Resolved
RESOLVED The Committee noted the outcome of the recent audit of the 2022/23 housing benefit subsidy claim and congratulated the team on their achievement.
Audit Committee noted this item on Monday 18 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED The Committee noted the outcome of the recent audit of the 2022/23 housing benefit subsidy claim and congratulated the team on their achievement.
To update Audit Committee on the report of the 2022/23 housing benefit subsidy claim.
Each year the housing benefit subsidy claim is audited by our appointed reporting accountant (Grant Thornton). The outcome of the audit is reported to the Department for Work & Pensions (DWP). The deadline for the report to be submitted to the DWP was originally 30 November 2023, this was extended to 31 January 2024. Grant Thornton submitted the claim for Solihull Council to the DWP on 25 January 2024.
2. Decision(s) Recommended
To note the outcome of the recent audit of the 2022/23 housing benefit subsidy claim.
3. Matters for Consideration
Housing benefit entitlement is a means tested calculation based on national legislation and guidance. The legislation and guidance are applied to each individual claim. During 2022/23 we had an average housing benefit caseload of 6,098 and processed in the region of 16,262 changes in circumstances.
Whilst it is not possible to check each change that is processed, particular focus has been made on checking cases that have earned income as part of their calculation. This is following the outcome of previous housing benefit audits that identified earned income cases as having a high error rate. Errors relating to earnings had been reported to the Department of Work and Pensions for the previous 7 years.
Since January 2020 a 100% check of earnings cases has been carried out. The 100% check only applies to cases where a change has occurred since January 2020.
Following the outcome of the 2021/22 housing benefit subsidy audit a more robust quality checking process has been implemented to ensure that any quality checks that identify an error are closely monitored until the claim is corrected.
A total of 1,285 checks have been undertaken by the benefits team during 2022/23 for both new claims with earned income and changes relating to earning income.
Members of the Benefits Team have completed the subsidy workbooks for the 2022/23 audit as in previous years, with Grant Thornton acknowledging that the completion of the workbooks continues to be of good standard.
AUDIT OUTCOME
In line with the guidance issued by the Department for Work & Pensions (DWP), Grant Thornton are required to undertake testing on a sample of cases from each main subsidy area, this is known as ‘Discovery’ testing:
- Rent allowances – housing benefit paid to private tenants. - Rent rebates – housing benefit paid to Solihull Community Housing tenants. - Non-HRA rent rebates – housing benefit paid to those in temporary accommodation. - Modified scheme cases – where the housing benefit scheme has been modified to disregard certain income types (i.e., a war disablement pension).
Any errors identified through the Discovery testing phase will mean additional cases are tested. Grant Thornton are also required to select a sample of cases from errors identified from previous audits to see if the same errors are replicated. This is known as Cumulative Assurance Knowledge and Experience - ‘CAKE’ for short.
For the 2022/23 housing benefit subsidy claim, Grant Thornton selected 142 cases for testing and no errors were identified. Testing of the 142 cases included CAKE testing of errors identified in previous audits:
- Incorrect calculation of earned income for rent allowances. - Incorrect input of new state pension for rent allowances.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 171 KB | Download |
PDF |
Housing Benefit Subsidy Claim 2022/23Report | 133 KB | DownloadRead as text |
Follow Audit Committee at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | Council’s Performance Management Framework - Annual UpdateRESOLVED Audit Committee reviewed and noted the report and asked for a more detailed presentation of the planning and... | Noted | Open |
| 20 Jul 2026 | Annual Report on Internal AuditRESOLVED Audit Committee: Noted the work of Internal Audit for 2025/26, detailed within the report, including the Hea... | Noted | Open |
| 20 Jul 2026 | Draft Annual Governance Statement for 2025-26RESOLVED Audit Committee endorsed the Council’s Annual Governance Statement. | Decided | Open |
| 20 Jul 2026 | Work ProgrammeRESOLVED Audit Committee approved the updated Work Programme, and noted the suggestions made in discussion. | Approved | Open |
| 17 Mar 2026 | 2025/26 Accounting PoliciesRESOLVED Audit Committee noted and considered the proposed Accounting Policies, accounting estimates and significant ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.