ICT Capital Projects Update

Noted Committee 2 papers

CPH Resources Decision Session noted this item on Monday 3 April 2023. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED The Cabinet Member noted the current status of the Capital ICT Projects Programme.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to CPH Resources Decision Session

Executive summary

1.1The purpose of this report is to update the Cabinet Member for Resources on the current status of the Capital ICT Projects Programme.

1.2The second and final phase of the Oracle cloud programme went live on time in February 2023 and Officers are currently completing a period of enhanced support for the go live as part of the transition into business as usual operations. All of the other projects in the ICT Capital Programme have been completed or are progressing well and updates for specific projects are highlighted below in the main report.

1.3Officers are working on a number of proposals for investment opportunities and hope to present these to the cabinet member in due course. Officers have no further recommendations for investment opportunities in this report however.

2. Decision(s) Recommended

2.1To note the current status of the Capital ICT Projects Programme. Report Title: ICT Capital Projects Update

3. Matters for Consideration

Background

3.1The Capital ICT Projects Programme for 2022-23 has a budget of £733,940 (which includes £350,000 of funds approved by the Cabinet member at the April Decision session for allocation to the Oracle Programme). Of this funding all but £12,940 has been committed to the projects that now make up the current Capital ICT projects Programme.

3.2An additional £500,000 of Capital ICT Projects Programme funding for 2023/24 was approved by Full Council on the 23rd February 2023 as part of the Budget Framework 2023/24 to 2025/26 bringing the total of uncommitted funds available to the Capital ICT Projects Programme to £512,940. These funds are available to spend on future ICT projects approved by the Cabinet Member.

Progress on current projects

3.3This section highlights progress on projects that were previously reported to the Cabinet Member for Resources in November 2022. The funds allocated to the projects, the spend to date, the predicted total spend on the project and any variance is shown in Appendix 1, Section A ‘Current Projects (previously reported to members)’.

Oracle Cloud

3.4The Council’s new Oracle Fusion Cloud system provides the core IT platform for Finance, Procurement, Accounts Payable, Accounts Receivable, Human Resources (HR), Payroll, and Organisational Development, across the Council, and it partners: Solihull Community Housing (SCH), the Urban Growth Company (UGC) and schools. At the last Decision Session, Officers reported that the first phase of the implementation of the Oracle Fusion system (Oracle Cloud) had been completed and that the Council and it partners were live on the new system for Finance, General Ledger, Procurement, Accounts Payable and Accounts Receivable.

3.5Officers can now report the second and final phase of the implementation which includes HR, Leaning Management, and Payroll for Core Council, SCH, UGC and Education, went live in February 2023 as planned and the first Payrolls on the new system were successfully usual operations. Officers expect to be able to close down the Oracle programme in the next couple of months once the transition to business as usual operations is complete.

Microsoft InTune and AutoPilot

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 132 KB Download
PDF
ICT Capital Projects UpdateReport 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 4 attended
BS
Councillor Bob Sleigh OBE Cabinet Portfolio HolderCommittee Member, expected
CD
Councillors DiaryOfficer, expected
AA
Councillor Ade Adeyemo Liberal Democrat Group SpokespersonCommittee Member, expected
SS
Councillor Shesh Sheshabhatter Green Group SpokespersonCommittee Member, expected

On this subject at Solihull

Search all
  1. ICT Capital Projects UpdateThis decision
  2. ICT Capital ProjectsNoted
  3. ICT Capital Projects UpdateNoted
  4. ICT Capital Projects UpdateNoted
  5. ICT Capital Project UpdateNoted
  6. ICT Capital Project UpdateNoted

More from Solihull CPH Resources Decision Session

All decisions
MeetingDecisionOutcome
14 Sep 2026 ApologiesApologies for absence were received from A. Felton (Director of Resources) due to other Council business. Decided Open
14 Sep 2026 Declarations of Pecuniary or Conflicting Interest from MembersNo Declarations of Interest were received. Decided Open
14 Sep 2026 Questions and DeputationsNo questions or deputations were received. Decided Open
14 Sep 2026 Applications for Discretionary Rate ReliefHaving considered the report, the Cabinet Portfolio Holder for Resources: Decided Open
14 Sep 2026 Debt Monitoring Report - Quarter 1 2026/27Having considered the report, the Cabinet Portfolio Holder for Resources: Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies