2025/26 Quarter 3 Treasury Management Monitoring Report

Noted Finance 3 papers

AI summarySolihull Audit Committee noted Q3 2025/26 treasury management activities, with £108.307 million of internal borrowing forecast by 31 March 2026 and £20-25 million of new external borrowing planned for the year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo amendments to strategy proposed
Money£108.307m internal borrowing21.0% of capital financing requirement
What happens nextExternal borrowing in Q4Likely needed in February and March 2026
Who it affectsCouncil finances and capital schemesHeat networks project and capital programme

What was decided

The Audit Committee noted the Treasury Management activities for quarter 3 of 2025/26, as required by the CIPFA Code of Practice. Report P3, P5, P6

No amendments to the Council's Treasury Management Strategy are proposed as a result of the report. Report P30

Why

The CIPFA Code of Practice requires members to be regularly updated on Treasury Management activities and risks, and a quarterly report is therefore presented. Report P5, P6

During the year to date the Council has operated within the treasury and prudential indicators set out in its Treasury Management Strategy Statement and complied with its Treasury Management Practices. Report P29

What happens next

The Director of Resources, under delegated powers, will consider the most appropriate form of any new borrowing depending on prevailing interest rates. Report P11

External borrowing is now expected mainly in February and March 2026 to cover in-year capital requirements. Report P25

Officers will continue to monitor the internal borrowing position against revenue budget pressures, use of reserves, and the Dedicated Schools Grant deficit. Report P9

The money

  • £108.307 million Forecast internal borrowing by 31 March 2026, equal to 21.0% of the capital financing requirement Report P8
  • £20-25 million Revised forecast of new external borrowing in 2025/26 Report P8
  • £30-40 million Previous quarter 2 estimate of new external borrowing in 2025/26 Report P8
  • £24.628 million 2025/26 capital schemes rephased or removed by Full Cabinet in December 2025 Report P8
  • £11.686 million Portion of rephased or removed schemes that was to be funded from external borrowing Report P8
  • £4.589 million Borrowed from the National Wealth Fund in the first half of 2025/26 for the heat networks project Report P10
  • £28.067 million Dedicated Schools Grant deficit as at 31 March 2025 Report P9
  • £31.490 million Investments held at 31 December 2025, all in liquid or short-term instruments under 1 month Report P24
  • 4.00% Initial budgeted in-house investment return for 2025/26 Report P22
  • 3.95%-4% Forecast average rate of return on in-house investments across 2025/26 Report P22
  • 4.103% Average SONIA rate for 2025/26 to date, the Council's benchmark Report P22
  • 3.726% SONIA closing rate at 31 December 2025 Report P22
  • £162 Notional cash exposure to default on the investment portfolio Report P20
  • 0.00051% Chance of default against the entire investment portfolio Report P20

Options considered

  • Rejected: Continue internal borrowing as the main approach for 2025/26. No longer possible due to revenue budget pressures, use of reserves to support the MTFS, and the £28.067m DSG deficit, so new external borrowing is required. Report P9
  • Chosen: Take new external borrowing during 2025/26. Required to meet the in-year capital financing requirement after internal borrowing capacity has been reached. Report P9, P8

Implications

  • Financial: Internal borrowing forecast at £108.307 million by 31 March 2026, with £20-25 million of new external borrowing planned for the year. Report P8
  • Financial: Cabinet in December 2025 rephased or removed £24.628 million of 2025/26 capital schemes, including £11.686 million that would have been funded by external borrowing. Report P8
  • Financial: Full Cabinet approved rephasing or removal of £24.628 million of 2025/26 capital schemes in December 2025, of which £11.686 million was to be funded from external borrowing. Report P8
  • Risk: Overall default risk on the investment portfolio is 0.00051%, with a notional cash exposure to default of £162; stringent counterparty credit criteria continue to be applied. Report P20, P19
  • Risk: The Council maintains a low risk appetite for treasury activities, in line with MHCLG guidance that security of principal is the primary concern. Report P51
  • Legal: It is a statutory duty for the Council to determine and keep under review the affordable borrowing limits; the Council has operated within the approved prudential and treasury indicators. Report P28, P29
  • Equalities: There are no direct equality or diversity implications from this report. Report P52
  • Other: The report sets out forecast rates for money market investment, PWLB borrowing, and Bank Rate from March 2026 to March 2029, with a forecast Bank Rate of 3.25% by Q4 2026. Report P15, P16

Who and where

  • Solihull Metropolitan Borough Council as borrower and investor Report P8, P24
  • Capital scheme delivery, including the heat networks project funded by the £4.589 million National Wealth Fund loan Report P10
  • Schools, affected by the £28.067 million Dedicated Schools Grant deficit as at 31 March 2025 Report P9
  • Counterparty banks and financial institutions with which the Council places investments Report P19, P20

Timeline

  • 31 March 2025: Dedicated Schools Grant deficit stood at £28.067 million Report P9
  • 11 August 2025: Last interest rate forecast update was undertaken Report P15
  • December 2025: Full Cabinet approved rephasing or removal of £24.628 million of 2025/26 capital schemes Report P8
  • 18 December 2025: Bank of England Monetary Policy Committee reduced Bank Rate from 4% to 3.75% Report P15
  • 31 December 2025: Investments of £31.490 million held, all in liquid or short-term instruments under 1 month Report P24
  • February and March 2026: External borrowing expected to be taken to cover in-year capital financing requirements Report P25
  • 31 March 2026: Internal borrowing forecast at £108.307 million (21.0% of the capital financing requirement) Report P8

