Resolved
That it be approved that the Council extends its commitment to the Waste Supply Agreement by a further 5 years, therefore entering into a 25 year Agreement instead of a 20 year Agreement
Cabinet approved this item on Thursday 8 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That it be approved that the Council extends its commitment to the Waste Supply Agreement by a further 5 years, therefore entering into a 25 year Agreement instead of a 20 year Agreement
1.1To provide an update regarding the Waste Supply Agreement for Sherbourne Recycling.
2. Decision(s) recommended
2.1That Cabinet approves that the Council extends its commitment to the Waste Supply Agreement by a further 5 years, therefore entering into a 25 year Agreement instead of a 20 year Agreement.
3. Matters for Consideration
3.1In September 2019, the Cabinet provided formal approval for the Council to participate in Sherbourne Recycling and become a partner in the development of a Sub-regional Material Recovery Facility (MRF).
3.2In the report, a number of delegated powers were set out and agreed by Cabinet.
3.3One of the delegations was in relation to the Waste Supply Agreement (WSA). The WSA is the formal agreement that commits the council to delivering specified dry recycling collected at the kerbside and delivered to the Household Waste Recycling Centre, Sherbourne Recycling. The WSA is an exclusive agreement and guarantees a supply of recycling to the facility.
3.4In the September 2019 report to Cabinet, it was agreed that through the delegations, the Council could agree to a WSA for up to 20 years.
3.5The relevant extract from the September 2019 Cabinet report is provided below under point (d):
Delegate authority to the Director of Resources & Deputy Chief Executive, in consultation with the Solicitor to the Council and the Cabinet Member for Resources to finalise and agree the detailed terms of the transaction with AssetCo. The authority under this delegation shall also include:
(a) the power to enter into the relevant legal agreements and associated documents necessary to complete the transaction with AssetCo;
(b) (in relation to the management of the loan facility) the power to negotiate and agree variations to the terms of the loan facility;
(c) the power for the Council to provide such services as is deemed necessary (e.g. HR and/or Payroll) to AssetCo;
(d) The power to enter into the Service Level Agreement with AssetCo committing the Council’s waste tonnage for 20 years.
4. What options have been considered and what is the evidence telling us about them?
4.1During the development of the MRF it has become clear that a longer operating period for the facility should be considered. Through dialogue with bidders (the facility is being procured using the Competitive Dialogue Procurement method enabling pre-tender submission discussions to take place to develop the solution), it was confirmed that with appropriate measures it would be feasible to operate the facility over a longer operating period of 25 years.
4.2Operating the facility over a 25 year period aligns with the revised financial model for the facility which profiles Solihull’s share of the capital financing of up to £9.000 million. This was approved by Cabinet on 11th February 2021 following a number of project developments.
4.3There are a number of financial impacts to increasing the financial lifecycle from 20 to 25 years:
- Longer term control and cost certainty
- Prudential borrowing can be repaid over a revised 25 year period, which reduces the annual repayment cost.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2021-04-08: Sherbourne Recycling Waste Supply Agreement (003)Report | 242 KB | DownloadRead as text |
Follow Cabinet at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... | Approved | Open |
| 17 Sep 2026 | Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... | Agreed | Open |
| 17 Sep 2026 | Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... | Decided | Open |
| 23 Jul 2026 | Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... | Approved | Open |
| 23 Jul 2026 | Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.