(i) That the rephasing of the corporate capital programme into 2025/26 as set out in the report and Appendix A to the report be approved; (ii) That the revised corporate capital programme for 2024/25, after rephasing, as detailed in Appendix A to the report be approved; (iii) That the HRA capital programme for 2024/25, after capital programme proposals detailed in paragraphs 3.4 and Appendix A of the report be approved; (iv) That the additional borrowing of £550,000 for the Solihull Town Centre Heat Network project as set out at paragraphs 3.7 – 3.9 of the report be approved; and (v) That the passporting of Government capital allocations for 2025/26 to individual Cabinet Portfolios for project allocation be approved.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1To outline the current financial position for the 2024/25 corporate capital programme.
1.2To seek approval to rephase capital budgets into 2025/26 as detailed in Appendix A.
1.3To seek approval for the revised capital programme for 2024/25, after rephasing, as detailed in Appendix A.
1.4To seek approval for the Housing Revenue Account (HRA) capital programme after revisions for 2024/25, detailed in paragraph 3.4 and Appendix A.
1.5To seek approval for the additional borrowing of £550,000 for the Solihull Town Centre Heat Network project as set out at paragraphs 3.7 – 3.9.
1.6To approve the passporting of Government capital allocations for 2025/26 to individual cabinet portfolios for project allocation. 2. Decision(s) Recommended
Approve the rephasing of the corporate capital programme into 2025/26 as set out in the report and Appendix A.
Approve the revised corporate capital programme for 2024/25, after rephasing, as detailed in Appendix A.
Approve the HRA capital programme for 2024/25, after capital programme proposals detailed in paragraphs 3.4 and Appendix A.
Approve the additional borrowing of £550,000 for the Solihull Town Centre Heat Network project as set out at paragraphs 3.7 – 3.9.
Approve the passporting of Government capital allocations for 2025/26 to individual cabinet portfolios for project allocation.
3. Matters for Consideration
Through the annual Capital Strategy document, Members approve a rolling 10 year capital programme which is reviewed on a regular basis to ensure expenditure is sustainable in terms of available funding. This funding currently consists of a combination of grant allocations from central government; prudential borrowing within Council approved limits; specific capital grants and capital receipts from the sale of Council assets.
Rephasing of 2024/25 Programme
The current capital programme for 2024/25 is £96.830 million and includes General Fund (£49.185 million) and HRA (£47.645 million). Over recent months, officers in the Financial Operations Division have been working with project managers to identify projects which will no longer complete during 2024/25 and therefore require rephasing into future years. The required rephasing totals £26.595 million and is analysed by Cabinet Portfolio in paragraph 3.6, Table 1, whilst individual projects are detailed at Appendix A.
Cabinet Members are asked to approve the rephasing of these budgets into future years as summarised in paragraph 3.6, Table 1 and detailed in Appendix A.
Programme Approvals in 2024/25 HRA Capital Programme
Appendix A includes provision for the release of £9.242 million from the HRA Capital Programme. This is for budgets previously allocated for new build housing developments, where works are not expected to commence until at least 2026/27. The individual schemes and their associated budgets will be presented to a future Cabinet meeting for approval once further details, about a viable scheme, become available.
Capital Programme 2024/25
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.