Resolved
RESOLVED The HS2 IAG noted the .
HS2 Implementation Advisory Group noted this item on Wednesday 15 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED The HS2 IAG noted the .
Last updated: Tuesday, 07 March 2023
Key Issues Tracker – 15 March 2023 Last Next Agenda Ref Theme HS2 Response Status updated Update Item Haul routes – An update on the proposed Haul routes was HS2 Ltd to provide a detailed presented at the IAG meeting on 7/3/22. Update programme of works for Solihull. presentation Effective mitigation measures required The latest position will be shown on the route to be to: flythrough at the 21/11 meeting. Haul routes and 1 21/11/22 provided at 15/3/23 Open -Manage impact of construction traffic plant crossings will remain in use during the a future -Minimise congestion duration of the civils construction period. meeting by -Minimise use of the highways HS2. network, where possible. The latest position will be shown on the route -Ensure road safety flythrough at the 15/3/23 meeting. HS2 have been able to relocate one of the two football pitches in Heath Park affected by the HS2 scheme. HS2 are reviewing the Cabinet Member request to see if construction of the Skate Park work could be incorporated into Site Restoration. It is not envisaged that we will be in a position to provide Chelmsley Wood public space – an update until later this year when the design will Verbal potential mitigation for loss of land at be further advanced. update to be Heath Park. Cllr Rolf requested that 2 21/11/22 provided at No Open HS2 consider providing a skateboard Updated wording circulated on 1/6/22: the meeting park in Heath Park to mitigate the loss on 15/3/23 of a football pitch Our position to date is that we will consider the request and make a judgement once we are in a position to do so as it could be supported through BBV’s community investment programme, so long as other funding/support from SMBC, or another route can be secured. Last updated: Tuesday, 07 March 2023
Last Next Agenda Ref Theme HS2 Response Status updated Update Item Update: A meeting was held between HS2 Ltd, BBV and SMBC on 24/11/22. To confirm, BBV’s demobilisation may be able to provide some facilitation for a future skatepark/leisure facility. However, whilst HS2 Ltd is not in a position to commit to the construction of such a facility, we will continue to engage with SMBC. SMBC are also considering making a bid for HS2’s Community & Environment Funding (CEF) to look at other options for Bluebell Park which is nearby.
HS2 has launched a vision for a ‘green corridor’ of new woodlands and wildlife habitats alongside the railway. They will replace habitats affected by the construction of HS2, while conserving and enhancing some too. On phase one of the railway, 33.4 sq km of habitats will be left behind in the corridor – which is over 30% more than we Update Loss of green spaces are affecting in the first place. This is part of the presentation - creation of ecological mitigation sites commitment to ensure there is no net-loss of bio- to be - issues with site clearance on 3 diversity as part of the construction of HS2. 13/12/21 provided at No Open Diddington Lane and mitigation plans A number of ecological webinars have taken a future - Joint collaborative working on re-use place and the item on ecology at a previous meeting by of land at Balsall Common meeting covered the steps taken to create the HS2. “green corridor” and mitigation sites. Please see links below to recent HS2 webinars:
Habitats and Wetlands in the West Midlands: https://www.youtube.com/watch?edufilter=NU LL&v=d0EE6V4xJoc Last updated: Tuesday, 07 March 2023
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Key Issues TrackerReport | 576 KB | DownloadRead as text |
Follow HS2 Implementation Advisory Group at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2024 | MINUTESRESOLVED : i. To agree the draft minutes arising from the HS2 IAG meeting held on 21 st September 2023. | Agreed | Open |
| 15 Mar 2023 | Main Programme UpdateRESOLVED The HS2 IAG noted the main programme update. | Noted | Open |
| 19 Jul 2022 | Main Programme UpdateAGREED: · It was agreed that an update on where the electrical infrastructure for the route would be sited would be i... | Agreed | Open |
| 19 Jul 2022 | River Blythe and Balsall Common ViaductsAGREED: · That members of the HS2 IAG Group would receive a briefing on the proposed design of the River Blythe Viadu... | Agreed | Open |
| 19 Jul 2022 | Key Issue TrackerAGREED: · A meeting be convened to explore and refine plans for a Skate Park in Heath Park. The meeting then looked a... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.