Interchange Triangle (HS2)Report | 1.2 MB | DownloadRead as text |
Follow Planning Committee at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jun 2026 | Birmingham Airport Night Flying Policy Sub-CommitteeRESOLVED That Councillors Bob Grinsell (Chairman), Jane Lamden and David Hoey were elected to sit on the Birmingham A... | Decided | Open |
| 27 May 2026 | Appointment of chairmanRESOLVED Councillor Bob Grinsell was elected Chairman for the Municipal Year 2026/27. | Decided | Open |
| 27 May 2026 | Appointment of vice-chairmanRESOLVED Councillor James Bradley was elected Vice-Chairman for the Municipal Year 2026/27. | Decided | Open |
| 21 May 2025 | Appointment of ChairmanRESOLVED Councillor Bob Grinsell was elected Chairman for the Municipal Year 2025/26. | Decided | Open |
| 21 May 2025 | Appointment of Vice-ChairmanRESOLVED Councillor Prish Sharma was elected Vice-Chairman for the Municipal Year 2025/26. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.