Plain English for the jargon

  • CIPFA Code of Practice: The Chartered Institute of Public Finance and Accountancy's Code of Practice for Treasury Management, which sets the framework members must follow.
  • Internal borrowing: Using the Council's own cash balances and reserves instead of taking new external loans to fund capital spending.
  • External borrowing: New loans taken from sources such as the PWLB or the National Wealth Fund to finance capital spending.
  • PWLB: Public Works Loan Board, a government body that lends to local authorities.
  • SONIA: Sterling Overnight Interbank Average, the benchmark rate used by the Council for investment returns.
  • DSG: Dedicated Schools Grant, the ring-fenced government funding for schools.
  • MTFS: Medium Term Financial Strategy, the Council's multi-year financial planning document.
  • MUFG Corporate Markets: The Council's external treasury advisers, whose forecasts are used in the report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

RESOLVED Audit Committee noted the Treasury Management activities for quarter 3 of 2025/26.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Audit Committee

Executive summary

To provide a monitoring report on the 2025/26 Treasury Management activities for quarter 3.

2. Decision(s) Recommended

The Committee is asked to note the Treasury Management activities for quarter 3 of 2025/26.

3. Matters for Consideration

The Treasury Management Practices introduced by the CIPFA Code of Practice and Cross-Sectoral Guidance notes and adopted by the Council require that members are regularly updated on Treasury Management activities and risks.

In accordance with the Code, a quarterly report on Treasury Management activities is presented to members.

Debt Activity 2025/26

The Council is currently forecast to be internally borrowed by £108.307 million (21.0% of the Council’s forecast overall capital financing requirement) by 31 March 2026. The current forecast assumes that the Council will externally borrow between £20-25 million during 2025/26 to cover the new capital borrowing requirement arising in year. This has reduced from the previous estimate of £30-40 million in quarter 2 mainly inline with reductions in capital expenditure forecasts (Full cabinet approved, in December 2025, the rephasing/removal of £24.628 million of 2025/26 capital schemes, £11.686 million of which was to be funded from external borrowing).

Internal borrowing is used to address investment counterparty risk and the cost of carry (where the cost of borrowing exceeds the investment rate). The use of internal borrowing has been a beneficial strategy for a number of years and has helped deliver a number of savings for the Council. However, with the current pressure seen in the Council’s revenue budget, the in creasing need to use reserves to support the overall MTFS, and the need to support the Dedicated Schools Grant (DSG) deficit (£28.067 million as at 31 March 2025), means the extension of this policy through 2025/26 will not be possible and therefore new external borrowing is required to meet in year capital financing requirements. The overall internal borrowing position is being carefully monitored against these pressures and the overall Council financial position.

During the 1st half of 2025/26 the Council has borrowed £4.589 million from the National Wealth Fund to support the Council’s heat networks project. This borrowing was the second half of the committed borrowing to support the overall heat network project (with the 1st half being taken in 2024/25), no other borrowing or debt rescheduling has been undertaken.

For any borrowing that is required the Director of Resources, under delegated powers, will consider the most appropriate form of borrowing depending on the prevailing interest rates at the time.

Economic Forecast

Forecast rates for money market investment and long-term borrowing are given in the table at 3.8. Officers continually review these forecasts with reference to activities in the market and will continue to pursue the optimum position for both debt and investments in accordance with the Council’s Treasury Management Strategy.

Medium-Term Rate Estimates – December 2025 (Source: MUFG Corporate Markets)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Quarter 3 Treasury Management Monitoring ReportReport 262 KB DownloadRead as text
PDF
Appendix AAppendix A 116 KB Download
PDF
Appendix BAppendix B 171 KB Download

At this meeting

Whole meeting

Who was there

6 of 8 attended
TH
Tammy HollisOfficer, expected
TB
Mr Tony Beirne Independent Co-opted memberChairman, present
MB
Mr Michael Burnett Independent Co-opted MemberCommittee Member, present
DP
Mr David Page Independent Co-opted MemberCommittee Member, present
LK
Councillor Leslie KayeCommittee Member, present
RL
Councillor Richard LongCommittee Member, present
MW
Mark WillsOfficer, expected
MM
Councillor Max McLoughlinCommittee Member, present

On this subject at Solihull

Search all
  1. 2025/26 Quarter 3 Treasury Management Monitoring ReportThis decision
  2. 2023/24 Quarter 3 Treasury Management Monitoring ReportNoted
  3. 2023/24 Quarter Treasury Management ReportNoted
  4. 2022/23 Quarter 3 Treasury Management Monitoring ReportNoted
  5. 2022/23 Quarter 1 Treasury Management Monitoring ReportNoted
  6. 2021/22 Quarter 3 Treasury Management Monitoring ReportNoted

More from Solihull Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Council’s Performance Management Framework - Annual UpdateRESOLVED Audit Committee reviewed and noted the report and asked for a more detailed presentation of the planning and... Noted Open
20 Jul 2026 Annual Report on Internal AuditRESOLVED Audit Committee: Noted the work of Internal Audit for 2025/26, detailed within the report, including the Hea... Noted Open
20 Jul 2026 Draft Annual Governance Statement for 2025-26RESOLVED Audit Committee endorsed the Council’s Annual Governance Statement. Decided Open
20 Jul 2026 Work ProgrammeRESOLVED Audit Committee approved the updated Work Programme, and noted the suggestions made in discussion. Approved Open
17 Mar 2026 2025/26 Accounting PoliciesRESOLVED Audit Committee noted and considered the proposed Accounting Policies, accounting estimates and significant ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies