Resolved
AGREED: · That members of the HS2 IAG Group would receive a briefing on the proposed design of the River Blythe Viaduct ahead of the scheme going out to public consultation.
HS2 Implementation Advisory Group agreed this item on Tuesday 19 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED: · That members of the HS2 IAG Group would receive a briefing on the proposed design of the River Blythe Viaduct ahead of the scheme going out to public consultation.
HS2 Solihull IAG Briefing Key Design Elements
Tuesday 19 July 2022 Balsall Common Viaduct Key Design Element Current Solution • Minimises flood risk
• Improved pedestrian visibility from PRoW (M197)
• Landscape integrated with abutment London and embankments responding to the highly natural context
• Piers shaped to further emphasise views under the viaduct
• Enhanced ecological connectivity Balsall Common Viaduct Key Design Element Current Solution
From Berkswell Station (North Side) From Station Road Balsall Common Viaduct Key Design Element Current Solution
From Baulk Lane Footpath • 2 Community Events at the British Legion Hall KDE Engagement • 200 attendees visited to talk to our 16 experts about the design, landscaping, community amenities and more. • 93 completed feedback forms providing 238 pieces of valuable feedback. • Fifteen Year 9 school children were welcomed on to our site and given a tour including the Greenway the Fisheries and
London Bayleys Brook. They provided their unique perspective on our designs
Feedback included comments relating to landscaping, public access and some expressed concerns around the noise barriers which we will assess as part of the final submission. River Blythe Viaduct Key Design Element The emerging design for the viaduct is now mature enough for public engagement
Two events planned for September 2022 at the George Fenton Hall in Hampton-in-Arden and The Pavilion in Meriden where residents will be able to talk to our London experts about the design, landscaping community amenities and more
Maps, Plans and visuals will can be viewed online or a booklet can be posted out by request.
Feedback will be collected at the events, online or in the post
This will be followed by a “you said, we did event later in the year Copyright notice The copyright for this presentation remains with HS2 Ltd.
It cannot be reproduced as a whole or in part without written permission from HS2 Ltd.
If required, please contact our Corporate Communications Team at [email removed].
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
River Blythe and Balsall Common ViaductsReport | 501 KB | DownloadRead as text |
Follow HS2 Implementation Advisory Group at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2024 | MINUTESRESOLVED : i. To agree the draft minutes arising from the HS2 IAG meeting held on 21 st September 2023. | Agreed | Open |
| 15 Mar 2023 | Main Programme UpdateRESOLVED The HS2 IAG noted the main programme update. | Noted | Open |
| 15 Mar 2023 | Key Issues TrackerRESOLVED The HS2 IAG noted the . | Noted | Open |
| 19 Jul 2022 | Main Programme UpdateAGREED: · It was agreed that an update on where the electrical infrastructure for the route would be sited would be i... | Agreed | Open |
| 19 Jul 2022 | Key Issue TrackerAGREED: · A meeting be convened to explore and refine plans for a Skate Park in Heath Park. The meeting then looked a... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.