Conditional approval as per Officer recommendation with an additional condition, to be agreed by Chairman, Vice-Chairman and Officers, requesting HS2 to pursue all efforts to seek the viability of integration of the building at both ends of the line.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1This request for approval of plans and specifications relating to works associated with the construction of a People Mover system on an elevated viaduct together with four station stops, a maintenance facility and associated works. The request for approval is made by HS2’s appointed Station Design Services Contractor (SDSC) via Schedule 17 of the High Speed Rail (London – West Midlands) Act 2017 (The Act), rather than the Town and Country Planning Act.
1.2Having regard to the parameters by which the local planning authority, as a qualifying authority, may consider them, the plans and specifications are considered to be acceptable, subject to conditions.
1.3This request for approval should be read in conjunction with submissions PL/2020/00289/HS2DIS and PL/2020/00275/MAROT, comprising a request for approval under Schedule 17 of The Act, for the construction of a High Speed Rail Interchange Station and associated external works; and a Reserved Matters application for details of access, appearance, landscaping and layout for the provision of car parking (excluding short stay, taxi and drop off parking) in connection High Speed Rail Interchange Station pursuant to Section 23 of the High Speed Rail (London West Midlands) Act, respectively. These submissions can be found elsewhere on this agenda.
1 2. Background
2.1The proposed People Mover system is specified as a Schedule 1 work in the Act. Work Nos. 3/20 and 3/20a apply as set out below:
2.2“Work No. 3/20 – An elevated People Mover commencing at a point 185 metres north-west of the centre of the Airport Way and Hermes Road roundabout at Birmingham International Airport passing eastwards over Vanguard Road, Bickenhill Lane, Birmingham International Station, Pendigo Way, Eastway, the M42 Motorway and Middle Bickenhill Lane and terminating at a point 498 metres south of the junction of Middle Bickenhill Lane with the A452 Chester Road;
2.3Work No. 3/20A – An elevated People Mover commencing by a junction with Work No. 3/20 at a point 110 metres west of the crossing of Middle Bickenhill Lane over Hollywell Brook passing eastwards then south-eastwards and terminating at a point 137 metres north-east of the junction of the Eastway Link Road with Eastway. Work No. 3/20A includes a depot for the proposed People Mover.”
2.4Schedule 1 of the Act (Paragraphs 1 (1) and 1 (2)) sets out certain construction requirements, including in relation to the carrying out of Scheduled Works. In particular, such works need to be:
• Carried out within the horizontal Limits of Deviation (LoD) shown on the deposited plans referenced in the Act; and • Vertically upwards to any extent not exceeding 3 metres from any level for that work shown on the deposited sections referenced in the Act.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.