RESOLVED The Cabinet Member for Resources: · Noted the current status of the Capital ICT Projects Programme. · Approved funding allocations from the Capital ICT Projects Programme as follows: o £50,000 for a project to develop a system to support the ongoing monitoring of adult social care payments. o £45,000 to rebuild the website in Drupal for local government. o £90,000 for a new ICT Service Management system. o £50,000 to top up the Oracle enhancement fund approved by the cabinet member at the April 2024 cabinet meeting. · Approved the transfer of outstanding balances from the following completed projects to the Capital Programme ICT Projects Fund. o a) Oracle Mitel Integration £627.25 o b) Web Site upgrade £10,450 o c) NEC document management system upgrade £4,000
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
The purpose of this report is to update the Cabinet Member for Resources on the current status of the Capital ICT Projects Programme.
This report also seeks permission from the Cabinet Member to allocate funds from the Capital ICT Projects Programme to fund the proposed investment decisions recommended by Officers in section 2, which are described in more detail in section 5 of this report.
This report also seeks permission from the Cabinet Member to approve the transfer of outstanding balances from three completed projects to the Capital Programme ICT Projects Fund. 2. Decision(s) Recommended
To note the current status of the Capital ICT Projects Programme.
To approve funding allocations from the Capital ICT Projects Programme as follows:-
£50,000 for a project to develop a system to support the ongoing monitoring of adult social care payments. £45,000 to rebuild the website in Drupal for local government.
£90,000 for a new ICT Service Management system.
£50,000 to top up the Oracle enhancement fund approved by the cabinet member at the April 2024 cabinet meeting.
To approve the transfer of outstanding balances from the following completed projects to the Capital Programme ICT Projects Fund.
a) Oracle Mitel Integration £627.25
b) Web Site upgrade £10,450
c) NEC document management system upgrade £4,000
3. Matters for Consideration
Background
The Capital ICT Projects Programme for 2025-26 has a budget of £535,542.68 in uncommitted funds available to spend on projects approved by the Cabinet Member. This includes £35,542.68 in uncommitted funds from the Capital ICT Projects Programme for 2024-25, plus an additional £500,000 of Capital ICT Projects Programme funding for 2025-26 which was approved by Full Council on the 23rd February 2023 as part of the Budget Framework 2023-24 to 2025-26.
4. Progress on current projects
This section highlights progress on projects that that were previously reported to the Cabinet Member for Resources in October 2024. The funds allocated to the projects, the spend to date, the predicated total spend on the projects and any variance is shown in Appendix 1, Section A ‘Current Projects (previously reported to members)’.
New E-tendering System
The new E-Tendering system (Atamis) will provide the Council with a modern Source to Contract (S2C) system that also enables the Council to meet the requirements of the new Public Sector Procurement Regime which came into force on 24th February 2025.
Officers in the Corporate Procurement Service report that there has been a delay to the implementation of the new system caused by teething problems with the governments central digital platform. The Council is required to publish procurement notices from the system to this platform and Officers took the decision to delay the implementation of the system until they could be confident that the problems with the platform had been resolved. This now appears to be the case and Officers can now report that they plan to go live with the first module, the Tender Management module, beginning in April. Officers also report that the issues reported in the October report relating to the supplier portal have also now been resolved. Plans for the implementation of the remaining modules will be drawn up once the Tender Management module is live.
Cloud Data Platform
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.